A new intrusive structural investigation of the Aylesbury Estate has found no evidence that its oldest low-rise Large Panel System blocks were strengthened against disproportionate collapse, while concluding that immediate decanting or strengthening is disproportionate where they remain occupied for only another three to five years.
The finding effectively extends an earlier Arup position that the affected Phase 1 blocks should be strengthened or vacated by around 2025. Conisbee's 26 June 2026 appraisal says its assessment, carried out after that date, "in essence constitutes an extension to the deadline" because the current condition remains broadly consistent with Arup's 2020 assessment.
The report was released by Southwark Council as part of the Aylesbury Estate renewal summit held on 29 October. Southwark is reconsidering the future of the estate after deciding earlier this year to end its long-running development partnership with Notting Hill Genesis once three existing sites are completed.
The technical evidence gives a more detailed picture than a simple choice between safe buildings and demolition. Conisbee found the Phase 1 low-rise blocks investigated to be generally in good repair, with good workmanship and no significant visible structural distress, but it found no evidence that they had received the post-Ronan Point strengthening needed to address disproportionate collapse risk.
Aylesbury Estate in Southwark, where new structural investigations have assessed the condition and short-term retention of older Large Panel System blocks. Illustration: London Construction Magazine.
Breakouts found generally good workmanship
Southwark appointed Conisbee to assess the four- and five-storey LPS blocks and review the recommendations from Arup's 2020 structural assessment.
The original investigation programme was intended to cover 20 flats. Delays in commissioning and a shortage of suitable void units reduced the sample to six flats across six blocks: Hambledon, Northchurch, Gayhurst and Missenden. Detailed intrusive breakouts were completed in four flats.
Covermeter surveys were first used to locate reinforcing steel and structural connections within the precast walls and floors. Targeted opening-up then examined wall-to-wall connections, levelling bolts, wall-to-floor connections, floor joints and reinforcement details. The approach is the same investigation sequence examined in LCM's earlier analysis of structural investigation work on ageing London buildings: scan first, then open selected locations where the construction detail needs to be physically verified.
Conisbee found typical reinforcement cover of 40mm to 60mm in the wall panels. Carbonation in the wall panels was generally below 5mm, while floor-plank readings ranged up to 30mm with a mean of 10mm. The engineer concluded there was little risk of reinforcement corrosion from carbonation in the areas tested. Maximum chloride content was recorded at 0.04% by weight of cement.
The detailed breakouts found the structural connections and workmanship generally consistent and to a good standard. Localised loose or voided dry pack, areas of low reinforcement cover and slight surface corrosion were recorded, but Conisbee classified these as minor defects that had not compromised the integrity of the as-built structure.
Floor planks had 75mm to 90mm bearing onto the walls. Insitu stitch concrete was described as well compacted, with pairs of 18mm square lacer bars identified at the connections and loop or continuity reinforcement found tying the precast elements together.
One less obvious construction detail also emerged from the investigation. Internal non-loadbearing partitions within the flats were identified as precast reinforced RAAC panels, typically 600mm wide and 75mm thick. These partitions are separate from the loadbearing Jespersen LPS wall and floor system assessed for disproportionate collapse.
Phase 1 strengthening was not found
The main structural issue is historical. Parts of the first Aylesbury construction phase were already built when Ronan Point collapsed in May 1968, before later government requirements changed the treatment of large-panel buildings.
Earlier investigations carried out by Conisbee in 2005 found no evidence of retrospective strengthening in Phase 1 low-rise blocks. Arup subsequently concluded that it was highly likely the Phase 1 four- and five-storey buildings had not been strengthened against disproportionate collapse.
The 2026 investigation found no evidence of retrospective strengthening in any of the Phase 1 blocks examined, which Conisbee says corroborates the earlier conclusion. Its recommendation is that priority should be given to either vacating or strengthening these blocks through the estate masterplan.
The position is different for later low-rise construction. Conisbee accepts the evidence that Phase 2 and Phase 3 four- and five-storey blocks were built or strengthened to comply with post-Ronan Point Ministry of Housing and Local Government requirements and says no further intrusive investigation is necessary for those buildings on that issue.
Three-to-five-year occupation window
For Phase 1 blocks remaining occupied in the short term, Conisbee says the need for immediate decanting or strengthening is disproportionate to the inherent risk where retention is limited to around three to five years.
The engineer warns against repeatedly extending that period. It says the probability of a serious incident increases with time and recommends that strengthening should be prioritised if any affected block is retained into the medium or long term, which it defines as more than five years.
Interim controls are unusually specific. Conisbee recommends permanent signage prohibiting potential explosion sources such as butane and LPG cylinders, petrol and paraffin within flats. It also raises the storage of multiple large lithium batteries used in e-bikes and e-scooters as a possible accidental-load concern where several batteries could fail in a confined space.
Vehicle protection measures such as bollards should continue to be reviewed, while each retained low-rise block should undergo at least annual reassessment against the accidental-load factors in BRE Report 511 and for changes in its general structural condition.
Wendover refurbishment priced at £28.8m
The engineering findings sit alongside a separate Potter Raper feasibility estimate for 1-240 Wendover. That June 2025 cost plan priced full decommissioning and demolition at £6.76m and full recommissioning and refurbishment at £28.81m.
The refurbishment estimate includes £9.62m for internal works to the flats, £3.46m for windows and external doors, £2.12m for fire-risk-assessment works and associated fire measures, £1.98m for building services, £803,125 for the external façade, walls and structure, £772,000 for access scaffolding and £452,500 for asbestos surveys and removal allowances.
Potter Raper's risk schedule contains a separate £100,000 allowance for additional structural works and repairs. The £28.81m figure is therefore a cost plan for bringing the 240 homes back to a liveable residential standard, including major fabric, MEP and fire works, with structural strengthening still dependent on the eventual engineering scope.
That creates an important distinction within Southwark's evidence base. Potter Raper's April 2025 strategy report describes the estate's LPS blocks as being at the end of their structural life and unsuitable for retrofit, while the later Conisbee investigation separates the structural position by construction phase and finds the inspected buildings generally in good physical condition.
For Southwark, the next decision is therefore tied to programme as much as condition. A short retention period for the unstrengthened Phase 1 blocks remains within Conisbee's current risk assessment; keeping them beyond about five years would move structural strengthening to the front of the engineering programme.