Construction output in Great Britain rose by 0.8% in September 2026, ending four consecutive monthly declines, according to figures published by the Office for National Statistics on 12 November. Infrastructure new work led the improvement with growth of 3.3%, while repair and maintenance also increased. But across the third quarter, total construction output still fell by 0.7%, with private new housing down 4.7% and five of the nine construction sectors recording declines.
The ONS release provides the first monthly increase since April, alongside a modest recovery in new orders. For London's construction market, the distinction is between improved national activity and the contracts actually progressing through the capital. Infrastructure renewals, office redevelopment and selected residential schemes are providing work, while large housing developments continue to face difficult decisions over finance, procurement and construction starts.
Tower crane above 61-65 Holborn Viaduct, a 669-bed student accommodation scheme in the City of London. Photo: London Construction Magazine
Construction output in figures
+0.8%output in September 2026, after four monthly falls
-0.7%output in the third quarter of 2026
-4.7%private new housing in the third quarter
+1.2%new orders in the third quarter, or £107m
Source: Office for National Statistics, Great Britain, published 12 November 2026.
One better month has not reversed the quarterly decline
The September increase came from both parts of the construction industry. New work grew by 0.9% compared with August 2026, while repair and maintenance rose by 0.6%. Infrastructure new work provided the largest positive contribution, growing by 3.3% during the month.
The revised monthly figures also show how little separates the latest improvement from the preceding decline. July output fell by 0.2% and August by 0.5%. LCM's calculation using those revised percentages shows that September's 0.8% rise lifted output approximately 0.1% above its June level, after allowing for the compounding of successive monthly changes. That recovers the losses recorded in July and August, but the earlier declines in May and June still leave the wider market below its previous level.
The quarterly figures are more revealing. Total output fell by 0.7% between Q2 and Q3 2026, with new work contracting by 1.6% and repair and maintenance growing by 0.5%. Separate ONS GDP estimates show construction output was 1.7% lower than in Q3 2025, even as the wider UK economy expanded by 0.7% during the latest quarter.
Construction has therefore recorded a genuine monthly improvement within a market still producing less work than a year earlier. September's figure is also a first estimate. The ONS reported a 76.6% turnover response rate for its construction survey, with further business returns and revised seasonal adjustments capable of changing the published result.
September against the third quarter
| Measure | September 2026, on August | Q3 2026, on Q2 |
|---|---|---|
| All work | +0.8% | -0.7% |
| New work | +0.9% | -1.6% |
| Repair and maintenance | +0.6% | +0.5% |
| Infrastructure new work | +3.3% | Not stated |
| Private new housing | Not stated | -4.7% |
| Private housing repair and maintenance | Not stated | +1.5% |
Source: Office for National Statistics. Seasonally adjusted volume measures for Great Britain; September is a first estimate.
Infrastructure is supplying the strongest positive signal
Infrastructure's 3.3% monthly growth is encouraging for civil engineering contractors, particularly those involved in electricity networks, railways, highways and water infrastructure. The September ONS figure covers Great Britain, however, and cannot be attributed to individual projects or applied directly to London.
London has its own confirmed infrastructure programme. Network Rail's £152m Christmas and New Year engineering investment across Britain includes a 10-day programme at Forest Gate, where six sets of points are scheduled for renewal, alongside track, sleeper and ballast replacement. At Dolphin Junction near Slough, a separate £27.8m project includes 88 pre-constructed track panels, nine overhead-line structures and one kilometre of new overhead wire. These are project and programme investment values attached to established works, not newly awarded contracts created by September's output increase.
Transport for London's procurement records also show smaller, identifiable work packages progressing. As LCM reported on 9 November 2026, Telent Technology Services was selected for a £4,454,727 contract to replace telecommunications and network infrastructure on the London Overground Windrush line. The published award notice schedules contract signature for 23 November and a delivery period from 30 November 2026 to 29 November 2029.
The distinction is important for specialist suppliers. Network Rail's renewal programme has physical work and possession dates, while Telent's award provides an identified contractor and scheduled delivery period but awaits contract signature. Both contribute to the London infrastructure pipeline through different stages of procurement and delivery.
Private housebuilding remains the main weakness
Private new housing output fell by 4.7% in Q3 2026, making it the largest negative contributor to the national quarterly decline. Public new housing was also weak, while private housing repair and maintenance grew by 1.5%. The figures describe different activities: building new homes continued to contract, but spending on work to existing homes was more resilient.
The national housing contraction is consistent with the delivery difficulties already documented in London. In LCM's October investigation into paused housing schemes, analysis of Greater London Authority data found residential starts had fallen from 48,962 in 2022/23 to 21,665 in 2024/25, a decline of 55.8%. The same investigation identified approximately 48,000 permitted homes on sites that had not started at the end of 2024/25.
Those London figures cover an earlier reporting period than the September 2026 ONS release, but they demonstrate the scale of the capital's existing construction-start problem. British Land's Canada Water residential programme and Landsec's Lewisham Shopping Centre redevelopment both experienced pauses in October 2026, with their respective developers identifying difficult market conditions and viability pressures.
Housing construction has nevertheless continued on projects with established delivery programmes. At Wandsworth Mills, Berkeley Group's 36-storey Artisan tower reached its full structural height on 9 November 2026. Concrete-frame contractor Statom Group has completed the tower structure, with 172 homes planned and the first residents expected in 2027.
