London accounted for about 88% of England’s annual fall in net additional dwellings in 2025-26, according to London Construction Magazine calculations using figures published by the Ministry of Housing, Communities and Local Government on 26 November 2026. The capital added 28,170 homes to its dwelling stock, down from about 32,680 in 2024-25, while England’s total fell from a revised 208,820 to 203,690.
A second set of figures points further upstream. The Greater London Authority recorded 21,665 net residential starts in 2024-25, compared with 48,962 in 2022-23, a 56% fall across two years. The national release measures changes in housing stock; the GLA start figures measure an earlier stage of construction. Read together, they show why a strong borough completion total is a poor substitute for evidence of current work reaching site.
Residential high-rise construction in London, photographed on 25 September 2026. Official housing figures show a decline in the capital’s net housing additions, while separate GLA data points to a longer-term reduction in residential construction starts. Photograph: © 2026 London Construction Magazine. All rights reserved.
London housing supply in figures
88%London’s share of England’s fall in net additional dwellings, 2025-26
28,170Net additional dwellings in London in 2025-26, down about 13.8%
21,665GLA-recorded net residential starts in 2024-25, down 55.8% in two years
53.9%2025-26 net additions as a share of the annualised London Plan target
Sources: MHCLG housing supply release, 26 November 2026; GLA Planning London Datahub; London Plan 2021. Shares and percentages are LCM calculations.
London accounted for most of England’s annual reduction
England’s 2025-26 net housing supply fell by 5,130 dwellings on the revised MHCLG series. London’s contribution to that fall was about 4,510 dwellings. Subtract London from England and the remainder of the country recorded a decrease of approximately 620 dwellings across the same year. LCM calculates that London therefore accounted for around 87.9% of the national contraction, using the published numbers rounded to the nearest 10.
Net additional dwellings, 2024-25 and 2025-26
| Area | 2024-25 net additions | 2025-26 net additions | Annual change |
|---|---|---|---|
| England | 208,820 | 203,690 | -5,130 |
| London | 32,680 | 28,170 | -4,510 |
| England excluding London | 176,140 | 175,520 | -620 |
Source: MHCLG, Housing supply: net additional dwellings, England, 2025 to 2026. The England excluding London row and the annual changes are LCM calculations from published figures rounded to the nearest 10.
That calculation changes the significance of the national 2% headline. England’s decline was relatively modest in aggregate, but London’s net additions fell by about 13.8%. The figures describe additions to the dwelling stock after gains from new building, conversion and change of use have been balanced against demolitions. They are not a count of construction sites opened or of main contracts awarded.
Starts had already slowed sharply before the latest completions
The GLA’s Affordable Housing in Planning Applications Referred to the Mayor report records the following net residential starts in the Planning London Datahub. The reported 2024-25 level was 27,297 homes below 2022-23, a 55.8% decline calculated by LCM. These are GLA planning-data records, with a different collection method from MHCLG’s net-additions statistics.
Net residential starts recorded by the GLA
| Financial year | Net residential starts recorded in Planning London Datahub | Change against previous year |
|---|---|---|
| 2022-23 | 48,962 | - |
| 2023-24 | 27,386 | -21,576 |
| 2024-25 | 21,665 | -5,721 |
Source: GLA, Affordable Housing in Planning Applications Referred to the Mayor. Year-on-year changes are LCM calculations.
The same GLA report records 31,770 net residential completions in 2024-25 and describes the conversion of approved housing into delivered homes as being affected by construction costs, interest rates, development scale, site infrastructure and the mix of tenures. It also records a net conventional residential pipeline of 277,552 homes as at March 2025. A consented pipeline of that scale can coexist with a much smaller stream of homes reaching construction and completion.
Contractors reading the 2025-26 stock figures should therefore separate three questions: where homes were added to the register during the year, where sites have actually begun construction, and where a client has confirmed funding, an appointed contractor and a package procurement route. Each needs its own dated evidence. LCM explored the same distinction in its earlier examination of why large London housing schemes keep pausing.
Three questions, three sets of evidence. Where were homes added to the register during the year? Where have sites actually begun construction? Where has a client confirmed funding, an appointed contractor and a package procurement route? A borough’s net-additions total answers only the first.
The borough figures conceal different kinds of activity
Only 13 of London’s 33 borough and City authorities recorded an increase in net additional dwellings between 2024-25 and 2025-26, MHCLG reports. Greenwich, Brent, Hammersmith and Fulham, Tower Hamlets and Redbridge were among England’s 50 highest authorities for net additions per 1,000 existing dwellings. At the other end, the City of London recorded just 0.4 per 1,000, the second-lowest rate in England.
Ten London authorities were among England’s bottom 50 by that stock-adjusted measure: the City of London, Kensington and Chelsea, Havering, Richmond upon Thames, Bromley, Lambeth, Lewisham, Sutton, Islington and Waltham Forest. This is a rate comparison, not a ranking of total homes built. A smaller local dwelling stock can change the rate markedly, and an individual regeneration phase can lift annual net additions after several years of construction.
