London's 2027 Infrastructure Pipeline: 10 Projects and Their Procurement Status

London's infrastructure pipeline contains projects at markedly different stages of delivery, from safeguarded railway routes without committed construction funding to major engineering schemes already employing hundreds of workers on site. For contractors preparing their 2027 order books, the procurement position of each individual project provides a more useful indication of future workload than its headline investment value.

London Construction Magazine examined 10 infrastructure schemes identified within the London Infrastructure Framework, comparing their published development programmes with client announcements, planning decisions and procurement records available on 17 November 2026.

The review identified a proposed £41.8m early works contract for the DLR extension to Thamesmead, a revised £1.25bn contract price for Edmonton's Energy Recovery Facility and several railway projects progressing through design, consultation and funding development. None of the 10 schemes produced a verified, currently open tender for its principal construction contract during LCM's review.

Aerial view of HS2's Old Oak Common station construction site in west London, one of the 10 infrastructure schemes examined in LCM's procurement review. Image source: HS2 Ltd

LCM's review in figures
10Infrastructure schemes examined from the London Infrastructure Framework
0Verified open tenders for a principal construction contract during the review
£41.8mEstimated staged early works call-off for the DLR extension to Thamesmead
£1.25bnRevised contract price for Edmonton's Energy Recovery Facility
Source: LCM review of client, planning and procurement records, 17 November 2026.

Separating the national pipeline from London's infrastructure priorities

The National Infrastructure and Service Transformation Authority (NISTA) published an updated UK Infrastructure Pipeline in March 2026 covering 734 announced projects and £718bn of projected public and private investment over the following decade.

The national dataset includes economic infrastructure projects expected to cost at least £25m and social infrastructure projects with anticipated costs of £15m or more. It covers projects under construction, schemes in development, investment programmes and proposals at earlier stages.

For London, a more geographically focused starting point is the London Infrastructure Framework, published by the Mayor of London and London Councils on 16 March 2026. The framework identifies 51 priority schemes within a wider portfolio of 150 infrastructure projects and programmes covering transport, energy, water, flood management, waste and digital connectivity.

These are separate datasets with different geographic coverage and inclusion criteria. LCM used the London framework to select the schemes examined below and checked their delivery positions against individual project records.

LCM's London infrastructure procurement review

The following table records the latest relevant evidence established during LCM's checks on 17 November 2026. Where a later project milestone could not be verified, the table identifies the date of the available client or procurement record.

10 schemes and their procurement position
ProjectClient or promoterVerified delivery positionProcurement position
Crossrail 2TfL / Department for TransportRoute safeguarding; development pausedNo committed construction funding
Bakerloo Line ExtensionTfLScheme development; further consultation expected in 2027Preferred scheme design and assessment
West London OrbitalTfL and local authority partnersDesign and public consultationUp to £6.65m development funding
DLR Thamesmead ExtensionDocklands Light Railway LimitedScheme development and early works procurement£41.8m estimated staged call-off; intended award to Amey Rail
Liverpool Street Station redevelopmentNetwork RailCommittee resolution to grant planning permission, 10 February 2026Design team appointed; main works tender not verified
HS2 Old Oak Common and London tunnelsHS2 LtdActive station and tunnelling constructionEstablished construction partners and subcontract supply chains
Euston Station CampusDepartment for Transport / Euston delivery partnersEnabling works and integrated station developmentPrivate finance and delivery arrangements under development
London Power Tunnels Phase 2National GridTunnelling completed; transmission circuits entering operationExisting £1bn project in later delivery stages
Edmonton Energy Recovery FacilityNorth London Waste AuthorityAdvanced construction; revised completion target December 2029Revised £1.25bn contract price with Acciona
Beckton Sewage Treatment Works upgradeThames WaterIdentified within AMP8 capital delivery programmeIncluded in September 2025 procurement programme; current package award not established
Source: LCM checks of client, planning and procurement records, 17 November 2026. Project values are not aggregated.

The sample includes related infrastructure programmes, particularly HS2 and Euston Station Campus. LCM has therefore avoided combining their project values into an aggregate investment figure.

The £41.8m DLR early works package

The proposed Docklands Light Railway extension from Gallions Reach to Beckton Riverside and Thamesmead provides one of the clearest examples of a London infrastructure scheme progressing towards more detailed construction procurement.

A contract award notice published on 28 October 2026 (2026/S 000-101858, OCID ocds-h6vhtk-0791f1) identifies Amey Rail Limited as the intended recipient of an early works call-off under TfL's Infrastructure Improvement Framework. The estimated contract value is £41.8m excluding VAT, covering three potential stages of delivery.

DLR early works call-off by stage
StageScopeCommercial position
1.1Mobilisation, programme review, risk assessment and survey scopingInitial contractual commitment
1.2Surveys, investigations, detailed scope and estimatingConditional progression
2Delivery of the defined early worksSubject to affordability, approvals and agreed commercial terms
Source: contract award notice 2026/S 000-101858, published 28 October 2026. The initial commitment is limited to Stage 1.1.

