Every UK respondent to Turner & Townsend's 2026 construction market survey reported a shortage of qualified mechanical, electrical and plumbing workers, with fast-growing sectors including data centres increasing demand for specialist trades faster than the workforce is adapting.
The pressure is becoming visible across the wider data-centre market. Turner & Townsend's separate 2026 data-centre study found 81% of respondents described skilled labour in their region as moderately or highly constrained, while data centres were the most constrained construction subsector for contractor capacity. In the UK and Europe, only 19% of respondents regarded contractor capacity as sufficient or better.
This is happening as European capacity expands at scale. Savills currently tracks about 10,990MW of live data centres, another 2,449MW under construction, 11,191MW committed and more than 39,000MW at earlier planning stages. Not all of that pipeline will be built, but the work already under construction is competing for electricians, commissioning engineers, controls specialists and other MEP trades across several countries.
The labour question has now been joined by a safety and welfare question. A five-month investigation published by the Guardian and Investigate Europe on 30 October reported serious electrical injuries, disputed working conditions, wage complaints, poor accommodation and difficulties faced by some migrant workers in raising concerns on European data-centre projects. The individual allegations vary in evidential status, and some have not resulted in formal findings of wrongdoing.
For UK construction, the evidence supports a narrower but important conclusion: data-centre delivery combines unusually heavy MEP demand, high-energy electrical systems, phased energisation, international specialist labour and multi-tier subcontracting at a time when the available technical workforce is already constrained.
Data-centre construction combines heavy MEP demand, electrical infrastructure and specialist labour at a time of growing skills shortages. Illustration: London Construction Magazine
MEP labour is becoming the delivery constraint
Turner & Townsend's 2026 UK market intelligence puts the labour problem plainly: 100% of its UK respondents cited shortages of qualified MEP workers. Its data-centre construction research identifies MEP trades as the skills most in demand and says electrical expertise is becoming still more important as projects incorporate grid upgrades and on-site generation.
That fits London's physical pipeline. LCM's London Data Centre Pipeline 2027 identified active and planned schemes across Docklands, Brent Cross, Hayes, Park Royal and the wider West London market, with contractors increasingly following the power-critical path as well as the building programme.
Pure DC's Brent Cross campus is one example. The operator says its LON01 campus has 90MW of secured capacity, with a 20MW building operating and a 70MW second building under construction. Glencar began piling for the latest cold-shell phase in September 2026; LCM's Q3 construction review recorded foundations, underground services, structural frame, slab, cores, envelope and roofing within that package.
The shell is only part of the workload. A data centre also needs transformers, switchgear, generators, UPS systems, extensive power distribution, cooling, controls, fire systems, security and testing. Many of the hardest-to-source people enter the programme when the building starts moving from construction into energisation and commissioning.
Two London fatalities sit inside the recent build-out
Two fatal incidents have been publicly recorded on London data-centre or directly related infrastructure construction during 2024 and 2025.
On 11 February 2024, a 28-year-old worker died following an incident on a London data-centre-related electrical infrastructure project. Contemporary reporting said the incident involved an aerial work platform. HSE confirmed that it was investigating alongside the Metropolitan Police.
On 23 August 2025, a 36-year-old worker died while working on a London data-centre construction project. The HSE fatality record lists the incident under construction of commercial buildings and records that the worker was self-employed and struck by a moving vehicle.
Those cases are serious, but two incidents do not establish a data-centre accident rate. HSE recorded 25 worker fatalities across UK construction in 2025/26, and its published statistics do not separate data-centre construction into its own injury-rate category. There is therefore no sound statistical basis at present for saying that data-centre construction is more dangerous than other construction sectors.
The construction-to-commissioning boundary needs control
Electrical exposure is one area where the characteristics of a data centre are different from an ordinary commercial building. High-voltage infrastructure, transformers, switchgear, UPS equipment, generators and increasingly on-site generation can be introduced progressively while other parts of a campus remain under construction.
HSE's HSG141 guidance on electrical safety on construction sites covers the installation and use of temporary electrical distribution and the commissioning and use of new fixed electrical systems. It says systems should be isolated so they cannot be inadvertently re-energised, while high-voltage temporary systems, typically at 11kV, require operational safety rules appropriate to high-voltage work.
For a data-centre team, that creates a management interface between construction and commissioning. One zone may still contain installers and finishing trades while another has moved into testing or controlled energisation. Drawings, permit systems, physical segregation, competence records and responsibility for switching all have to follow the changing electrical status of the building.
LCM has previously examined how power and operational risk are moving deeper into London data-centre supply chains. The same principle applies during construction: electrical infrastructure is not a late-stage service package sitting behind an otherwise complete building. It is part of the project's critical path.
Subcontracting pushes responsibility through several companies
Large European data-centre projects can combine an international client, construction manager or principal contractor, major MEP firms, specialist electrical contractors, commissioning companies and labour suppliers. Workers can also move between countries as posted workers or join projects on short rotations.
The Guardian and Investigate Europe investigation reported examples involving Romanian workers in Belgium and Sweden, including a serious electrical injury during testing, claims over overtime and pay, and complaints about accommodation. The Belgian labour inspectorate closed its investigation into the electrical incident without finding wrongdoing, according to the report.
The commercial structure itself is not evidence of exploitation. It does, however, increase the number of interfaces through which competence, working hours, wages, welfare and safety information have to be controlled. A worker may be employed by one organisation, supplied through another and supervised on a package sitting several contractual levels below the client.
EU rules for posted workers recognise this cross-border structure. Employees temporarily sent to another member state remain employed by their sending company, while mandatory host-country employment conditions apply in specified areas. On large construction projects, payroll, accommodation, supervision and site safety can therefore involve different organisations and different legal jurisdictions.
CDM duties remain with the UK project
For UK projects, a long subcontract chain does not remove the CDM dutyholder structure. HSE states that the principal contractor on a multi-contractor project must plan, manage, monitor and coordinate the construction phase, maintain the construction phase plan, organise cooperation between contractors, consult workers, provide suitable welfare and check the capability of organisations it appoints.
Contractors retain duties for work under their own control, including supervision and checking that workers have the skills, knowledge, training and experience needed for the task. Those duties apply whether the operative is working on a conventional office, an HV substation or a 100MW data-centre campus.
The harder question is how far assurance reaches down the commercial chain. A client may have a labour standard in its supplier code, the principal contractor may audit a Tier 1 MEP business, and that MEP contractor may use several specialist companies and labour providers beneath it. The quality of the system depends on what is checked at the point where the work is actually being done.
The next constraint is competence, not just headcount
The data-centre labour problem cannot be measured simply by counting vacancies. Turner & Townsend's research points to a shortage of the specialist MEP capability required to build and commission technically dense facilities, while larger AI projects are increasing demand for power infrastructure and electrical expertise.
A project can add labour without adding the authorised people needed to control an energisation sequence, verify isolation, supervise specialist work or carry out integrated testing. As more UK campuses move from planning into physical construction, that distinction will become increasingly important to programmes built around scarce HV, controls and commissioning capability.
London already has large data-centre packages on site and a much bigger proposed pipeline behind them. The evidence so far does not show a uniquely unsafe construction sector. It does show a sector expanding into a constrained specialist labour market while concentrating some of its most difficult work at the point where construction, electrical energisation, commissioning and multi-company control meet.