Square Mile's £1bn-Plus Heat Network: Which Buildings Could Have to Connect?

The City of London Corporation estimates that around 1,200 buildings in the Square Mile could be required to connect to a future heat network, with combined annual heat demand of approximately 1,000 GWh and investment exceeding £1bn needed to develop a City-scale system. The figures appear in the Corporation's heat network programme update of 5 October 2026 and point to substantial changes in how commercial properties across London's financial district could receive heating.

The Corporation is seeking to designate the whole Square Mile as a heat network zone, following a boundary consultation that closed on 12 August 2026. Separately, it is procuring a development partner for the central and western Square Mile under a proposed long-term concession with an estimated procurement value of £4.342bn excluding VAT. That procurement remains subject to the project's approval process, with a development partner appointment expected in November 2026.

For building owners, engineers and contractors, the immediate question is which properties may fall within future connection requirements, how existing heating installations would be assessed and where the first physical works could take place.

Farringdon Street viewed north from Holborn Viaduct in the City of London, with commercial office buildings and street works visible, photographed in October 2026. The photograph illustrates the Square Mile's office stock and streets; the works pictured have not been identified as heat network construction. Photo: London Construction Magazine

The Square Mile heat network in figures
1,200Buildings that could be required to connect, City Corporation estimate
1,000 GWhApproximate combined annual heat demand
£1bn-plusInvestment needed for a City-scale system
£4.342bnEstimated procurement value of the long-term concession, excluding VAT
Sources: City of London Corporation programme update, 5 October 2026; Find a Tender notice 2025/S 000-083343. Neither money figure is a construction award.

Which Square Mile buildings could be required to connect?

The government's heat network zoning response, published on 21 January 2026, identifies three principal building categories that may be subject to connection requirements once a zone has been designated and a developer appointed.

Buildings that may face a connection requirement
Building categoryProposed connection testEvidence for owners and engineers
Existing commercial buildingsAnnual average heat demand above 100 MWh, with a wet heating systemHeat consumption, heating distribution type and plant configuration
Existing communally heated buildingsDomestic or non-domestic buildings with existing communal heatingCommunal plant arrangements, distribution systems and connection feasibility
New developmentsBuildings receiving planning permission after zone designationPlanning date, proposed heating strategy and capacity for a district heat connection
Source: government heat network zoning response, 21 January 2026. Applies once a zone is designated and a developer appointed; exemptions and deferrals are envisaged.

For existing offices, the 100 MWh annual heat-demand threshold is particularly relevant. The government describes this level of consumption as broadly equivalent to a medium or large office building. A property's address within the proposed zone would be only one part of assessing its position; heating demand, system type and connection feasibility would also need examination.

Under the government's published policy, a zone coordination body would issue a connection requirement at the request of the appointed network developer, provided it was satisfied that the building could be connected within the proposed timeframe. Owners would be able to seek exemptions, including where an existing building already has a low-carbon heating system or where structural incompatibility prevents connection. Temporary deferrals are also envisaged.

A requirement to establish a functional connection would involve external pipework, a heat interface unit and associated modifications inside the building. The government's approach also allows owners to retain existing heating systems after connection where they are not ready to purchase heat exclusively from the network.

Where the heat network could be developed

The City Corporation's published heat network programme distinguishes the proposed Square Mile-wide zoning boundary from the central and western area being procured for development.

The December 2025 procurement notice describes a development area bounded by the City's borders with Westminster, Camden and Islington, roads including Moorgate, Princes Street, King William Street and London Bridge, and the River Thames. These boundaries identify the competition area. They do not provide a confirmed street-by-street construction route or a list of buildings scheduled for connection.

The existing Citigen network, operated by E.ON, is currently the Square Mile's only operating heat network, according to the Corporation. E.ON has explored expansion and decarbonisation options, with further development being considered alongside the forthcoming zoning arrangements.

The north-eastern Square Mile is at a different stage. A 2024 study undertaken with support from the Greater London Authority and in collaboration with Hackney and Tower Hamlets examined options for a further low-carbon network. The Corporation identifies this area as having the highest heat density within the Square Mile, but its published programme gives no construction timetable for the proposed north-eastern system.

These geographical distinctions affect the potential construction pipeline. A City-wide zoning proposal, an existing operational network and an area covered by a live development-partner procurement each have different design, commercial and delivery positions. The first substantive construction packages will depend on which network sections receive approval and funding.

Four areas at four different stages
AreaPosition
Whole Square MileProposed heat network zone; boundary consultation closed on 12 August 2026
Central and western Square MileDevelopment partner being procured under a proposed long-term concession
Citigen network, operated by E.ONThe Square Mile's only operating heat network; expansion and decarbonisation options explored
North-eastern Square Mile2024 study with the GLA, Hackney and Tower Hamlets; highest heat density; no construction timetable published
Source: City of London Corporation heat network programme and the December 2025 procurement notice.

The £4.342bn concession and the £1bn-plus investment estimate

The Corporation's early assessment identifies more than £1bn of investment required for a City-scale heat network serving the approximately 1,200 potentially connectable buildings. The separate Find a Tender notice 2025/S 000-083343, published on 16 December 2025, gives an estimated procurement value of £4.342bn excluding VAT for a long-term heat network concession.

The concession's indicative contract period runs from 26 November 2026 to 31 August 2068. Its estimated procurement value covers a different commercial scope and period from the Corporation's City-scale investment requirement. Neither figure is an announced award of construction works to a named contractor.

