The Department for Energy Security and Net Zero reported 8,983 homes with external wall insulation remediation still incomplete under the ECO4 and Great British Insulation Scheme programmes, in a release published on 26 November 2026. Work had been completed and evidence signed off at 2,227 properties, following an inspection programme covering installations across England, Scotland and Wales. The figures are based on TrustMark records at 4 November 2026.
The new Find and fix programme data covers 24,615 properties offered free on-site audits after earlier checks found widespread defects in government-funded solid wall insulation. It reports 11,141 completed audits, including 9,288 properties with major technical faults and 1,111 where immediate health and safety risks were identified. The latest figures establish the scale of the remaining inspection and repair task, but the audit and remediation categories require careful reading.
External facade construction in London, photographed in November 2026. The image illustrates building-envelope installation and quality assurance as the UK addresses defects identified in government-funded wall insulation programmes. The photographed building is not identified as an ECO4 or GBIS remediation project. Photograph: © 2026 London Construction Magazine. All rights reserved.
Find and fix in figures
8,983Properties with remediation not yet complete at 4 November 2026
2,227Properties with remediation completed and evidence signed off
45.3%Share of the 24,615 eligible properties with a completed audit
83%Completed programme audits recording major technical faults
Source: Department for Energy Security and Net Zero, Find and fix programme release, 26 November 2026, from TrustMark records. The 45.3% is an LCM calculation.
Fewer than half of eligible properties have been audited
The Find and fix programme began on 17 November 2025 and focuses on external wall insulation installed under ECO4 and GBIS at properties that had not previously received a qualifying audit. The 24,615-property programme scope sits within 33,839 external wall insulation measures installed under those schemes; the two figures have different definitions.
By 4 November 2026, TrustMark had contacted 19,216 eligible households, 14,335 had accepted audit appointments and 3,194 appointments were booked but still awaiting completion. London Construction Magazine calculates that 45.3% of the eligible properties had received a completed programme audit, while approximately 78.1% had been contacted. Those percentages measure programme progress, not the prevalence of faulty insulation among all British homes.
Find and fix programme at 4 November 2026
| Find and fix measure | Position at 4 November 2026 |
|---|---|
| Programme reach | |
| Unique eligible properties | 24,615 |
| Households contacted | 19,216 |
| On-site audits completed | 11,141 |
| Audits scheduled, awaiting completion | 3,194 |
| Audit findings | |
| Major technical faults recorded | 9,288 |
| Immediate health and safety risks recorded | 1,111 |
| Remediation | |
| Unique properties requiring remediation | 11,064 |
| Remediation completed and evidence signed off | 2,227 |
| Properties with remediation not yet complete | 8,983 |
Source: Department for Energy Security and Net Zero, from TrustMark records at 4 November 2026. Some properties hold more than one status, so the categories cannot be added together.
Among the programme audits completed, DESNZ reports 83% with major technical non-compliance and 10% with immediate health and safety risks, with 77 properties recorded as compliant and 669 having minor faults. These results concern households audited through the Find and fix programme. They should not be extrapolated as a new national rate for every wall insulation installation.
Why the repair totals need separate treatment
London Construction Magazine compared the three figures in the department’s remediation table: 11,064 unique properties identified as requiring work, 2,227 with remediation completed and 8,983 with work not yet complete. Adding the latter two statuses produces 11,210, which is 146 more than the unique properties requiring remediation. The department says some properties have multiple recorded audit or remediation statuses, so the categories do not operate as two mutually exclusive groups.
LCM calculates that completed, signed-off work amounts to about 20.1% of the unique properties identified as requiring remediation. That is a progress comparison using the published denominator, not a final proportion of cases permanently closed. The non-completion figure remains 8,983 in the official release; subtracting completed work from the total to invent a different outstanding figure would conceal the department’s recording method.
Why the remediation figures do not add up. 2,227 completed plus 8,983 not yet complete gives 11,210, which is 146 more than the 11,064 unique properties requiring work. Some properties hold more than one recorded status, so the two counts are not mutually exclusive groups.
The distinction also prevents a misleading comparison with older government repair totals. The November 2026 release covers the defined external wall insulation Find and fix programme, whereas previous reports included remediation activity from other audits or broader insulation cohorts. No directly comparable earlier Find and fix repair series is presented in the new release.
