Contractors undertaking construction, demolition and infrastructure repairs in London can apply for prior consent under Section 61 of the Control of Pollution Act 1974 to agree working methods, operating hours and noise mitigation measures with the relevant local authority. The legislation establishes a 28-day decision period, but individual borough requirements can affect construction programmes considerably.
An examination by London Construction Magazine of published requirements in Westminster, Camden and Tower Hamlets on 17 November 2026 identified differences in ordinary Saturday working hours, the treatment of piling and demolition, and the circumstances under which contractors must obtain prior consent before starting work.
LCM calculates that the standard general construction working window under Tower Hamlets' 2023 Code of Construction Practice is five hours shorter per week than the corresponding general working windows in Camden and Westminster. Over a 20-week programme, this amounts to a difference of 100 potential working hours before project-specific restrictions and exceptional permissions are considered.
Construction works at 55 and 65 Old Broad Street, City of London, photographed in November 2026, illustrating the proximity of construction operations to neighbouring buildings and public highways. Photo: London Construction Magazine
Section 61 in figures
28 daysDecision period for a Section 61 application
21 daysPeriod to appeal to a magistrates' court after the initial 28 days
5 hoursShorter weekly general working window under Tower Hamlets' 2023 code
100 hoursDifference in potential working time over a 20-week programme
Source: Control of Pollution Act 1974, Section 61; LCM comparison of published borough requirements, 17 November 2026.
The difference between Section 60 and Section 61
Sections 60 and 61 of the Control of Pollution Act 1974 establish two mechanisms through which local authorities can control noise generated by construction activities.
Four routes for controlling construction noise
| Regulatory mechanism | Purpose |
|---|---|
| Section 60 notice | Allows the local authority to impose requirements controlling construction noise, including machinery, operating hours and noise levels. |
| Section 61 prior consent | Allows the person proposing the works to obtain advance agreement to specified activities and noise mitigation arrangements. |
| Planning conditions | Establish development-specific restrictions and requirements under the planning regime. |
| Variation or dispensation | Provides a route for requesting changes to existing agreed construction noise arrangements. |
Source: Control of Pollution Act 1974, Sections 60 and 61, and published local authority guidance.
Section 61 is an application mechanism rather than a universal statutory requirement for every construction site. Local authority codes, planning conditions and project-specific contractual obligations can nevertheless require contractors to obtain consent before particular activities commence.
The local authority must communicate its decision within 28 days of receiving an application. Where consent is refused, not granted within that period, or made subject to conditions or limitations, Section 61(7) provides a 21-day period following the end of the initial 28 days in which the applicant may appeal to a magistrates' court.
The expiry of the decision period does not create automatic consent. Contractors must also establish whether their planning permission permits the proposed working arrangements, as Section 61 consent does not automatically amend planning conditions or remove other statutory obligations.
The Section 61 decision clock
Day 0The local authority receives the Section 61 application
Within 28 daysThe local authority must communicate its decision
After 28 daysNo decision does not create automatic consent
Following 21 daysWhere consent is refused, not granted in time or made subject to conditions or limitations, the applicant may appeal to a magistrates' court under Section 61(7)
Construction working hours across three London boroughs
LCM compared the published construction noise requirements of Westminster, Camden and Tower Hamlets. The comparison covers general construction working windows, with additional restrictions applying to particular activities and developments.
General construction working windows compared
| Local authority | Monday to Friday | Saturday | General weekly window |
|---|---|---|---|
| Westminster | 8am-6pm | 8am-1pm, subject to activity restrictions | 55 hours |
| Camden | 8am-6pm | 8am-1pm | 55 hours |
| Tower Hamlets, 2006 code | 8am-6pm | 8am-1pm | 55 hours |
| Tower Hamlets, 2023 code | 8am-6pm | General construction requires exceptional approval | 50 hours |
Sources: published local authority construction noise guidance, checked by LCM on 17 November 2026. The figures represent general permitted time windows before breaks, bank holidays and individual site restrictions.
Westminster
Westminster's March 2026 Code of Construction Practice separates ordinary building activities from piling, excavation and demolition. These three activities are restricted to weekdays under the standard arrangements, even though other construction work may be permitted on Saturday mornings.
The council's Section 61 guidance, updated on 29 October 2026, requires Level 1 and Level 2 developments under its construction code to apply at least 28 days before commencement. Draft submissions can be prepared up to three months in advance.
The council generally applies Section 60 notices to basement developments covered by the code, a practice introduced on 2 January 2018.
Camden
Camden's construction noise guidance requires planned applications for noisy work outside ordinary working hours to be submitted at least 28 days in advance.
The council identifies external constraints, including railway possessions, road closures and safety requirements, as grounds for considering such requests. Unexpected overruns and emergencies follow a separate notification procedure, with officers retaining the ability to require noisy activities to cease.