There is also evidence of future public-sector housing work entering the contractual delivery programme. Tower Hamlets signed a £17m design-and-build contract with Formation Design & Build on 5 October 2026 for 36 council homes and a replacement community centre at Caxton Grove in Bow. The contract-details notice published on 9 November sets a delivery period from 30 March 2027 to 30 December 2028. The agreement establishes a contractual programme for a permitted scheme, with main construction scheduled for 2027.
New orders rise as contractors compete for work
The ONS recorded a 1.2% increase in construction new orders during Q3 2026, equivalent to £107m compared with Q2. The strongest contributions came from public other new work and private commercial construction, suggesting that these markets are beginning to generate additional contract activity even while total construction output remains below its earlier level.
New orders are useful because they record work entering the contractual pipeline ahead of delivery. They are not a measure of how much work contractors have already completed, and individual projects can still move through design, enabling works and procurement before substantial construction starts.
Tender conditions provide another indication of how the market is changing. The BCIS All-in Tender Price Index recorded estimated annual growth of 3.2% in Q3 2026, with tender prices increasing by 0.7% between the second and third quarters. In the same survey, 77% of respondents described contractors as eager to tender, compared with 67% in Q2.
That increased appetite creates an opportunity for clients with finance, design information and procurement arrangements ready to proceed. More competition can improve tender participation and give developers a stronger basis for comparing bids, but the position varies between general building work and specialist packages with limited supply-chain capacity.
Building costs are still rising faster than tender prices
BCIS forecast annual growth of 4.3% in its General Building Cost Index for Q3 2026, against the estimated 3.2% increase in tender prices. LCM's comparison of the two published annual rates gives a 1.1-percentage-point difference between forecast building cost inflation and estimated tender price inflation. BCIS says weak demand is limiting the extent to which contractors can pass rising input costs through to clients.
The Department for Business and Trade's materials statistics, published on 4 November, provide further evidence of the pressure. The all-work construction material price index increased by 7.2% in the 12 months to September 2026, with fabricated structural steel rising by 19.9%, rigid pipes and fittings by 16.9% and reinforcing steel by 16.1%. Ready-mixed concrete fell by 0.5% over the same period, demonstrating why material-specific procurement remains important.
For London quantity surveyors and contractors, the difference between building costs, tender prices and individual materials is commercially relevant. A client may receive competitive bids for a well-developed scheme while structural steel, M&E equipment or electrical infrastructure continues to carry higher input costs. Package pricing, programme certainty and the financial capacity of the proposed supply chain remain central to tender evaluation.
The ONS Construction Output Price Index, which measures prices associated with work being carried out, rose by 3.2% in the 12 months to September 2026. That is a separate measure from the BCIS tender index and the Government's material price statistics. Comparing them helps explain why a contractor may face rising procurement costs without seeing an equivalent increase in the prices accepted by clients.
Four price measures, annual change
| Measure | Annual change | Period | Publisher |
|---|---|---|---|
| All-work material price index | +7.2% | 12 months to September 2026 | Department for Business and Trade |
| General Building Cost Index | +4.3% forecast | Q3 2026 | BCIS |
| All-in Tender Price Index | +3.2% estimated | Q3 2026 | BCIS |
| Construction Output Price Index | +3.2% | 12 months to September 2026 | Office for National Statistics |
Materials in the same period: fabricated structural steel +19.9%, rigid pipes and fittings +16.9%, reinforcing steel +16.1%, ready-mixed concrete -0.5%. The four indices measure different things and are not directly interchangeable.
London's workload depends on which projects move to site
The current London market contains several different types of opportunity. Civil engineering and railway renewals have defined access windows and programmes. Commercial redevelopment can provide work where clients have committed to construction. Public-sector housing contracts are progressing, although their future site starts must be distinguished from the contract award date. Repair, maintenance and building upgrades continue to support contractors working on existing assets.
For developers, the combination of increased tender participation and modest new-orders growth provides a reason to test the market where project viability is already established. For contractors, the more useful test is whether an appointment carries an agreed scope, workable programme and credible route to payment. The latest ONS figures support selective improvement, with the strongest monthly growth in infrastructure and the sharpest quarterly weakness in new housing.
The next ONS construction output release is scheduled for 11 December 2026 and will contain the October figures, alongside any revisions to September's initial 0.8% increase. It will provide the next official test of whether the monthly rebound continued beyond the end of Q3.
London work named in this report
| Project | Client or developer | Stage | Key date |
|---|---|---|---|
| Forest Gate track and points renewal | Network Rail | Scheduled engineering works | 10-day Christmas and New Year programme |
| Windrush line telecommunications, £4,454,727 | Transport for London | Contractor selected: Telent | Signature scheduled 23 November 2026 |
| Artisan tower, Wandsworth Mills, 172 homes | Berkeley Group | Structure topped out | 9 November 2026 |
| Caxton Grove, Bow, £17m, 36 council homes | Tower Hamlets | Contract signed: Formation Design & Build | Delivery 30 March 2027 to 30 December 2028 |
These schemes are at different stages of procurement and delivery. Their values are not additive and are not part of the ONS September figure.
How LCM calculated this
LCM used the revised July 2026 construction output change of -0.2%, the revised August change of -0.5% and the September increase of 0.8% published by the ONS on 12 November 2026. Compounding those three monthly changes gives an increase of approximately 0.095% between June and September, rounded to 0.1%. The calculation uses published percentage changes rounded to one decimal place and does not measure the full loss from May to August.
For the cost comparison, LCM subtracted the BCIS Q3 2026 estimated annual tender price increase of 3.2% from its forecast annual General Building Cost Index increase of 4.3%, producing a difference of 1.1 percentage points. The figures come from separate BCIS publications available by 12 November 2026 and compare rates of growth, not contractor profit margins.