The Greater London Authority said it did not hold a requested exact count and detailed list of London's planned data centres in an environmental information response dated 3 November 2026. City Hall is developing a Data Centre Monitoring Dashboard and said collection, verification and quality assurance had already taken several months.
The response, reference MGLA131026-9721, concerns a consolidated inventory covering locations, application references, floorspace, power capacity and project status. It directs readers to the Planning London Datahub for application information already received by the GLA.
Electricity transmission pylon and overhead power lines near ExCeL London, photographed in September 2026. The photograph illustrates the electricity infrastructure on which data centres depend; it does not show a data centre or a site in the GLA's planning records. Photo: London Construction Magazine
The disclosure in brief
3 Nov 2026Date of the GLA's environmental information response
Not heldThe requested exact count and detailed list of planned data centres
3Planning stages the Data Centre Monitoring Dashboard is intended to cover
2027–2050Period covered by City Hall's separate growth-forecast scenarios
Source: Greater London Authority disclosure, reference MGLA131026-9721.
The dashboard is intended to connect different planning stages
City Hall's published disclosure says the dashboard is intended to cover planning applications for existing data centres, applications awaiting determination and consented schemes awaiting completion. Its response anticipated completion of the data work in the following months, without giving a fixed launch date.
The request also asked about cumulative electricity demand and grid constraints. The GLA referred that question to its separate growth-forecast assessment. The disclosure therefore identifies a gap in the requested consolidated project information, alongside existing planning data and strategic research.
What was asked and how the GLA answered
| Requested information | GLA position |
|---|---|
| Exact count and detailed list of planned data centres | Not held; a Data Centre Monitoring Dashboard is in development |
| Locations, application references, floorspace, power capacity and project status | Readers directed to the Planning London Datahub for application information already received |
| Cumulative electricity demand and grid constraints | Referred to the GLA's separate growth-forecast assessment |
Source: GLA response dated 3 November 2026.
What the dashboard is intended to cover
| Covered, according to the disclosure | Not promised in its published scope |
|---|---|
| Planning applications for existing data centres | Confirmation of every project's financing |
| Applications awaiting determination | Confirmation of every project's contractor appointment |
| Consented schemes awaiting completion | A fixed launch date |
Source: GLA disclosure. The response anticipated completion of the data work in the following months.
Existing planning data needs checking against project records
The Planning London Datahub allows users to search applications, build queries and export data. Its own guidance says information is supplied by applicants and planning authorities and is not quality-checked as it arrives. Records may be amended following reviews or analysis that identifies deficiencies.
For a contractor assessing workload, the next check is the underlying borough record: the application, decision notice, approved scope and relevant conditions. A consented data centre can still require separate evidence of financing, a construction appointment and an electricity connection programme before its delivery prospects can be assessed.
LCM's proposed approach is to record those stages separately against each site and date every check. Application references should remain attached to the relevant proposal so amendments or successive applications are not automatically counted as additional developments.
Stages to record separately for each site
Planning permissionThe application, decision notice, approved scope and relevant conditions
ProcurementEvidence of financing and a construction appointment
Physical worksEvidence of work on site
Operational capacityAn electricity connection programme and supply
LCM's proposed approach: date every check and keep application references attached to the relevant proposal.
Growth forecasts answer a different question
City Hall describes its data-centre growth study as evidence on future scenarios for 2027–2050 and infrastructure impacts. Such scenarios support strategic planning; a construction pipeline needs dated evidence for individual sites.
LCM's July 2026 market review examined data-centre policy and infrastructure constraints. The November disclosure adds a specific monitoring issue: the GLA is still verifying the information needed for its dedicated dashboard.
For suppliers assessing a particular scheme, the useful record should distinguish planning permission, procurement, physical works and operational capacity. The dashboard described by the GLA covers planning and completion stages; its published scope does not promise confirmation of every project's financing or contractor appointment.
Three sources, three different questions
| Source | What it provides | Limit |
|---|---|---|
| Planning London Datahub | Searchable applications, queries and data export | Supplied by applicants and planning authorities; not quality-checked as it arrives |
| Data Centre Monitoring Dashboard | A consolidated view across planning and completion stages | Still in development; data being verified |
| Data-centre growth study | Future scenarios for 2027–2050 and infrastructure impacts | Strategic scenarios, not dated evidence for individual sites |
Source: GLA disclosure, Planning London Datahub guidance and City Hall's description of its growth study.