Fusion21 has extended the tender deadline for its £1bn Construction and Refurbishment Framework to 22 January 2027, giving contractors an additional 14 calendar days to prepare bids for the four-year programme covering housing, education, healthcare and wider public-sector construction across the UK.
The revised deadline appears in a Find a Tender amendment published on 13 November 2026, which also extends the deadline for clarification questions to 7 January 2027. London Construction Magazine's review of the procurement records found that Fusion21's 9 November announcement still carried the original 8 January closing date when checked on 14 November.
Construction activity in Islington, London, photographed in November 2026. Used to illustrate the wider London construction market. Photo: London Construction Magazine
The framework in figures
£1bnEstimated framework value over four years, excluding VAT
22 Jan 2027New tender deadline, noon, 14 days later than before
600Maximum appointment positions nationally
60Maximum appointment positions in the London region
Source: Find a Tender notices 2026/S 000-105267 and 2026/S 000-107851. Appointment positions are LCM calculations.
The January deadline extension
Fusion21 originally advertised the opportunity on 5 November 2026 under tender notice 2026/S 000-105267, reference Fusion21-0304. The subsequent amendment, notice 2026/S 000-107851, changes two dates while retaining the framework's scope, procurement requirements, estimated value and evaluation arrangements.
The clarification deadline has moved from 16 December 2026 at 5pm to 7 January 2027 at 5pm, providing 22 additional calendar days for suppliers to raise questions. Tender submissions now close at noon on 22 January 2027, two weeks later than the original deadline.
What changed in the timetable
| Procurement stage | Original date | Current date |
|---|---|---|
| Clarification deadline | 16 Dec 2026, 5pm | 7 Jan 2027, 5pm |
| Tender submission | 8 Jan 2027, noon | 22 Jan 2027, noon |
| Estimated award decision | 19 Apr 2027 | 19 Apr 2027 |
| Framework commencement | 24 May 2027 | 24 May 2027 |
The amendment expressly confirms that all other procurement requirements remain unchanged. For contractors preparing technical submissions and commercial pricing over the Christmas and New Year period, the revised timetable gives bid teams more time to finalise supporting evidence, complete tender responses and address clarification matters before submission.
The revised deadline also provides an important correction to the Fusion21 announcement issued on 9 November and construction industry reports published before the amendment. The operative procurement timetable is now recorded in the 13 November notice.
From £750m market engagement to a £1bn framework
Fusion21's framework has also grown in estimated value since the preliminary procurement stage. Its September 2026 preliminary market engagement record, updated on 24 September, identified an estimated value of £750m excluding VAT. By the time the formal tender was issued on 5 November, the estimate had increased to £1bn excluding VAT.
LCM's comparison of the two procurement stages identifies a £250m increase in the estimated framework value, equivalent to 33.3%. The published records reviewed do not explain that adjustment. The £1bn figure is the estimated aggregate value of potential work through the framework over four years, with individual construction contracts to be procured through subsequent call-offs.
The framework is divided into two lots, each carrying an estimated value of £500m excluding VAT. Lot 1 covers Housing Refurbishment and New Build, including social housing improvement, retrofit, energy efficiency, extensions, conversions, extra-care accommodation, infill development and regeneration. Lot 2 covers Non-Domestic Refurbishment and New Build, including schools, healthcare facilities and other public-sector buildings.
The two lots
| Lot | Scope | Estimated value |
|---|---|---|
| Lot 1: Housing Refurbishment and New Build | Social housing improvement, retrofit, energy efficiency, extensions, conversions, extra-care accommodation, infill development and regeneration | £500m excluding VAT |
| Lot 2: Non-Domestic Refurbishment and New Build | Schools, healthcare facilities and other public-sector buildings | £500m excluding VAT |
Source: Find a Tender. Estimated values may be shared between the two lots.
The notice permits estimated values to be shared between the two lots, giving Fusion21 flexibility to accommodate different levels of demand from participating public bodies. Call-off contracts may be awarded with or without further competition, subject to the framework's procedures and applicable procurement requirements.
