London's construction market produced several important developments during 16–22 November 2026, led by a £2.7bn development arrangement for Thameside West in the Royal Docks, fresh details of the £1.25bn Edmonton energy recovery contract and a gas-main rupture during demolition work in Enfield. The week's reporting also covered specialist construction above Bond Street station, a £30.9m affordable housing appointment in Tower Hamlets and increasing scrutiny of contractors' financial reporting.
The developments are at very different stages. Thameside West is progressing through land agreements and design work, West One is moving from demolition into structural work, and Edmonton is subject to revised contractual terms following substantial cost and programme changes. A separate £500m national retrofit framework is open for bids, providing a procurement opportunity for London contractors and specialist suppliers.
A tower crane rises above buildings near Old Street, London, photographed in November 2026. Photo: London Construction Magazine
The week in figures
£2.705bnEstimated value of the Thameside West development arrangement
£1.25bnRevised Edmonton construction contract price, up from £799m
300People evacuated after the Enfield gas-main rupture
£500mEstimated ceiling of the NEPO233 retrofit framework
The week at a glance
Source: documents linked in each section below. Values are as published and are not all construction contract awards.
Royal Docks: £2.705bn arrangement advances Thameside West
The Greater London Authority published Mayoral Decision MD3542 on 16 November 2026, approving changes to the land arrangements needed to deliver Thameside West, a residential-led regeneration scheme in Newham with consent for at least 5,000 homes. The associated procurement documentation records an estimated £2.705bn value for the long-term development arrangement with Silvertown Homes Limited, backed by UAE developer Arada.
The decision authorises GLA Land and Property Limited to enter a variation of its existing 2019 cooperation agreement and transfer publicly owned land in phases, subject to the transaction's conditions. The proposed direct award is supported by provisions of the Procurement Act 2023 concerning the existing land rights held by Silvertown Homes. The £2.705bn figure relates to the development arrangement; it is not a single main construction contract available for competition.
LCM's review of
Mayoral Decision MD3542 identified an important distinction in the delivery programme. The published timetable identifies demolition in 2028, main construction in 2029, first residential completions in 2032–33 and completion of the wider scheme during the 2040s. Arada is working towards starting the opening phase during 2028, but the formal timetable places the principal construction phase in 2029.
The document also identifies a dependency affecting residential occupation. Under the existing planning obligations, more than 1,400 homes cannot be occupied until 15,000 sq m of strategic industrial land at Plot V has effectively been completed. This industrial development is being progressed separately with General Projects. For contractors assessing Thameside West, that dependency links housing delivery to industrial infrastructure and land coordination across the wider site.
Thameside West programme
2019Cooperation agreement between GLA Land and Property and Silvertown Homes
16 November 2026Mayoral Decision MD3542 approves revised land arrangements
2028Demolition
2029Main construction
2032–33First residential completions
2040sCompletion of the wider scheme
Source: Mayoral Decision MD3542, Greater London Authority.
Edmonton: Acciona's energy recovery contract rises to £1.25bn
North London Waste Authority has agreed revised terms with Acciona Industrial for construction of the Energy Recovery Facility at Edmonton EcoPark. Announced by the authority on 12 November and examined in trade reporting during the week beginning 16 November, the agreement raises the construction contract price from its original £799m to £1.25bn, an increase of approximately £451m.
The revised contractual completion date is December 2029. The authority says construction is more than 60% complete, with around £700m already spent. The project has experienced inflation, higher material and financing costs, programme disruption and shortages of specialist mechanical and electrical subcontractors, particularly for boilers and flue-gas treatment equipment.
According to
NLWA's published decision, Acciona will assume additional responsibilities for future delivery risks under the revised arrangements. More than 400 skilled workers are now on site daily, compared with approximately 200 at the beginning of 2026, and the turbine has been installed.
The authority says abandoning the project would create additional costs for its seven constituent boroughs, including an estimated £100m annually by 2030/31. The next delivery issue is the revised construction and commissioning programme, which NLWA has asked officers to explain in greater detail.
Enfield: gas-main rupture forces evacuation of 300 people
A 12-inch gas main was ruptured during construction work on Napier Road, Enfield, on 16 November 2026, prompting the evacuation of approximately 300 people from surrounding residential properties. London Fire Brigade was called at 12.13pm, with residents initially taken to a rest centre before the local authority arranged alternative accommodation.
Two nearby schools were closed by their directors on 17 November while emergency services and the gas authority continued responding. The
London Fire Brigade incident record states that the incident concluded at 6.36pm on 17 November.
The incident occurred in connection with works at Curlew House, part of the Alma Estate regeneration programme. Demolition contractor Goody Demolition said it had opened an investigation into the circumstances. The investigation must establish the sequence of events before responsibility or the precise mechanism of the damage can be determined.
For London contractors carrying out demolition, groundworks and utility diversions, the incident reinforces the importance of coordinating underground-services information with the actual site conditions, work methods and controls agreed before excavation or intrusive operations begin. Those checks are especially consequential on regeneration projects surrounded by occupied homes, schools and live public infrastructure.
Bond Street: groundworks advance above an operational station
Ground Construction Limited is preparing to deliver piling, groundworks and a new concrete core at the West One redevelopment above Bond Street Underground station in central London. The specialist works follow demolition being undertaken by sister company Demolition Contracting UK as part of an approximately £8m demolition and enabling works package associated with McLaren Construction's redevelopment for British Land.
The scheme at 75 Davies Street retains around 60% of the existing concrete structure, according to architect Allford Hall Monaghan Morris. Four upper floors are being replaced with six floors of lightweight steel construction, increasing the amount of office accommodation while retaining substantial parts of the original building.
