Hackney Backs 490-Unit Finsgate House Tower at Old Street

Hackney's Planning Committee resolved on 11 November 2026 to grant conditional planning permission for HUB's Finsgate House redevelopment at 5–7 Cranwood Street, near Old Street station. Application 2025/2794 proposes replacing three existing office buildings with a 35-storey co-living tower containing 490 units and a separate five-storey office building.
The committee resolution, published on 12 November, remains subject to completion of a legal agreement following a Stage 2 referral to the Greater London Authority. Designed by Allford Hall Monaghan Morris (AHMM), the scheme includes approximately 4,000 sq m of workspace, a community hub and changes to the surrounding streets. The planning papers also establish a detailed proposed construction sequence.
Architectural visualisation of the proposed Finsgate House redevelopment at 5-7 Cranwood Street, near Old Street, Hackney. The HUB development, designed by AHMM, includes a 35-storey tower with 490 co-living units and a separate five-storey office building.
Finsgate House in figures
35Storeys in the co-living tower
490Co-living units, individually rented
55 monthsProposed programme, including pre-construction
£18.22mProposed affordable housing contribution
Source: Hackney planning committee report, application 2025/2794.

Demolition programme and TfL infrastructure safeguards

Hackney's planning committee report sets out a 55-month programme comprising 12 months of pre-construction work, six months of demolition and 37 months of construction. LCM calculates that the two physical works phases account for 43 months of that programme. These periods are planning assumptions rather than announced start and completion dates.
Proposed programme
PhaseDurationNote
Pre-construction12 monthsPreparation before physical works
Demolition6 monthsExisting office buildings on the site
Construction37 monthsTower and five-storey office building
Total55 monthsDemolition and construction together are 43 months, on LCM's calculation
Source: Hackney planning committee report. These are planning assumptions, not announced start and completion dates.
The redevelopment requires demolition of the office buildings occupying the site, close to transport infrastructure around Old Street. Hackney's proposed conditions require a demolition and construction management plan addressing delivery vehicles, traffic arrangements, noise and dust, with detailed construction logistics developed in consultation with Transport for London.
LCM's review of the committee report also identifies specific safeguards for TfL assets before demolition. These include a ground movement and impact assessment, a movement monitoring action plan and, where monitoring is required, baseline instrument readings before works begin. Detailed risk assessments are also specified for demolition, foundations, basement works and lifting equipment.

£18.22m affordable housing contribution

The Finsgate House viability assessment includes an accepted construction-cost allowance of £108.46m. This is an appraisal assumption used to assess the scheme's economics, not an announced main-contractor award or signed construction contract.
The residential tower would contain 490 individually rented co-living units with shared social facilities and communal terraces. The smaller eastern building would provide offices, with 10% of its workspace intended to be affordable for smaller businesses. Developer HUB also proposes a flexible community hub at ground-floor level.
The development makes no provision for conventional affordable homes on site. Instead, HUB has proposed £18.22m towards affordable housing elsewhere in Hackney, payable in four annual instalments during the construction programme. Council officers accepted the contribution following an independent viability review, although the GLA's earlier response questioned whether it represented the maximum viable amount.
The proposed legal agreement also lists £114,219 towards employment training and £110,000 towards TfL cycle hire, alongside other transport and carbon-offset contributions. HUB says the development will incorporate material reuse, additional planting and public-realm improvements. A whole-life carbon assessment and site waste management plan form part of the submitted planning documents.
The money in the planning papers
ItemAmountStatus
Construction-cost allowance£108.46mViability appraisal assumption, not a contract award
Affordable housing contribution£18.22mPayable in four annual instalments during construction
Employment training£114,219Listed in the proposed legal agreement
TfL cycle hire£110,000Listed in the proposed legal agreement
Source: Hackney planning committee report. Other transport and carbon-offset contributions are also listed.

Remaining planning and construction approvals

Hackney's committee supported the Finsgate House redevelopment despite objections concerning building height, heritage, neighbouring amenity and transport. The officer report acknowledged potential effects on nearby properties but concluded that the planning benefits, including the affordable housing payment, supported approval.
The next formal steps are the GLA Stage 2 process and completion of the legal agreement, after which Hackney can issue the planning decision notice. Subsequent pre-commencement approvals would govern demolition logistics, construction management and protection of nearby TfL infrastructure.
The committee records do not identify an appointed main construction contractor. The proposed delivery sequence remains 12 months of pre-construction preparation, six months of demolition and 37 months of construction, with physical works dependent on completion of the relevant planning and technical approvals.
Steps to a start on site
11 November 2026Planning Committee resolves to grant conditional permission
12 November 2026Committee resolution published
NextStage 2 referral to the Greater London Authority
NextCompletion of the legal agreement
ThenHackney issues the planning decision notice
Before works startPre-commencement approvals for demolition logistics, construction management and protection of TfL infrastructure
LCM project record: Finsgate House
ItemDetail
Site5-7 Cranwood Street, near Old Street station, Hackney
Planning application2025/2794
DeveloperHUB
ArchitectAllford Hall Monaghan Morris (AHMM)
Scheme35-storey tower with 490 co-living units and a separate five-storey office building
WorkspaceApproximately 4,000 sq m, with 10% of the office building's workspace intended to be affordable
Planning statusResolution to grant, subject to GLA Stage 2 and a legal agreement
Main contractorNot identified in the committee records
Source: Hackney planning committee report and decision record, reviewed 14 November 2026.