London's Unsold New-Build Homes: How Affordable Housing Grants Can Help

London's Social and Affordable Homes Programme 2026-36 allows public grant funding to be used to acquire completed but unsold private-market homes and convert them to affordable housing. The provision forms part of the Greater London Authority's (GLA) funding programme of up to £11.7bn and provides an alternative sales route for developers holding completed residential stock.

A review by London Construction Magazine of London borough acquisition decisions has identified an example at 76 Mayes Road in Wood Green, where Haringey Council approved the purchase of 21 completed private-market apartments from Weston Homes during 2026 for use as social rented housing.

Although the Wood Green transaction uses funding from the previous affordable housing programme, it provides a precedent for the acquisition model included in the 2026-36 funding guidance. For developers, such transactions can release capital held in completed properties. For housing providers, they can deliver affordable accommodation without waiting for another construction programme to finish.

Residential buildings near ExCeL London in east London, with electricity pylons alongside. The photograph illustrates London apartment housing; the buildings pictured have not been identified as unsold stock or as part of any acquisition discussed in this article. Photo: London Construction Magazine

Unsold homes and acquisitions in figures
£11.7bnMaximum size of London's Social and Affordable Homes Programme 2026-36
3,648Completed but unsold new-build homes in London in Q1 2026
21Private-market apartments Haringey approved for purchase at 76 Mayes Road
60.2%Share of the 83-home scheme that would be council-acquired, LCM calculation
Sources: GLA funding guidance; CBRE research using Molior data; Haringey Council decision records.

The acquisition provision in London's £11.7bn programme

Paragraph 42 of the GLA's London Social and Affordable Homes Programme 2026-36 funding guidance, updated in February 2026, permits grant funding for a limited number of completed, unsold market homes to be transferred into affordable housing.

Paragraph 43 establishes a separate route for acquiring existing market housing, primarily for social rent or, in the case of local authorities, temporary accommodation. The GLA's bidding guidance distinguishes between newly completed properties that have never been occupied and previously occupied homes.

Both acquisition routes sit within a programme primarily intended to increase the supply of newly built affordable housing. At least 60% of homes delivered through the wider programme are expected to be for social rent.

The commercial relevance of the acquisition provision has increased as London's private residential sales market has weakened. CBRE research using Molior data recorded 3,648 completed but unsold new-build homes in London during Q1 2026, equivalent to 39% of the annual sales rate recorded at that point.

Homes transferred into affordable tenures accounted for 15% of new-home sales during the 12 months to Q1 2026, compared with 11% in 2024. The figures cover the wider market and cannot be attributed exclusively to GLA grant-funded purchases.

The accumulation of completed stock was examined in LCM's August 2026 investigation into London's new-build housing pipeline. Acquisitions provide one potential means of releasing capital from these developments, although the suitability of individual properties and the availability of grant funding will determine which transactions can proceed.

The market for completed homes
FigureWhat it describes
3,648Completed but unsold new-build homes in London during Q1 2026
39%That stock as a share of the annual sales rate recorded at that point
15%Share of new-home sales transferred into affordable tenures in the 12 months to Q1 2026
11%The same share in 2024
60%Minimum share of homes in the wider programme expected to be for social rent
Sources: CBRE research using Molior data; GLA funding guidance. The sales figures cover the wider market, not only grant-funded purchases.

Wood Green: converting 21 private-market homes to social rent

Haringey Council's acquisition at 76 Mayes Road, Wood Green, concerns a completed mixed-use development by Weston Homes on a former petrol filling station site. The development contains 83 apartments and six commercial units.

The council had already acquired the development's 29 designated affordable homes in July 2025 before reopening negotiations with Weston Homes in February 2026 over a further 21 apartments originally intended for private sale.

The additional properties comprise 14 one-bedroom and seven two-bedroom apartments. Haringey initially approved their acquisition on 5 May 2026, before seeking revised approval following legal advice concerning the funding structure.

The cabinet member decision of 7 August 2026 (reference 3517) approved the revised transaction using a combination of GLA Council Homes Acquisition Programme funding from the 2021-26 allocation and Housing Revenue Account borrowing.

LCM calculates that completing the additional acquisition would bring the number of council-acquired homes within the 83-home development to 50, equivalent to 60.2% of its residential units. The original designated affordable housing component comprised 29 homes, or 34.9% of the development by unit count.

The change would increase the proportion of council-acquired homes by 25.3 percentage points without increasing the number of dwellings within the completed development.

The council's August 2026 acquisition report makes legal completion conditional on its monitoring surveyor accepting the completed works and handover documentation. Haringey intends to allocate the apartments at social rents to households to whom it owes a full homelessness accommodation duty.

76 Mayes Road, Wood Green
ItemDetail
Development83 apartments and six commercial units, by Weston Homes
Designated affordable homes29, acquired by the council in July 2025 (34.9% of units)
Additional private-market homes21: 14 one-bedroom and seven two-bedroom apartments
Prospective council-acquired total50 of 83 homes (60.2% of units)
ChangeAn increase of 25.3 percentage points, with no additional dwellings
FundingGLA Council Homes Acquisition Programme, 2021-26 allocation, and Housing Revenue Account borrowing
ConditionCompletion depends on the monitoring surveyor accepting the works and handover documentation
Source: Haringey Council decision 3517, 7 August 2026, and acquisition report. Percentages calculated by LCM on unit counts.

Three acquisition models with different construction outcomes

LCM identified three London developments that illustrate how affordable housing acquisitions can produce different outcomes for residents, developers and construction contractors.

