Hams Hall Battery Project Secures Financing as Phase 1 Nears Operation

BW ESS has secured debt financing from OCBC, Rabobank and Société Générale for the Hams Hall battery energy storage system in North Warwickshire as the project's first 350MW / 1,243MWh phase moves through final commissioning towards commercial operation.

The financing follows the successful energisation of both 400kV 220MVA supergrid transformers on 30 September, connecting the project to the National Grid transmission system. BW ESS continues to target commercial operation in Q4 2026, so Hams Hall has reached a substantially more advanced stage than an early development or construction announcement but has not yet been confirmed as commercially operational.

Under the financing announced by BW ESS on 22 October, the three international lenders will provide the facility in equal proportions, with Rabobank acting as Facility Agent. The amount of debt has not been disclosed and the transaction is expected to close at the project's Commercial Operations Date rather than during the remaining commissioning period.

The Hams Hall battery energy storage system in North Warwickshire during construction, with battery blocks installed across the site ahead of commercial operation. Image: BW ESS.

350MW First Phase Approaches Commercial Operation

Hams Hall has been under physical construction since October 2024 on a site close to the existing Hams Hall 400kV substation. BW ESS describes the ultimate project as a 400MW / 1,424MWh asset, but its latest financing announcement makes an important distinction between the two delivery phases: the initial installation provides 350MW / 1,243MWh, with a second phase intended to increase capacity by a further 50MW and 181MWh.

The first phase is also covered by a 10-year floor and optimisation agreement with EDF announced in April. BW ESS says the 350MW installation is expected to begin commercial operation during Q4, while the company's main Hams Hall project page continues to classify the wider 400MW / 1,424MWh development as under construction.

That capacity distinction matters because the additional 50MW should not be treated as already operational simply because the site's ultimate configuration is described as 400MW. BW ESS states that the project will rise to 400MW / 1,424MWh following completion of the second phase but has not given a firm commercial-operation date for that expansion in the material published with the financing announcement.

40,000m² Platform and 400kV Infrastructure Already Delivered

The construction story behind the financing is considerably more substantial than the banking announcement alone. Wills Bros' Hams Hall project record describes a 40,000m² engineered platform formed through cut-and-fill ground-improvement earthworks, together with civil and electrical balance-of-plant design and build.

The delivered scope includes 124 battery energy-storage blocks, a new 400kV bay within the National Grid Electricity Transmission compound, a 400/33kV substation building, two switchgear buildings and two control buildings with associated foundations. Wills Bros identifies GDG and Energy-IO within the design and delivery team and lists a £55m budget against its Hams Hall project record.

That £55m figure should not be treated as the total capital cost of the complete Hams Hall development. BW ESS has not disclosed the total development capex or the amount of the new debt facility, so the project budget shown by Wills Bros and the financing announced on 22 October represent different financial measures.

For construction and infrastructure teams, the project's transmission connection is particularly notable. London Construction Magazine has recently examined how substations, high-voltage cabling and grid access are increasingly becoming part of the construction critical path for major developments. Hams Hall provides the reverse side of that problem: a large storage asset deliberately located alongside high-voltage infrastructure and built around a direct 400kV connection.

Transformer Energisation Moves Project Into Commissioning

The clearest evidence of the project's present physical stage came at the end of September. Wills Bros confirmed that both 400kV 220MVA supergrid transformers were energised on 30 September, establishing the live transmission connection to National Grid after almost two years of planning, construction and engineering work.

Wills Bros is EPC contractor for BW ESS, with Energy-IO responsible for the main electrical works. Transformer energisation is a major commissioning milestone, but it is separate from the Commercial Operations Date: the battery systems, controls and wider plant still have to complete the required commissioning and operational-readiness process before the asset can enter full commercial service.

The project also illustrates the scale of construction required as Britain expands transmission and flexibility infrastructure. LCM's recent coverage of the electricity networks investment programme to 2035 examined the growing workload around substations, cable routes, foundations, switchgear and high-voltage systems. Hams Hall brings many of those packages together within a single battery-storage development.

Three Banks Back the Project Ahead of COD

BW ESS said more than 30 lenders participated in the financing process before OCBC, Rabobank and Société Générale were selected. Rabobank will also act as Facility Agent, while the debt transaction is structured to close when Hams Hall reaches commercial operation.

CMS acted as legal adviser to BW ESS and Watson Farley & Williams advised the lenders, with Everoze acting as technical adviser and Modo Energy as market adviser. Hams Hall forms part of BW ESS's Ardenham portfolio, which is co-owned with AIP Management.

The next material project milestone is therefore commercial operation of the 350MW / 1,243MWh first phase. BW ESS continues to target Q4 2026, while the timing of the additional capacity needed to take Hams Hall to its ultimate 400MW / 1,424MWh configuration has not yet been specified in the latest project announcement.