The proposed arrangement would require the selected development partner to establish a special purpose vehicle responsible for progressing the network through design and development. A further approval gateway would follow before the delivery arrangements moved into the construction and operational stages.

Under the tender structure, the City Corporation would contribute no capital to the special purpose vehicle and would hold a special or 'golden' share giving it specified governance rights. The procurement uses a competitive flexible procedure, with evaluation criteria weighted 50% technical, 40% commercial and 10% social value.

The initial supplier response deadline was 26 January 2026, followed by an indicative final tender submission date of 22 June 2026. The procurement timetable targeted an award decision on 5 November 2026 and contract signature on 26 November 2026.

Two figures, two different things
FigureWhat it describesDetail
More than £1bnInvestment required for a City-scale heat networkThe Corporation's early assessment, serving about 1,200 potentially connectable buildings
£4.342bn excluding VATEstimated procurement value of the long-term concessionIndicative contract period 26 November 2026 to 31 August 2068
50% / 40% / 10%Evaluation weightingTechnical, commercial and social value, under a competitive flexible procedure
No capitalCity Corporation contribution to the special purpose vehicleIt would hold a special or 'golden' share with specified governance rights
Source: Find a Tender notice 2025/S 000-083343, published 16 December 2025.

What City committee records show in November 2026

LCM's review of City of London Corporation committee records on 15 November 2026 found that a Phase 1 Heat Network Zoning Procurement Stage 2 report, identified as GW2b, was listed for non-public consideration by the Planning and Transportation Committee on 10 November and the Projects and Procurement Sub-Committee on 12 November.

A further GW2b procurement report is scheduled for the Policy and Resources Committee on 19 November 2026. The public agenda identifies the report as restricted business and provides no named development partner or contract award outcome.

The Corporation's public programme page, updated on 5 October 2026, continues to describe the development partner appointment as expected in November 2026. LCM's 15 November check did not establish a publicly confirmed award or signed development agreement.

Procurement timeline
16 December 2025Find a Tender notice published
26 January 2026Initial supplier response deadline
22 June 2026Indicative final tender submission date
12 August 2026Zone boundary consultation closes
5 October 2026Corporation programme update: appointment expected in November 2026
5 November 2026Target award decision under the tender timetable
10 and 12 November 2026GW2b report listed for non-public consideration by two committees
15 November 2026LCM check finds no publicly confirmed award or signed agreement
19 November 2026Further GW2b report scheduled for the Policy and Resources Committee, as restricted business
26 November 2026Indicative contract signature and concession start

The engineering work behind building connections

For existing Square Mile offices, the proposed connection requirements raise several design questions before any retrofit package can be priced. Building services engineers would need to establish the existing heat demand, distribution temperatures, plantroom space, equipment access and available routes for new pipework from the external network into the property.

The government's zoning response identifies functional connections involving external mains, heat interface units and modifications to internal systems or building structures. Where buildings have undergone repeated alterations, the location and condition of existing services may require surveys before a connection design can be completed. Penetrations through fire compartments, occupied areas or protected building fabric would also need to be assessed against the relevant approvals.

This connects with the wider construction work already occurring in London's office stock. LCM's review of major London retrofit contractors identifies existing services capacity, retained structures and restricted access as recurring issues in commercial refurbishment. Future heat network connections would introduce additional interfaces where buildings already have planned MEP replacement or wider energy upgrades.

For the network developer, construction would involve the design and installation of district heating mains, connections to buildings and the associated heat generation and distribution infrastructure. Work in City streets would need to be coordinated with underground utilities, highway access and building operations. The Corporation's published procurement establishes the intended development area, but detailed pipe alignments and individual connection programmes will depend on the design and approvals process.

What a connection design needs to establish
ItemWhy it matters
Existing heat demandSets the capacity of the connection
Distribution temperaturesDetermines compatibility with the network supply
Plantroom space and equipment accessGoverns where a heat interface unit can go and how it gets there
Pipework routesFrom the external main into the property
Location and condition of existing servicesMay require surveys where buildings have been repeatedly altered
PenetrationsThrough fire compartments, occupied areas or protected fabric, assessed against the relevant approvals
Compiled by LCM from the design questions described in this article.

Connection costs and the developing regulatory framework

The government's 4 November 2026 Energy Independence Bill factsheet sets out a further element of the proposed zoning framework. At the launch of heat network zoning, buildings required to connect would not be required to contribute to the connection cost. The government is seeking powers to introduce capped connection charges later, with a proposed £0 cap for existing residential buildings and a cap linked to the cost of alternative heating technology for commercial properties.

Proposed connection charges
StagePosition
At the launch of heat network zoningBuildings required to connect would not contribute to the connection cost
Later, if powers are grantedCapped connection charges
Existing residential buildingsProposed cap of £0
Commercial propertiesCap linked to the cost of alternative heating technology
Source: Energy Independence Bill factsheet, 4 November 2026. Connection charges, internal upgrades and heat supply agreements are separate costs.

The distinction will affect future commercial negotiations between building owners and heat network developers. Connection charges, internal building upgrades and ongoing heat supply agreements concern different costs, and the final arrangements will depend on the applicable legislation and individual contracts.

The next published City Corporation procurement governance item is the Policy and Resources Committee's restricted GW2b report scheduled for 19 November 2026. The development agreement's indicative signature date remains 26 November 2026 under the December 2025 tender timetable.