What Does 100MW Mean for a Data Centre? IT Load vs Grid Capacity

A 100MW data centre can mean 100 megawatts of capacity for servers, storage and networking equipment, or a 100MW grid connection supplying the whole site. On a phased campus, either figure can describe the completed development while the first building opens with a smaller allocation.

At Court Lane in Iver, Buckinghamshire, three figures appear in the project record. The planning appeal documents (APP/N0410/W/24/3337981) describe an expected 90MW of IT load. Developer Corscale lists 103MW of power capacity. Contractor McLaren describes a 140MW campus. For an estimator pricing the first data hall, the most useful question is which figure appears in the employer's requirements for that hall.

A data centre's grid connection supplies both the IT equipment and the plant that keeps it running, including rooftop cooling units. Image: London Construction Magazine.

The numbers in this guide
876,000MWhEnergy used by a 100MW average load over a 365-day year
1.25Annual PUE assumed in LCM’s worked examples
140MVASupply reserved at Court Lane, Iver, according to appeal evidence
90MWIT load the Court Lane supply was expected to support at appeal

Where is the 100MW measured?

IT capacity is the power a data centre is designed to deliver to its computing equipment. The facility also needs electricity to remove heat, run pumps and fans, and cover losses as power passes through transformers and uninterruptible power supplies. A grid import figure covers electricity entering the site at the connection point. The wording alongside the number tells the reader where the measurement starts and ends.

Three ways to read a 100MW announcement
Illustrative announcementWhat it tells a contractorWhat to check for phase one
100MW of IT capacity at full build-outThe completed campus is designed to supply 100MW to IT equipment across its data halls.Which halls are in the first package and what IT load is specified for each?
100MW grid connection secured for a phased campusThe developer reports securing 100MW of import capacity at the site boundary.How much import capacity does the agreement provide at first energisation, and on what date?
First 20MW IT hall commissioned on a planned 100MW IT campusThe announcement identifies a completed commissioning milestone for one hall and a separate campus target.Which electrical and cooling systems were tested, and what load did the client accept at handover?

How much electricity would a 100MW data centre use?

A megawatt (MW) measures power. A megawatt-hour (MWh) measures energy: equipment drawing an average of 100MW for one hour uses 100MWh. To put an annual consumption figure against a proposed campus, the missing input is its average operating load over the year. A connection rating gives no record of how many halls were occupied or how hard their equipment ran.

Power usage effectiveness (PUE) relates the electricity used by the whole facility to the share used by its IT equipment. The formula in Commission Delegated Regulation (EU) 2024/1364 divides total data centre energy by IT equipment energy over the same period. At an annual PUE of 1.25, every 1MWh used by IT equipment corresponds to 1.25MWh used by the facility. The other 0.25MWh includes cooling and electrical losses.

Units and terms
TermWhat it measures
MW (megawatt)Power at a given moment
MWh (megawatt-hour)Energy: 100MW for one hour is 100MWh
MVA (megavolt-ampere)Apparent power, used to rate electrical equipment and connections; MW = MVA × power factor
IT capacityPower the facility is designed to deliver to servers, storage and networking equipment
Grid importElectricity entering the site at the connection point
PUETotal facility energy divided by IT equipment energy over the same period
Sources: Commission Delegated Regulation (EU) 2024/1364 and LCM.

LCM calculated what happens when the same 100MW average is measured at two different points. If the IT equipment averages 100MW for a 365-day year, it uses 876,000MWh. At an assumed annual PUE of 1.25, the whole facility uses 1,095,000MWh, equivalent to an average facility load of 125MW.

If the whole facility averages 100MW over that year, its total consumption is 876,000MWh. At the same PUE, the IT equipment accounts for 700,800MWh, or 80MW on average. A designer sizing switchgear or cooling plant still needs the peak duties from the design brief. An annual energy ratio cannot supply them.