The 92% failure finding was published in 2025
The original DESNZ statistical audit report was published in October 2025 and subsequently updated in November 2025. It used randomised samples of 378 external and 380 internal solid wall insulation installations. The report found major technical non-compliance in 92% of external and 27% of internal installations, alongside separate immediate health and safety categories of 6% and 2% respectively. Those figures were known before the 26 November 2026 update.
The earlier audit used PAS 2035 assessment standards and classified failures according to their likely effect on insulation performance or occupants. The House of Commons Public Accounts Committee linked poor-quality installations with risks including water ingress, condensation, mould and inadequate ventilation. Its January 2026 report questioned whether the existing system could inspect and remediate affected homes quickly enough.
The November 2026 programme results answer a different question: how far the inspection and repair response has progressed. Their 83% major-fault and 10% immediate-risk categories come from the Find and fix audit records, not the two original randomised samples. The two sets of percentages should therefore be labelled separately in construction quality reporting.
Two sets of percentages, two different questions
| Measure | 2025 statistical audit | Find and fix programme |
|---|---|---|
| What it covers | Randomised samples of 378 external and 380 internal wall insulation installations | 11,141 completed audits of external wall insulation |
| Major technical non-compliance | 92% external, 27% internal | 83% |
| Immediate health and safety risk | 6% external, 2% internal | 10% |
| Published | October 2025, updated November 2025 | 26 November 2026 |
Sources: DESNZ statistical audit results and DESNZ Find and fix programme release. The two sets of figures use different populations and should not be compared as a trend.
What contractors and retrofit clients should verify
The recorded faults concern building fabric quality and the evidence used to demonstrate compliance. For a remedial external wall insulation package, a contractor or client needs a building-specific schedule identifying the observed defect, the original system and installation documentation, the required corrective scope, responsibility for inspection and the evidence for completion sign-off. Moisture management, ventilation and the integrity of interfaces with existing openings are important areas for competent investigation where the survey identifies related concerns.
LCM previously examined installation competence and documented quality assurance in its London retrofit contractor analysis. Its separate review of the 2026 electrification roadmap considered the relationship between fabric upgrades, ventilation and wider building-performance requirements. Neither a government grant nor the presence of an accredited installer replaces inspection of the actual work and a traceable close-out record.
This Find and fix response concerns ECO4 and GBIS domestic wall insulation. It is separate from the statutory remediation programmes for unsafe cladding on taller residential buildings. For employers pricing retrofit repairs, the published national figures establish a substantial technical workload, but they do not identify available London tenders, awarded subcontract values or borough-specific repair allocations.
How affected households can arrange a check
The government advice for households with poor-quality wall insulation says eligible recipients of external wall insulation under ECO4 and GBIS are offered a home check by qualified professionals. Where faulty work is found, the original installer is asked to rectify it, and households should not be asked to pay for those repairs. Residents can contact Ofgem through the official guidance, including its freephone helpline on 0808 169 4447, to check correspondence or raise concerns.
The Public Accounts Committee called for stronger consumer protection when installers or guarantees cannot meet the cost of repairs. The government’s 2026 consultation on home-upgrade consumer protections addresses the wider assurance system. ECO4 has been extended to 31 December 2026 for the orderly completion of its remaining obligations; the government has not extended GBIS on the same basis.
How the programme reached this point
October 2025DESNZ publishes its statistical audit, finding major technical non-compliance in 92% of sampled external wall insulation installations
17 November 2025The Find and fix programme begins
January 2026The Public Accounts Committee reports on faulty energy efficiency installations
4 November 2026Date of the TrustMark records used in the latest release
26 November 2026DESNZ publishes the Find and fix figures: 11,141 audits completed and 8,983 properties with remediation not yet complete
31 December 2026Extended end date for ECO4
Sources: DESNZ; House of Commons Public Accounts Committee.
Method and Sources
LCM used the Department for Energy Security and Net Zero’s Find and fix statistics published on 26 November 2026, covering records from 17 November 2025 to 4 November 2026, and checked the source on 29 November 2026. Completed audits divided by eligible properties were 11,141 / 24,615 = 45.3%; contacted properties were 19,216 / 24,615 = 78.1%; and completed remediation divided by unique properties requiring work was 2,227 / 11,064 = 20.1%. The two published remediation status counts sum to 11,210, exceeding the unique-property total by 146 because the department allows multiple statuses per property.