The notice expressly limits the initial commitment to Stage 1.1. Prices for the subsequent stages are to be developed during the initial appointment. The full £41.8m estimate therefore cannot be recorded as committed construction expenditure.

For ground investigation specialists, utility surveyors, civil engineering subcontractors and temporary works designers, the development of Stage 1.2 is a procurement milestone worth monitoring. Individual subcontract packages and their tender dates will depend on the scope subsequently agreed with the client.

LCM previously examined TfL's staged contracting arrangements in its July 2026 construction market analysis, including the Infrastructure Improvement Framework's estimated £500m to £700m capacity and its use of early contractor involvement.

Edmonton: established construction workload with revised terms

North London Waste Authority's Energy Recovery Facility at Edmonton EcoPark is already at an advanced construction stage. On 12 November 2026, the authority's members agreed revised commercial terms with Acciona, including a revised contract price of £1.25bn and a December 2029 completion target.

The authority reported that £700m had already been spent, that the turbine had been installed and that more than 400 skilled workers were attending the site daily. NLWA also identified difficulties securing specialist mechanical and electrical subcontractors during earlier stages of delivery.

A voluntary ex ante transparency notice published on 13 November 2026 concerns the proposed amendment to the existing construction agreement. Businesses monitoring the project should distinguish the revised contract arrangements from any separate procurement of mechanical installations, electrical systems or commissioning services by the established contractor.

Where suppliers can respond to published procurement notices

LCM's wider procurement search identified two separate London-related competitions with submission deadlines after 17 November 2026. These are examples of published procurement opportunities outside the 10-project main-contract sample.

Great Hall Bridge, Alexandra Palace

Haringey Council published a contract notice for the Great Hall Bridge at Alexandra Palace on 31 October 2026, with an estimated construction value of £850,000 excluding VAT (OCID ocds-h6vhtk-079454).

The works include waterproofing improvements, regulatory compliance and alterations to enable continued public access and emergency escape provision within the historic venue. The procurement uses a restricted procedure, with a published submission deadline of 27 November 2026 and an anticipated contract period from 22 January to 30 April 2027.

Interested contractors should obtain the participation requirements and procurement documents through the London Construction Programme procurement portal.

Architecture and Urbanism Framework 4

Transport for London's Architecture and Urbanism Framework 4 tender notice (2026/S 000-105635, OCID ocds-h6vhtk-06b87b) establishes a procurement route for architectural, urban design and related professional services.

The framework is intended for use by TfL, the Greater London Authority, London boroughs and other eligible public organisations, with an anticipated operating period from January 2028 to December 2031.

The notice lists nine lots and repeats an estimated maximum value of £45m across individual lots. Its additional procurement information explains that the maximum is shared across the framework and that committed expenditure arises through individual call-offs. Adding the repeated lot figures would produce a misleading workload estimate.

The procurement selection questionnaire submission deadline is noon on 22 December 2026. Suppliers should register through the SAP Business Network, using TfL project reference WS2588285274 and following the access instructions in the tender notice.

Accessing established infrastructure supply chains

HS2 illustrates how substantial future workload can remain available through subcontract procurement after the principal construction contracts have been awarded. At Old Oak Common, station platforms, structural works, building services and connections to the existing railway are progressing under established delivery arrangements.

HS2 publishes information on its indirect contract opportunities page, including awarded specialist packages and routes for accessing further supply-chain competitions through CompeteFor. Published subcontract records can help suppliers identify which organisations control particular work packages.

The approach complements LCM's planning-to-procurement intelligence guide, which explains how to match development records with named buyers, consultants and contractors before individual packages reach the market.

For the proposed West London Orbital, the next public milestone is the closure of TfL's first consultation on 18 November 2026, ahead of a targeted decision in late 2027 on whether to seek statutory construction powers through a Transport and Works Act Order.

Dates for suppliers to note
18 November 2026West London Orbital: TfL's first consultation closes
27 November 2026Great Hall Bridge, Alexandra Palace: published submission deadline
22 December 2026Architecture and Urbanism Framework 4: procurement selection questionnaire deadline, noon
22 January to 30 April 2027Great Hall Bridge: anticipated contract period
2027Bakerloo Line Extension: further consultation expected
Late 2027West London Orbital: targeted decision on seeking a Transport and Works Act Order
January 2028Architecture and Urbanism Framework 4: anticipated start of operating period
December 2029Edmonton Energy Recovery Facility: revised completion target

Method and Sources
London Construction Magazine selected 10 infrastructure schemes from the March 2026 London Infrastructure Framework portfolio and checked their client, planning and procurement records on 17 November 2026. Each scheme was counted once, with no aggregation of project values because of overlapping programme scopes and different financial definitions. Zero of the 10 schemes produced a verified open principal construction tender during the review; the two separately identified procurement competitions are excluded from that calculation.