Why construction has stopped at 90 Abbey Wood Road

For several months, residents walking past 90 Abbey Wood Road have noticed the same puzzling sight: a completed concrete frame, a crane towering overhead and no signs of ongoing work. 
 
Located just metres from Abbey Wood Station, the site was once hailed as one of the area’s most strategic mixed-use developments. Today, however, the structure stands in a paused state, raising questions among locals and construction professionals alike.

Image © London Construction Magazine: A wide view of the unfinished development at 90 Abbey Wood Road, with the static tower crane overlooking the concrete frame.
 
From Post Office to a New Vision for Abbey Wood

The site formerly housed the Abbey Wood Post Office and Royal Mail sorting depot, a 1970s building vacated in 2019. In 2020, planning permission (19/1081/F) was granted for a much-anticipated redevelopment:

 30 new homes across a part-4 / part-5-storey building
 A mixed-use ground floor with flexible commercial units
 A design meant to complement the new Elizabeth line-driven regeneration of Abbey Wood

Early construction activity, including crane installation and initial ground and frame works, signalled positive momentum as recently as early 2025.
 
Image © London Construction Magazine: A street-level view of the unfinished development at 90 Abbey Wood Road, showing the bare concrete frame and stationary tower crane above.

But for Months Now — Nothing Has Moved

Despite the promising start, the site now appears entirely inactive:

 No operatives on site
 No fit-out, façade installation, or envelope works underway
 Crane static and unused
 No visible plant movement or material deliveries
 Hoarding unchanged for months

For a project at such a strategic commuter location, the prolonged inactivity is unusual. While pauses can occur for many reasons (programme changes, design revisions, funding milestones, contractor changes, or technical constraints) the silence on this particular scheme has become noticeable.

A Structure Frozen at Shell Stage

Today the building stands as a bare concrete frame, open to the elements. This stage typically precedes:

 External façade installation
 Window and glazing packages
 MEP first-fix works
 Internal layout construction
 Weatherproofing and envelope completion

Yet none of these phases appear to have begun. For surrounding residents, the static crane and dormant frame have become a visual reminder of a project that once promised much but has yet to move forward.

Image © London Construction Magazine: The idle crane and unfinished concrete frame of 90 Abbey Wood Road seen across the rooftops of Abbey Wood.

A Challenging Site Beneath the Surface

Planning documents reveal several technical constraints that may have complicated progress: 
 
Flood Zone Classification

Much of the site falls within Flood Zone 3, triggering several engineering requirements:

 Elevated finished floor levels
 Restrictions on basements
 Surface water management conditions
 Drainage resilience measures

Such constraints can add complexity to foundation design, programme planning and approval cycles.
 
Access & Logistics Constraints

The Construction Management Plan (CMP) highlights:

 Restricted lorry movements near the station
 Tight residential roads
 Limited lay-by and loading areas
 Need for coordinated routing for HGVs

Any changes to logistics planning or contractor mobilisation could cause delays.
 
Potential Contractor or Delivery Changes

London’s construction market has seen frequent shifts in contractors, supply chains and funding conditions, all of which can lead to temporary pauses while new arrangements are finalised. There is no public confirmation that this is the case here, but the prolonged stillness suggests a transition or reassessment phase.

A Missed Opportunity — For Now

With the Elizabeth line transforming Abbey Wood into one of Southeast London’s most connected hubs, sites like 90 Abbey Wood Road are critical to delivering much-needed housing and revitalising local high streets. A fully developed mixed-use building here would:

 Strengthen commercial activity near the station
 Support population growth
 Bring new homes into an area with high demand
 Complement wider regeneration efforts

Instead, residents are currently left with a half-finished frame and an unanswered question: when will work resume?

What Comes Next?

Royal Greenwich’s planning conditions remain active, and the approved scheme still represents a positive opportunity for the area. If activity resumes, the next visible stages would include:

 External cladding and façade installation
 Window and door packages
 Removal of the crane once the superstructure is complete
 Internal partitioning, MEP, and first-fix works
 Landscaping and public-realm improvements along Abbey Wood Road

Until then, the site remains in a state of limbo, a reminder of the unpredictability inherent in London’s development pipeline.

90 Abbey Wood Road is a project with strong potential, a prime location, and a previously active construction programme. But as of today, the structure sits silent. Whether this pause is temporary or indicative of deeper challenges remains unclear, but one thing is certain: Abbey Wood residents, commuters, and the wider construction community will be watching closely to see when momentum returns.