Same 100MW, two measuring points
Where the 100MW average is measuredIT energy per yearFacility energy per yearAverage IT loadAverage facility load
IT equipment876,000MWh1,095,000MWh100MW125MW
Whole facility700,800MWh876,000MWh80MW100MW
LCM calculation, assuming an annual PUE of 1.25 over 8,760 hours. Annual ratios do not give peak design duties.

What the London project records actually say

Goldacre Ventures used two different units when it announced the sale of its east London data centre site on 19 November 2026. It reported approximately 130MVA of reserved grid power and approximately 90MW of potential IT capacity. Goldacre also said site remediation and enabling works had been completed. The sale announcement therefore gives a grid reservation, a proposed computing capacity and a physical works milestone, each with its own label.

Megavolt-amperes (MVA) measure apparent power, a quantity used to rate electrical equipment and connections. Converting an MVA figure to MW at the same point requires the power factor: MW equals MVA multiplied by power factor. Dividing Goldacre's 130MVA reservation by its 90MW IT target would not give a PUE. Calculating PUE requires energy readings for the facility and its IT equipment over a common period.

At Court Lane in Iver, paragraph 136 of the inspector's report accompanying the 6 December 2024 appeal decision records evidence that 140MVA had been reserved. That supply was expected to support 90MW of IT load, with power also needed for cooling and site operations. The 90MW figure belongs to the proposal described at appeal.

When LCM checked Corscale's Court Lane project entry on 22 November 2026, the developer listed "103 MW power capacity". McLaren's pre-construction appointment announcement described a 140MW campus comprising two buildings with a dedicated 140MVA substation. Neither company gave an IT allocation for the first building in those statements. Dividing the campus figure by two would introduce a phase split neither source supports.

What each source says
SourceProjectFigure reportedWhat the figure describes
Goldacre Ventures sale announcement, 19 November 2026East London data centre siteApprox. 130MVA; approx. 90MWReserved grid power; potential IT capacity
Inspector’s report, para. 136, appeal decided 6 December 2024Court Lane, Iver140MVA; 90MWReserved supply; expected IT load at appeal
Corscale project entry, checked 22 November 2026Court Lane, Iver103MW“Power capacity” as listed by the developer
McLaren pre-construction appointmentCourt Lane, Iver140MW; 140MVATwo-building campus; dedicated substation
Sources: Goldacre, Planning Inspectorate, Corscale and McLaren. No source gives a first-building IT allocation.

Which figure belongs in a construction package?

A first-phase tender needs a load schedule tied to the buildings and systems in scope. A campus may need its incoming substation in the first package while the client orders switchgear, cooling equipment and fit-out for individual halls in stages. For a project identified through the London data centre pipeline or the European data centre construction ranking, carry the source's unit and phase description into the enquiry.

Three documents answer different questions. The connection agreement sets out the import terms and any staged capacity. The electrical load schedule and single-line diagram show which supplies and loads belong to the first hall. At handover, the signed commissioning records identify the systems tested, the load applied and the acceptance criteria met. For the contractor asked to demonstrate a hall's performance, that last figure is the one to agree before booking the load banks.

Which document answers which question
DocumentQuestion it answers
Connection agreementImport terms and any staged capacity
Electrical load schedule and single-line diagramWhich supplies and loads belong to the first hall
Signed commissioning recordsSystems tested, load applied and acceptance criteria met at handover
Source: LCM.

Method and Sources

LCM used the PUE formula in Annex III of Commission Delegated Regulation (EU) 2024/1364, checked on 22 November 2026, and assumed an annual PUE of 1.25 for both examples. Average power was multiplied by 8,760 hours in a 365-day year to obtain annual energy. Where 100MW referred to IT load, IT energy was multiplied by 1.25 to obtain facility energy. Where 100MW referred to total facility load, facility energy was divided by 1.25 to obtain IT energy.

Project figures are taken from the Court Lane appeal documents (APP/N0410/W/24/3337981), Corscale’s project entry, McLaren’s appointment announcement and Goldacre Ventures’ 19 November 2026 sale announcement. Each figure is reported with the unit and measuring point its source used; no phase split was calculated.