Tower Hamlets
Tower Hamlets operates transitional arrangements between its 2006 and 2023 construction codes. According to its Construction Management Plan Service guidance, the applicable requirements depend on when planning permission was granted and the conditions attached to that permission.
The 2023 Code of Construction Practice requires strategic and major developments to obtain Section 61 consent. It also introduces restricted weekday delivery windows for construction vehicles, between 9am and noon and between 2pm and 5.30pm.
Construction management plan charges are administered separately from the statutory noise consent process. The code also provides for administration charges relating to certain variations and dispensations.
Euston: when noise consent affected a railway programme
Network Rail's preparatory works on the approach to Euston Station in October 2016 provide a documented example of the relationship between railway possessions and construction noise consent.
According to Camden Council's project update, Network Rail had informed residents about forthcoming night and weekend operations before obtaining the required Section 61 agreement. The works were subsequently postponed until consent was granted on 21 October 2016.
The consent covered initial activities between 22 October and 3 November 2016, including material movements and track maintenance. Railway operational requirements meant that some activities needed to take place outside normal construction hours.
A confirmed railway possession and an approved construction programme are separate from environmental consent. The Euston case demonstrates why these approvals need to be coordinated before contractors commit resources to restricted working periods.
Noise predictions, monitoring and BS 5228
Section 61 applications require information about the proposed works, construction methodology and measures intended to minimise noise. Local authority guidance expands these statutory requirements into more detailed technical submissions.
Westminster's March 2026 construction code references BS 5228-1:2009+A1:2014 for construction noise and BS 5228-2:2009+A1:2014 for vibration control. For larger developments, environmental assessments and monitoring arrangements are expected to address the impact on nearby occupied properties.
Tower Hamlets' Section 61 application guidance requires equipment information to be organised by construction phase. Acoustic assessments must account for simultaneous operations, including their combined effect on sensitive building façades.
The borough also expects vibration monitoring during demolition, piling and excavation, using peak particle velocity (PPV) as a measurement parameter. Noise and vibration limits must be established for the particular site and its surrounding properties; a single universal construction noise limit does not apply across London.
For contractors planning demolition and substructure packages within the London construction pipeline for 2027-2030, these environmental requirements can influence specialist appointments, monitoring budgets and the sequencing of works before mobilisation.
Changes to approved working arrangements
Section 61 consent is based on the works and methods agreed with the local authority. Changes to equipment, construction sequencing or working hours may therefore require further approval.
Westminster's October 2026 guidance establishes separate submission periods for changes to existing consents.
Westminster submission periods
| Application type | Westminster submission period |
|---|---|
| Initial Section 61 application | At least 28 days before works |
| Variation without increased noise impact | Two to seven days before works |
| Standard dispensation | At least 14 days in advance |
| Exceptional critical works beyond the applicant's control | At least 48 hours, or seven days for works lasting five days or more |
Source: Westminster City Council Section 61 guidance, updated 29 October 2026.
These periods relate specifically to Westminster's published procedure. Contractors working in other boroughs must establish the applicable local requirements before requesting alterations to previously agreed arrangements.
Westminster also operates a separate out-of-hours approval process for qualifying short-duration street works and other activities. Its published guidance identifies response targets of three working days for standard minor street or utility works and 10 working days for other qualifying activities.
Lessons from Crossrail's construction programme
Crossrail Limited examined the administration of construction noise consents in its Section 61 Consents Lessons Learned report, published on 13 March 2018.
The review involved local authorities, construction contractors, Network Rail, London Underground and Crossrail Limited. It identified difficulties coordinating noise impacts where multiple contractors occupied neighbouring or overlapping construction sites.
Recommendations included improved transfer of environmental information between successive contractors, centrally maintained consent registers and clearer allocation of responsibility for investigating noise complaints.
Crossrail's experience also identified the value of early discussions with environmental health officers before formal applications were submitted. For major infrastructure projects crossing several London boroughs, consent administration therefore becomes a programme-wide management responsibility involving the client and its delivery partners.
Under Section 61(10) of the Control of Pollution Act 1974, an applicant must take reasonable steps to communicate the consent to other parties undertaking the works. Failure to fulfil this obligation constitutes an offence under the Act.
Method and Sources
London Construction Magazine compared the published general construction working hours of Westminster, Camden and Tower Hamlets on 17 November 2026. Five weekdays of 10 hours plus five Saturday hours produce a 55-hour weekly window, compared with 50 hours under the standard weekday-only arrangements of Tower Hamlets' 2023 code. The five-hour weekly difference multiplied by an illustrative 20-week programme produces 100 hours of potential working time, before breaks, public holidays, exceptional approvals and activity-specific restrictions.