Three acquisition models
DevelopmentHomesTransaction typeConstruction position
76 Mayes Road, Wood Green21Private-market homes to social rentCompleted homes; revised acquisition approved 7 August 2026
67 Lawrence Road, Tottenham12Shared ownership to proposed social rentConstruction completed in 2024; acquisition approved 20 January 2026
TwelveTrees Park, West Ham426Agreement to deliver social rent and shared ownership homesDevelopment agreement announced in March 2026; delivery targeted by March 2030
Sources: Haringey Council decision records; Berkeley Group announcement. None of the cited records establishes an award under paragraph 42 of the 2026-36 programme.

At 67 Lawrence Road, Haringey Council approved the acquisition of 12 apartments on 20 January 2026 (reference 3365) within a 71-home development completed by Vabel in 2024 under planning permission HGY/2016/1212. The homes were already designated as affordable housing through a Section 106 agreement.

The proposed tenure conversion involves seven one-bedroom and five two-bedroom apartments, including four wheelchair-accessible homes. The council's January 2026 report identified a deed of variation to the Section 106 agreement as part of the proposed change from shared ownership to social rent.

TwelveTrees Park in West Ham illustrates a different delivery model. Berkeley and Metropolitan Thames Valley Housing announced an agreement in March 2026 to deliver 278 social rented homes and 148 shared ownership properties within the development's second phase, supported by GLA grant funding.

The West Ham agreement supports future physical construction, whereas the Wood Green transaction changes the tenure of completed market housing. The Tottenham acquisition changes the tenure of homes already designated as affordable. These transactions illustrate different delivery models; none of the cited records establishes an award under paragraph 42 of the new 2026-36 programme.

Building safety and technical acceptance

The GLA's 2026-36 funding guidance establishes different external wall requirements for new-build developments and acquisitions. Paragraph 52 prohibits combustible external wall materials in funded new-build buildings of any height, subject to the specified exemptions under the Building Regulations.

Paragraph 53 requires acquisition providers to make reasonable efforts to establish whether combustible materials are present. Under certain circumstances, the GLA may accept a fire risk appraisal carried out using PAS 9980:2022 or its applicable successor, where the assessment concludes that the external wall risk is sufficiently low to avoid remediation.

Acquired properties must also meet the London Plan's minimum internal floor area and storage requirements, unless the GLA accepts a justified exception under paragraph 58 of the funding guidance.

For surveyors and specialist contractors, the transfer of completed residential blocks can generate work involving condition assessments, fire safety investigations, defect inspections, building services verification and remedial packages. The extent of this work depends on the condition of the building and the purchaser's technical specification.

For higher-risk buildings subject to the relevant Building Safety Act regime, purchasers also need to establish the applicable completion certification, registration and building safety information requirements before occupation.

Acquisition prices, developer liquidity and public value

An acquisition grant cannot automatically bridge the difference between a developer's original sales valuation and the price a housing association or council can afford to pay. Under the GLA's assessment process, applicants must demonstrate that the subsidy requested is necessary to make affordable housing delivery financially viable.

The Competition and Markets Authority's Subsidy Advice Unit published its report on the proposed London funding programme on 3 February 2026. The programme incorporates project-level assessments intended to limit public subsidy to the amount required to deliver the affordable housing.

Housing providers purchasing apartments within mixed-tenure developments must also account for ongoing expenditure on lifts, communal heating, external walls, building management and other shared services. A competitive acquisition price can be undermined by high long-term service charges or outstanding defects.

The purchase prices and individual grant contributions for the two Haringey acquisitions are contained in exempt council reports, preventing an independent comparison of their acquisition costs with equivalent new construction.

For developers, capital released through completed-stock acquisitions could support subsequent development phases. That possibility is particularly relevant to the market conditions examined in LCM's October 2026 coverage of stalled housing development at Canada Water and Lewisham. Whether released capital leads to further construction depends on the viability and investment approval of the subsequent development.

The route into the new funding programme

The London Social and Affordable Homes Programme 2026-36 accepts funding proposals from local authorities, registered housing providers and eligible unregistered organisations, including developers. Organisations must obtain GLA Investment Partner status before receiving grant funding, and landlords delivering low-cost rental housing must meet the applicable registration requirements.

The initial bidding round opened on 24 February 2026 and closed in April 2026. An October 2026 mayoral response concerning accessible housing confirmed that allocations from the initial bidding round were still being finalised. LCM's checks on 17 November 2026 did not establish a project-level list of completed market homes approved for acquisition under paragraph 42.

The GLA bidding guidance requires providers submitting indicative acquisition proposals to identify expected numbers separately for never-occupied new-build and previously occupied market homes.

Funding remaining after the initial allocations is intended to become available through Continuous Market Engagement for identified projects. The wider programme requires funded projects to start by March 2036 and reach practical completion by 31 March 2039.

Timeline
July 2025Haringey acquires the 29 designated affordable homes at 76 Mayes Road
20 January 2026Haringey approves the acquisition of 12 apartments at 67 Lawrence Road
3 February 2026Subsidy Advice Unit publishes its report on the proposed London programme
24 February 2026Initial bidding round for the 2026-36 programme opens
March 2026Berkeley and Metropolitan Thames Valley announce the TwelveTrees Park agreement
5 May 2026Haringey initially approves the purchase of 21 further apartments at 76 Mayes Road
7 August 2026Haringey approves the revised transaction
31 March 2039Practical completion deadline for projects funded by the wider programme

Method and Sources
London Construction Magazine reviewed Haringey Council's acquisition decisions and supporting documents from May and August 2026 on 17 November 2026. At 76 Mayes Road, the original 29 council-acquired homes plus the additional 21 approved acquisitions give a prospective total of 50 out of 83 residential units, equivalent to 60.2%. The original 29 homes accounted for 34.9%, giving an increase of 25.3 percentage points; these calculations measure residential unit counts, not affordable housing percentages by habitable room or additional physical construction.