Cladding Bill Brings Jail Terms as 2,111 Buildings Sit Untouched

The Building Safety (Remediation of Unsafe Cladding etc) Bill cleared its second reading in the Commons on 27 October 2026, carrying a criminal offence of up to two years in prison or a fine of up to £500,000 for a landlord who deliberately fails to remediate unsafe cladding. The day before, the government's own data showed that remediation has not started on 2,111 of the 4,732 monitored buildings over 11 metres with unsafe cladding in England, 45% of the total.

The Bill was introduced on 14 October 2026 and has now been committed to a Public Bill Committee. Line-by-line scrutiny begins on 12 November 2026, and the committee's proceedings are due to conclude by 8 December 2026, the same date set as the deadline for written evidence submitted to the Commons Scrutiny Unit.

Cladding remediation works on a residential block, with sections of the external wall system removed and scaffolding in place. Illustration: London Construction Magazine.

A statutory duty to remediate

The Bill creates a duty on the "responsible entity", usually the freeholder or principal accountable person, to assess external wall fire safety risk, put in place any interim measures an assessor recommends, and remediate "as soon as reasonably practicable". The duty covers residential buildings in England with two or more dwellings, completed before 28 June 2022, that are at least 11 metres high or have five or more storeys. Accompanying guidance expects PAS 9980 to become the mandated methodology for the fire risk assessment of external walls behind that duty.

Failing to carry out the assessment within the period set is itself an offence, carrying up to two years in prison or a fine of up to £14,000, with a further penalty for each day the failure continues. Deliberately failing to remediate without reasonable excuse carries up to two years or the £500,000 fine. Obstructing an assessment or remediation work carries up to £40,000 for an individual, or up to 5% of a company's worldwide group revenue. Directors can be prosecuted personally where a failure results from their consent, connivance or neglect, and the Bill lets local housing authorities apply to a tribunal for a remediation management order to take over works a responsible entity will not carry out.

A register for medium-rise buildings

Clause 14 creates a mandatory register for residential buildings between 11 and 18 metres, closing a gap left by the Building Safety Act 2022, which required registration only at 18 metres and above. The principal accountable person for a covered building will have six months from commencement to register it with the Building Safety Regulator, supplying the cladding material and manufacturer data, a current PAS 9980 assessment, remediation timelines and funding, and the approximate number of occupied units. Failing to register, or giving false information, is a criminal offence carrying an uncapped fine or up to two years in prison for a director.

Manufacturers face a lower bar

The Bill amends section 149 of the Building Safety Act 2022 so that liability turns on a product being "unsafe" rather than "defective", and on misleading conduct rather than a misleading statement. A product need only have made more than a trivial contribution to a building being unsafe, rather than being the main or sole cause, and the amendments extend to Scotland and Northern Ireland. Courts will be able to order disclosure of a manufacturer's product information and issue Building Liability Orders with no statutory time limit, and Corporate Redress Orders that reach a parent company where a subsidiary has been used to avoid a remediation debt. Crest Nicholson's dispute with Ardmore over £15.7m in building safety costs, reported earlier this year by LCM, shows the kind of recovery claim these provisions are aimed at.

The backlog the Bill has to close

The Ministry of Housing, Communities and Local Government published its latest monthly data release on 28 October 2026. Across five tracking frameworks, it is monitoring 4,732 buildings over 11 metres with unsafe cladding: 722 have remediation underway, about 1,900 are complete, and 2,111, 45% of the total, have not started. Local authorities have taken or are pursuing Housing Act 2004 enforcement action against 942 of these buildings, up from 929 a month earlier.

Progress is uneven by height and by who is paying. Medium-rise buildings between 11 and 18 metres, the same band the Bill's new register targets, have started or finished work on only 47% of cases, against 63% for buildings over 18 metres. The Developer Remediation Contract, signed by 53 housebuilders and covering 2,682 buildings, has not started work on 1,266 of them, 47%, and 857 of those have no remediation plan in place at all. Just over half the signatories met the contract's interim target of starting or completing work on 80% of their buildings by July 2026. By contrast, the ACM programme set up after Grenfell, covering 516 buildings over 18 metres with the same cladding type, has 503 started or complete and only 13 not started.

Programme Buildings monitored Not started
ACM (Grenfell-style, 18m+)51613 (3%)
Developer remediation contract2,6821,266 (47%)
Cladding Safety Scheme1,5241,072 (70%)
All programmes (de-duplicated)4,7322,111 (45%)

Developers who missed the July target cited planning and Gateway 2 delays, disputes with contractors and product manufacturers over who pays, and shortages of certified fire engineers and remediation contractors. LCM's own coverage of the Building Safety Regulator's enforcement unit and Gateway 2 approvals reaching 87% has tracked the same capacity constraints on the new-build side. A stalled case such as Archway Heights, where the regulator is still seeking further evidence before remediation can proceed, shows how an individual building can sit in the "not started" column for reasons a single national figure does not capture.

Key takeaway: the Bill's criminal duty to remediate lands hardest on medium-rise buildings between 11 and 18 metres, which is exactly the band the official data shows furthest behind, at 47% started or complete against 63% for taller blocks.

What happens next

The Public Bill Committee's line-by-line scrutiny starts on 12 November 2026. Written submissions go to the Scrutiny Unit at scrutiny@parliament.uk in Word format, with the submitter's identity stated at the start, paragraphs numbered for reference in debate, and any request for anonymity made explicitly. The deadline is 5pm on 8 December 2026, and the Commons has said evidence submitted once the committee has voted on a clause will not be revisited for that clause.

Mihai Chelmus
Expert Verification & Authorship
Founder & Author, London Construction Magazine | Construction Testing & Investigation Specialist