Fusion21 says the previous version of its construction and refurbishment framework has supported 95 member projects worth a combined £675m. Peter Francis, Group Executive Director (Operations), said the updated framework is intended to bring requirements together earlier and support larger, strategically planned construction programmes, while giving suppliers greater consistency in future opportunities.
Up to 600 appointment positions across the UK
The detailed supplier structure provides another useful indication of how the new Fusion21 framework could operate. Both lots cover 10 geographical regions, including London, the South East and East of England, with each region divided into three construction contract value bands.
A maximum of 10 suppliers may be appointed to each lot, region and value-band combination. LCM calculates that the published structure therefore allows up to 600 appointment positions nationally, including 60 within the London region. These are potential positions across the framework, with individual contractors permitted to secure appointments in more than one lot, region or value band.
The three bands also carry distinct financial qualification requirements. Band 1 covers projects valued from £0 to £5m and requires minimum annual turnover of £10m. Band 2 covers £5m to £15m with a £30m turnover requirement, while Band 3 covers projects above £15m with a minimum annual turnover of £50m.
Value bands and turnover thresholds
| Band | Project value | Minimum annual turnover |
|---|---|---|
| Band 1 | £0 to £5m | £10m |
| Band 2 | £5m to £15m | £30m |
| Band 3 | Above £15m | £50m |
LCM calculation: 2 lots x 10 regions x 3 value bands x 10 suppliers = 600 positions nationally; 2 lots x 3 value bands x 10 suppliers = 60 in the London region.
For smaller construction businesses, the turnover conditions are an important consideration before committing resources to a bid. Specialist firms that do not meet the direct appointment requirements may find opportunities through the supply chains of successful framework contractors, particularly where their experience supports refurbishment, building services, retrofit or specialist construction packages. Any joint-bidding arrangements would need to meet the tender documentation.
The published evaluation weighting allocates 70% to quality and technical submissions and 30% to commercial and cost assessment. Bidders must also demonstrate relevant construction experience, appropriate financial standing and compliance with the stated participation requirements, including the Common Assessment Standard or CHAS Elite. The notice identifies minimum insurance levels of £10m employers' liability, £5m public liability and £5m professional indemnity.
Commercially, the procurement notice specifies a maximum framework fee charged to suppliers of 4%, with a typical range between 1% and 4% depending on call-off value and the services required. The detailed charging arrangements are contained in Schedule 9 of the Framework Agreement. For illustration, applying rates of 1% and 4% to a hypothetical £10m call-off produces £100,000 and £400,000 respectively; the actual applicable charge depends on the agreement's terms.
The London regional opportunity is particularly relevant to contractors involved in occupied housing refurbishment, retrofit and public-building improvements. Previous use of Fusion21's construction framework can be seen in Havering, where the council approved procurement through Lot 1 of the predecessor framework for a separate £13.4m high-rise building safety improvement programme in April 2025. LCM examined that procurement context in its report on Havering's tower lift safety works in October 2026.
The new framework is being procured through an open procedure under the Procurement Act 2023, with electronic submissions managed through the Fusion21 procurement portal. The estimated award decision remains 19 April 2027, with the four-year framework scheduled to run from 24 May 2027 until 23 May 2031. Contractors have until 7 January 2027 at 5pm to submit clarification questions and until 22 January 2027 at noon to submit their tenders.
Procurement timeline
24 September 2026Preliminary market engagement record updated, with an estimated value of £750m excluding VAT
5 November 2026Tender notice 2026/S 000-105267 published, with the estimate at £1bn excluding VAT
9 November 2026Fusion21 announcement issued with the original 8 January closing date
13 November 2026Amendment notice 2026/S 000-107851 extends both deadlines
7 January 2027, 5pmClarification questions close
22 January 2027, noonTender submissions close
19 April 2027Estimated award decision
24 May 2027 to 23 May 2031Four-year framework term