The location imposes specific constraints on structural works, lifting, vibration and construction sequencing because the building sits above an operational Underground and Elizabeth line interchange. Groundworks and the new core must be coordinated with retained structure, underground railway infrastructure and the structural steelwork that follows.
Tower Hamlets: Sinden selected for £30.9m affordable housing scheme
Tower Hamlets Council has named Sinden Construction Limited in the contract award notice for the redevelopment of Albert Jacob House in Roman Road, Bethnal Green. The main works contract is valued at £30,911,821 excluding VAT and covers 53 affordable homes with five ground-floor commercial units.
The award notice was published on 13 November 2026 and featured in construction industry reporting on 16 November. The planned contract period runs from 27 November 2026 to 27 November 2028. The council secured planning approval for the development in July 2025, replacing the former office accommodation with a building ranging from five to nine storeys.
The distinction for specialist subcontractors is that Sinden has been selected through the procurement process. The published award is not evidence that the main building works have physically started. The council's
planning announcement sets out the approved residential scope and the intended mix of homes.
London office development faces another cautious investment period
Landsec's half-year results, published on 13 November and discussed across the construction market during the following week, confirmed that the property company has no plans to commit significant additional capital to speculative office development at its current investment stage. Its three recently completed London office developments were reported to be 88% let or under offer.
The position affects expectations for the next wave of major central London office construction. Developers can continue leasing completed buildings and undertaking selected projects while holding back commitments to new speculative schemes. LCM has previously examined similar delivery constraints affecting
Canada Water and Lewisham regeneration, where planning progress and actual construction investment have followed different timetables.
Westminster restoration faces mounting delay costs
Parliamentary authorities published a response on 16 November 2026 to the Public Accounts Committee's scrutiny of the Palace of Westminster Restoration and Renewal programme. The committee's earlier November report warned that each year of delayed decision-making could add approximately £420m to the programme's costs, including inflation and continued development of options.
The restoration has a proposed initial delivery phase with a £3bn capped budget, including contingency arrangements described in the
Public Accounts Committee report. Parliamentary approval of the preferred delivery approach remains central to the programme. The cost pressures concern decisions and future delivery; they do not represent an additional construction contract award.
Contractor finances: reporting scrutiny and supplier exposure
The Financial Reporting Council published a construction and housebuilding thematic review on 18 November 2026, examining reporting practices among nine contractors and six housebuilders. The regulator identified scope for stronger disclosure of uncertain contract revenue, variations, delay-related liabilities, provisions and the assumptions used to estimate project outcomes.
The
FRC review focused on the quality of financial disclosures. Its findings are relevant to developers, lenders and subcontractors assessing the financial risks associated with long-duration building contracts, particularly where disputed payments or changes to programme and scope affect the timing of revenue recognition.
Separately, administration reporting published on 19 November described approximately £4.8m owed to suppliers and subcontractors following the collapse of Helix Construct Limited. The Newbury-based contractor worked across London and the South East in residential, education, care and commercial construction.
Companies House records confirm that the business entered administration on 17 September 2026, with KR8 Advisory appointed as administrator.
Building Safety Regulator data shows London remains central to approvals
The Building Safety Regulator's latest published August–October 2026 dataset shows that London accounted for 29 of 40 national new-build and conversion approvals during the 12 weeks to 1 November 2026. Thirty applications in this category were determined in London, giving the capital a 97% approval rate and covering 6,733 residential units.
The regulator's
6 November transparency release also records 42 Gateway 3 cases closed nationally during the period, with 31 approvals and 11 invalidations. Those approvals largely concerned internal refurbishment, remediation, NHS and transitional cases. The regulator reported that new-build schemes passing through Gateway 2 had not yet reached Gateway 3.
The figures were published before the reporting week but remained relevant to the industry's discussion of regulatory throughput. For clients planning residential starts, the distinction between Gateway 2 approval, commencement of building work and eventual Gateway 3 approval continues to affect delivery programmes.
A £500m retrofit framework opens for national bids
The North East Procurement Organisation launched its NEPO233 Retrofit and Energy Efficiency Works procurement on 19 November 2026. The proposed four-year framework has an estimated ceiling of £500m excluding VAT and is divided into ten lots covering domestic and non-domestic retrofit, building fabric improvements, low-carbon heating, renewable energy installations and related works.
Several lots cover projects nationally, making the framework relevant to contractors and specialist suppliers operating in London. The tender sets an 80% quality and 20% price weighting for framework appointment, with a 1% rebate payable to NEPO on work secured through the arrangement. The framework is expected to operate from 17 July 2027 to 16 July 2031, with individual work packages awarded through permitted call-off arrangements.
The
NEPO233 tender notice gives contractors until 12 noon on 18 January 2027 to submit bids through NEPO's Open procurement system. The £500m figure is an estimated framework ceiling and does not represent committed spending or guaranteed work for appointed suppliers.
Dates to watch
Key dates from this week’s developments
27 November 2026Albert Jacob House contract period begins
18 January 2027, 12 noonNEPO233 bid deadline
17 July 2027NEPO233 framework expected to start
2028Thameside West demolition
2029Thameside West main construction and West One completion target
December 2029Revised Edmonton contractual completion date
Method and Sources
LCM compiled this weekly review from documents published or reported during 16–22 November 2026, including Mayoral Decision MD3542, North London Waste Authority’s contract decision, the London Fire Brigade incident record, Tower Hamlets Council’s planning announcement, the Public Accounts Committee report, the Financial Reporting Council thematic review, Companies House insolvency records, the Building Safety Regulator’s August–October 2026 dataset and the NEPO233 tender notice.
Values are reported as published. Development arrangement values, capped budgets and framework ceilings are not single construction contract awards and do not represent committed spending. Some source documents were published shortly before the reporting week and are included where they shaped the week’s reporting.