A 100MW data centre can mean 100 megawatts of capacity for servers, storage and networking equipment, or a 100MW grid connection supplying the whole site. On a phased campus, either figure can describe the completed development while the first building opens with a smaller allocation.
At Court Lane in Iver, Buckinghamshire, three figures appear in the project record. The
planning appeal documents (APP/N0410/W/24/3337981) describe an expected 90MW of IT load. Developer Corscale lists 103MW of power capacity. Contractor McLaren describes a 140MW campus. For an estimator pricing the first data hall, the most useful question is which figure appears in the employer's requirements for that hall.
A data centre's grid connection supplies both the IT equipment and the plant that keeps it running, including rooftop cooling units. Image: London Construction Magazine.
The numbers in this guide
876,000MWhEnergy used by a 100MW average load over a 365-day year
1.25Annual PUE assumed in LCM’s worked examples
140MVASupply reserved at Court Lane, Iver, according to appeal evidence
90MWIT load the Court Lane supply was expected to support at appeal
Where is the 100MW measured?
IT capacity is the power a data centre is designed to deliver to its computing equipment. The facility also needs electricity to remove heat, run pumps and fans, and cover losses as power passes through transformers and uninterruptible power supplies. A grid import figure covers electricity entering the site at the connection point. The wording alongside the number tells the reader where the measurement starts and ends.
Three ways to read a 100MW announcement
How much electricity would a 100MW data centre use?
A megawatt (MW) measures power. A megawatt-hour (MWh) measures energy: equipment drawing an average of 100MW for one hour uses 100MWh. To put an annual consumption figure against a proposed campus, the missing input is its average operating load over the year. A connection rating gives no record of how many halls were occupied or how hard their equipment ran.
Power usage effectiveness (PUE) relates the electricity used by the whole facility to the share used by its IT equipment. The
formula in Commission Delegated Regulation (EU) 2024/1364 divides total data centre energy by IT equipment energy over the same period. At an annual PUE of 1.25, every 1MWh used by IT equipment corresponds to 1.25MWh used by the facility. The other 0.25MWh includes cooling and electrical losses.
Units and terms
Sources: Commission Delegated Regulation (EU) 2024/1364 and LCM.
LCM calculated what happens when the same 100MW average is measured at two different points. If the IT equipment averages 100MW for a 365-day year, it uses 876,000MWh. At an assumed annual PUE of 1.25, the whole facility uses 1,095,000MWh, equivalent to an average facility load of 125MW.
If the whole facility averages 100MW over that year, its total consumption is 876,000MWh. At the same PUE, the IT equipment accounts for 700,800MWh, or 80MW on average. A designer sizing switchgear or cooling plant still needs the peak duties from the design brief. An annual energy ratio cannot supply them.
Same 100MW, two measuring points
LCM calculation, assuming an annual PUE of 1.25 over 8,760 hours. Annual ratios do not give peak design duties.
What the London project records actually say
Goldacre Ventures used two different units when it
announced the sale of its east London data centre site on 19 November 2026. It reported approximately 130MVA of reserved grid power and approximately 90MW of potential IT capacity. Goldacre also said site remediation and enabling works had been completed. The sale announcement therefore gives a grid reservation, a proposed computing capacity and a physical works milestone, each with its own label.
Megavolt-amperes (MVA) measure apparent power, a quantity used to rate electrical equipment and connections. Converting an MVA figure to MW at the same point requires the power factor: MW equals MVA multiplied by power factor. Dividing Goldacre's 130MVA reservation by its 90MW IT target would not give a PUE. Calculating PUE requires energy readings for the facility and its IT equipment over a common period.
At
Court Lane in Iver, paragraph 136 of the inspector's report accompanying the 6 December 2024 appeal decision records evidence that 140MVA had been reserved. That supply was expected to support 90MW of IT load, with power also needed for cooling and site operations. The 90MW figure belongs to the proposal described at appeal.
What each source says
Sources: Goldacre, Planning Inspectorate, Corscale and McLaren. No source gives a first-building IT allocation.
Which figure belongs in a construction package?
A first-phase tender needs a load schedule tied to the buildings and systems in scope. A campus may need its incoming substation in the first package while the client orders switchgear, cooling equipment and fit-out for individual halls in stages. For a project identified through the
London data centre pipeline or the
European data centre construction ranking, carry the source's unit and phase description into the enquiry.
Three documents answer different questions. The connection agreement sets out the import terms and any staged capacity. The electrical load schedule and single-line diagram show which supplies and loads belong to the first hall. At handover, the signed commissioning records identify the systems tested, the load applied and the acceptance criteria met. For the contractor asked to demonstrate a hall's performance, that last figure is the one to agree before booking the load banks.
Which document answers which question
Source: LCM.
Method and Sources
LCM used the PUE formula in Annex III of Commission Delegated Regulation (EU) 2024/1364, checked on 22 November 2026, and assumed an annual PUE of 1.25 for both examples. Average power was multiplied by 8,760 hours in a 365-day year to obtain annual energy. Where 100MW referred to IT load, IT energy was multiplied by 1.25 to obtain facility energy. Where 100MW referred to total facility load, facility energy was divided by 1.25 to obtain IT energy.
Project figures are taken from the Court Lane appeal documents (APP/N0410/W/24/3337981), Corscale’s project entry, McLaren’s appointment announcement and Goldacre Ventures’ 19 November 2026 sale announcement. Each figure is reported with the unit and measuring point its source used; no phase split was calculated.