London developers assessing temporary Community Infrastructure Levy relief need to distinguish the government's housing-support announcement from the regulations required to implement the concession. When LCM checked the government's consultation page on 15 November 2026, it remained labelled a closed consultation and linked to proposed amendment regulations. LCM's checks did not establish a commenced statutory instrument implementing this particular relief.
The March 2026 package therefore needs to be read alongside the subsequent July 2026 consultation. Developers considering the concession should establish the applicable legislation and obtain a scheme-specific position from the borough before treating a prospective CIL reduction as an agreed saving in a construction funding appraisal.
Tower crane above construction works in Islington, London, photographed in November 2026. The photograph illustrates London construction activity; the site pictured has not been identified as a scheme seeking Community Infrastructure Levy relief. Photo: London Construction Magazine
The proposed relief in brief
25 Mar 2026London housebuilding support package published
18 Sep 2026Consultation on the proposed regulations closed
31 Mar 2030Proposed deadline for commencement
5 yearsProposed default completion period, with potential clawback
Source: MHCLG support package and consultation. LCM's checks on 15 November 2026 did not establish a commenced statutory instrument implementing the relief.
The July consultation followed the March announcement
MHCLG published its London housebuilding support package on 25 March 2026. It combined planning measures, investment support and proposed partial relief from borough-level CIL. The document expressly identified amendments to the CIL regulations as the implementation route for the relief.
The consultation on those proposed regulations opened on 16 July 2026 and closed on 18 September 2026. Its supporting documents include draft regulations, a viability template and a statutory declaration. Those documents describe the proposed application process.
The distinction affects project cash flow. An appraisal can model potential relief as a scenario, but the commercial team needs to identify what legislative and application steps remain before that saving can be relied upon. The amount, timing and conditions of any reduction should be recorded separately from existing CIL liabilities.
Timeline
25 March 2026MHCLG publishes the London housebuilding support package
16 July 2026Consultation on the proposed amendment regulations opens
17 July 2026MHCLG corrects the proposed regulations
18 September 2026Consultation closes
15 November 2026LCM check: page still labelled a closed consultation; no commenced instrument established
31 March 2030Proposed commencement deadline for qualifying schemes
Announced, consulted or available now?
| Measure | Position on 15 November 2026 |
|---|---|
| Partial relief from borough-level CIL | Announced in the March 2026 package; implementation requires amended regulations |
| Proposed amendment regulations | Consulted on from 16 July to 18 September 2026; consultation closed |
| Commenced statutory instrument for this relief | Not established by LCM's checks |
| CIL instalment policies under regulation 69B | An existing option that boroughs can publish |
Source: MHCLG support package, consultation page and March consultation response.
Eligibility depends on more than a stalled consent
The March policy proposed relief for qualifying residential floorspace, including within mixed-use schemes. It set affordable housing requirements, land-related restrictions and a viability test. It also proposed a commencement deadline of 31 March 2030 and a default five-year completion period, with potential clawback where the required build-out is not achieved.
The proposed viability route uses a residual appraisal demonstrating that the development is unviable, supported by a declaration about the fairness and reasonableness of its inputs and assumptions. The intended test is therefore connected to the development's economics, alongside its housing commitments and other eligibility conditions.
Proposed eligibility conditions
| Condition | What the March policy proposed |
|---|---|
| Floorspace | Qualifying residential floorspace, including within mixed-use schemes |
| Affordable housing | Affordable housing requirements |
| Land | Land-related restrictions |
| Viability | A residual appraisal showing the development is unviable, with a declaration on the fairness and reasonableness of its inputs |
| Commencement | By 31 March 2030 |
| Completion | A default five-year period, with potential clawback where the required build-out is not achieved |
Source: MHCLG support package and consultation documents. These are proposals.
For a consented site, the developer's review should bring together the planning permission, Section 106 obligations, affordable housing schedule, grant assumptions and borough CIL calculation. Each needs to refer to the same development or clearly identified phases. A proposed planning variation can change the information on which the assessment depends.
A corrected grant condition shows why wording matters
MHCLG corrected the proposed regulations on 17 July 2026. The original draft referred to at least 10% of the affordable housing being free of Mayoral grant. The correction changed the reference to at least 10% of all housing units within the development, provided to satisfy the affordable housing condition, being free of that grant where the provision applies.
That changes the denominator used to assess compliance. Development teams should check the corrected text against the unit schedule and grant agreement instead of carrying an earlier summary into their appraisal. The consultation page records the correction and identifies the affected sections of the accompanying document.
The 17 July 2026 correction
| Version | Grant condition |
|---|---|
| Original draft | At least 10% of the affordable housing to be free of Mayoral grant |
| Corrected text | At least 10% of all housing units within the development, provided to satisfy the affordable housing condition, to be free of that grant where the provision applies |
Source: MHCLG consultation page. The correction changes the denominator used to assess compliance.
The wider review also needs to distinguish borough CIL, Mayoral CIL and Section 106 obligations. The proposed emergency concession concerns borough-level CIL. Any effect on another payment or affordable housing commitment needs its own supporting legal or contractual basis.
Three payments to keep separate
| Payment | Position |
|---|---|
| Borough CIL | The subject of the proposed emergency concession |
| Mayoral CIL | Outside the proposed concession |
| Section 106 obligations | Separate; any effect needs its own legal or contractual basis |
LCM summary of the distinction drawn in this article.
Keep planning milestones separate from construction readiness
The time-limited planning route has its own programme requirements. The March package describes a default early-stage review trigger based on reaching a first-floor slab milestone within 30 months of planning permission, with scope for an agreed alternative. This is a separate test from the proposed CIL commencement and completion conditions.
For contractors assessing whether a stalled scheme will restart, the useful evidence is the agreed development programme and the approvals, funding and appointments supporting it. A developer's intention to seek relief should be recorded as that intention. A borough decision, revised liability position or executed construction appointment provides a different level of evidence.
LCM recommends that any scheme-level tracker identifies the exact relief decision and conditions, alongside the planning position, financing status, contractor appointment and observed works stage. Site clearance, piling and frame construction should have separate dates and sources. None should be inferred from the publication of a housing-support policy.
What a scheme-level tracker should record
ReliefThe exact relief decision and its conditions
PlanningThe planning position
FinanceFinancing status
ContractorContractor appointment
WorksObserved works stage, with separate dates and sources for site clearance, piling and frame
None of these should be inferred from the publication of a housing-support policy.
The government's published March consultation response also confirms an existing option: boroughs can publish CIL instalment policies under regulation 69B, specifying payment amounts and timings. Developers can check that established payment route with the collecting authority while separately verifying the position on the proposed emergency relief.