Royal Armouries has moved its Leeds Dock Waterfront programme into detailed design with BDP, while its latest annual report puts the development at about £148m, split between a £114m Tiltyard project and a £34m adjacent hotel.
The project is still ahead of planning and main construction procurement. BDP was selected through a competitive design process and is taking forward work towards a planning application expected in 2027, but the public procurement trail currently shows client-side and professional-services appointments rather than a main works tender.
That makes the current position more specific than the "£100m+" descriptions used around the architect appointment. Royal Armouries' 2024/25 annual report describes a wider £188m investment ambition for its Leeds estate, including about £148m for the Waterfront development. Within that figure, about £114m is allocated to developing the Tiltyard and about £34m to an adjacent hotel development.
BDP's design for the proposed Royal Armouries Waterfront redevelopment at Leeds Dock. The scheme includes a new exhibition and events venue on the existing Tiltyard site, with the wider development moving through detailed design ahead of a planned 2027 planning application. Image: BDP.
The £148m figure is a programme, not a contract
The £188m, £148m, £114m and £34m figures describe different layers of the Royal Armouries investment plan. The £188m is the wider Leeds-estate ambition under its longer-term Armouries 700 capital programme. The £148m sits within that total and combines the Tiltyard redevelopment with the adjacent hotel.
None of those figures is an awarded main construction contract. The annual report calls the £188m figure an "investment ambition", and the £34m hotel is listed separately from the £114m Tiltyard project. The hotel operator, development partner and construction procurement route have yet to appear in the published project material.
Royal Armouries already controls the land. It bought the freehold of its Leeds Dock site for £11.69m in May 2025 using a government-backed loan through the Department for Culture, Media and Sport. The acquisition included waterfront buildings beside the museum and gave the organisation outright ownership of the site for the first time.
Professional team grows before main works procurement
BDP's latest appointment follows its earlier work on the Waterfront masterplan. Its design now centres on a new 3,500 sq m exhibition and events hall on the existing Tiltyard, with the wider development intended to provide more than 8,000 sq m of conference and events accommodation.
The project already has a client-side delivery structure behind that design work. Royal Armouries awarded Mason Clark Associates a £439,215.78 project-management contract in June 2026 through the YORconsult3 framework. The Contracts Finder award covers coordination of the design team and control of the building project through all RIBA stages, including any enabling works and associated Section 278 works.
A further client-side programme role was awarded in September to MBF Advisory. Its 12-month remit covers the venue plan and functional brief, design development, the planning application and management of project stakeholders and funders.
Those appointments show a project team being assembled around design, planning and programme management. Royal Armouries had not published a main works contractor tender, PCSA or preferred-contractor appointment by 31 October 2026.
Museum and events venue will stay open during construction
The delivery conditions will be unusual for the eventual contractor because the existing Royal Armouries Museum, conference facilities and New Dock Hall are intended to stay operational during the redevelopment.
BDP's design appointment puts the new venue on the present Tiltyard, immediately beside the museum at Leeds Dock. The current design work also includes hospitality and immersive visitor uses, with the Waterfront plans intended to improve connections around the riverside site.
Royal Armouries has hosted UKREiiF at Leeds Dock since 2022, bringing large visitor and event movements through the estate alongside normal museum operations. Its 2025 land-acquisition announcement said more than 16,000 people had attended UKREiiF at the site since the event began there.
Detailed construction logistics have not yet been published. The design team will eventually have to resolve contractor access, deliveries, visitor segregation, temporary routes, servicing and event operations around a national museum that the client intends to keep trading throughout the works.
Planning is targeted for 2027
A planning application is expected in 2027. No application has yet been published for the Waterfront redevelopment, and the current design remains in the development and options phase ahead of submission to Leeds City Council.
Funding is also being developed alongside the design. Royal Armouries' annual report records the £188m Leeds programme as an investment ambition, while council work on the Leeds City Fund has examined the Tiltyard as a potential pilot project and the role of future public funding in getting construction under way.
The £11.69m freehold purchase is already complete, giving Royal Armouries control of the site. The next construction milestones are now the 2027 planning application, publication of the delivery and funding structure and, later, the procurement that will put the £114m Tiltyard element in front of contractors.
Expert Verification & Authorship
Founder & Author, London Construction Magazine | Construction Testing & Investigation Specialist