The City’s low ratio, for example, cannot be read as evidence that every type of building project in the Square Mile is inactive. Equally, a high 2025-26 housing-additions rate in Greenwich or Brent does not show how many 2026 construction starts have occurred there. Borough-level claims about current work require matching the MHCLG local-authority net-additions tables with the GLA’s recorded starts, project status and actual commencement dates.
Gateway 2 remains a constraint, although approvals are improving
Building Safety Regulator approval remains a statutory hold point before construction of higher-risk buildings can begin. Its effect is concentrated on schemes that fall within the higher-risk building regime, so it cannot explain low-rise housing delivery across every London borough. Planning permission, Gateway 2 approval, a contractor appointment and physical commencement are separate events.
The regulator’s August-to-October 2026 transparency release shows that 40 of 42 new-build Gateway 2 decisions in the rolling 12 weeks to 1 November 2026 were approvals, an approval rate of 95%, with a median approval time of 20 weeks. These are national new-build Gateway 2 decisions, not a London-specific estimate of delayed homes. The latest performance also contrasts with the much lower approval rates and longer determination times reported in 2025.
Twenty weeks remains an important pre-construction programme period for an affected project, but the 2025-26 net-additions data does not attribute individual missing completions to a specific regulator, viability problem or site. The GLA identifies several delivery influences, including development costs, interest rates, land ownership, market absorption, infrastructure and the time large sites take to build out. LCM’s Gateway 2 Approval Index tracks the regulator’s decisions separately from evidence of starts on site.
The annual London Plan comparison
The adopted 2021 London Plan sets a ten-year housing target of 522,870 homes for 2019-20 to 2028-29, averaging 52,287 a year. London’s 28,170 net additional dwellings in 2025-26 equal 53.9% of that annualised benchmark, a difference of 24,117 homes. This is an LCM scale comparison, not a formal Housing Delivery Test result: London Plan monitoring and the MHCLG dwelling-stock series differ in their treatment of some forms of accommodation and reporting detail.
Another caution comes from the government’s own interim Energy Performance Certificate model. MHCLG’s revised September 2026 estimate for London’s 2025-26 net additions was 31,400, while the annual release recorded 28,170, a difference of 3,230. That is an 11.5% overestimate measured against the published outturn. A forecasting proxy can therefore overstate the amount of housing added even before a commercial team tries to infer the level of construction work still to come.
What the figures mean for London contractors
A specialist contractor deciding where to spend estimating time needs a live-stage record as well as an annual delivery number. For a proposed residential frame, façade or M&E package, useful evidence includes the original planning reference, discharged pre-commencement conditions, Gateway 2 decision where required, procurement notice or contractor appointment, and a direct confirmation of the package’s status. None can be supplied by the borough’s net-additions total.
This is especially important on multi-phase sites. A block completed during 2025-26 may belong to an earlier main contract, while a later phase remains in design, funding negotiation or building-control assessment. The live opportunity for a contractor lies in the later phase only if its client, scope, programme and procurement route can be established. LCM has previously reported project-level examples in its coverage of Canada Water and Lewisham housing delivery pauses.
For public clients and housing associations, check current capital programmes and actual procurement notices; for private developments, verify the contracting route and whether specialist works have been let. A company might have a large historic delivery programme without an open tender, just as an authority with low annual net additions may still have refurbishment, remediation and infrastructure contracts progressing on site.
What would demonstrate a recovery
The first useful signal would be a sustained rise in GLA-recorded residential starts across successive reporting periods, supported by identifiable projects reaching commencement. The next would be more confirmed main contracts and specialist package invitations, with planning and Gateway permissions matched to actual site activity. Later MHCLG net-additions data would show whether those starts ultimately became additions to the housing stock.
For now, the verified sequence is clear: GLA-recorded starts fell from 48,962 in 2022-23 to 21,665 in 2024-25; London then recorded 28,170 net additions in 2025-26; and the regulator approved 40 new-build Gateway 2 cases in the 12-week period to 1 November 2026. Those figures each describe a different stage, and none establishes how many London specialist packages are currently open for tender.
Three figures, three stages
2022-23 to 2024-25GLA-recorded net residential starts fall from 48,962 to 21,665
2025-26London records 28,170 net additional dwellings, down from about 32,680
12 weeks to 1 November 2026The Building Safety Regulator approves 40 of 42 new-build Gateway 2 decisions, nationally
Sources: GLA; MHCLG; Building Safety Regulator. Each figure describes a different stage of delivery.
Method and Sources
LCM used MHCLG’s housing supply release published on 26 November 2026, the adopted London Plan housing target and the GLA Planning London Datahub series cited in the GLA housing delivery report, checking the source material on 29 November 2026. England’s annual fall is 208,820 minus 203,690, or 5,130; London’s is 32,680 minus 28,170, or 4,510. London’s share of the fall is 4,510 divided by 5,130, or 87.9%; values are approximate because the source series presented here is rounded to the nearest 10. The separate decline in recorded net residential starts is (48,962 minus 21,665) divided by 48,962, or 55.8%, between 2022-23 and 2024-25.