London Planning: 96% 'On Time', Just 11% Within 13 Weeks

London boroughs recorded an average 96.2% of major planning applications decided within the statutory period or an agreed extended deadline in the 12 months to June 2026, but only 10.7% were decided within the statutory 13-week period. The figures appear in a Camden Council planning performance report considered on 12 November 2026 and expose a substantial difference between the measure used to assess council performance and the time developers may actually spend waiting for decisions.

Camden itself reported 96.9% of major decisions within the statutory or agreed period, against 3.1% within 13 weeks. The figures concern planning decisions and agreed extensions of time, including Planning Performance Agreements, and do not measure the time subsequently needed for discharge of conditions, building control approval, contractor procurement or construction commencement.

Bank Junction in the City of London, showing historic commercial buildings, the Bank Underground station entrance and a construction crane in the background, photographed in April 2026. Photo: London Construction Magazine

The planning performance gap in figures
96.2%London borough average: major applications decided within the statutory or an agreed period
10.7%London borough average: decided within the statutory 13 weeks
85.5Percentage-point difference between the two measures, LCM calculation
60%Government's minimum performance threshold for major applications
Source: Camden Council Development Management Performance Report, 12 November 2026. Figures cover the 12 months to June 2026.

For London developers and contractors, the distinction affects the point at which a proposed scheme can be treated as a credible construction opportunity. A council can meet its nationally assessed planning performance target while an individual application remains in the planning process for considerably longer than 13 weeks.

London's planning performance gap

Camden's Development Management Performance Report, prepared for its Planning Committee on 12 November 2026, compares major application decisions made within statutory or agreed timescales with those determined within the statutory period alone.

The report gives London-wide and Inner London borough averages alongside Camden's own performance for the 12 months ending June 2026. LCM calculated the percentage-point difference between the two measures for each geographical grouping.

Two measures of an on-time decision
AreaWithin 13 weeks or agreed periodWithin statutory 13 weeksDifference
London boroughs average96.2%10.7%85.5 percentage points
Inner London boroughs average93.58%4.5%89.08 percentage points
Camden96.9%3.1%93.8 percentage points
Source: Camden Council; differences calculated by LCM. London and Inner London figures are borough averages.

The London and Inner London figures are borough averages reported by Camden, not percentages calculated by pooling every major application across the capital. The percentage-point differences compare the two published measures; they are not a separate count of applications with extensions of time.

Camden says the statutory-or-agreed measure is used when assessing whether councils meet the government's minimum performance threshold of 60% for major planning applications. The stricter 13-week measure is monitored separately. The council also reports that its legal service completed 141 Section 106 agreements in 2025/26, including 26 relating to major developments.

The national figures tell a similar story

The Ministry of Housing, Communities and Local Government's April to June 2026 planning applications statistical release, published on 24 September and corrected on 29 October 2026, recorded 91% of major applications in England decided within 13 weeks or an agreed extended period. Only 19% were determined within the statutory 13 weeks.

That represents a 72-percentage-point difference between the two national measures during the quarter. The release also reported that 77% of major decisions involved a performance agreement, a category covering Planning Performance Agreements, Extensions of Time and Environmental Impact Assessments.

England's district planning authorities decided approximately 74,500 applications between April and June 2026, down 8% against the equivalent quarter of 2025. London accounted for approximately 14,100 decisions, of which around 11,800 were granted, giving the capital an 84% grant rate across all application categories.

Those national quarterly figures and the London borough averages cover different reporting periods. The national comparison relates to April to June 2026, while Camden's London comparison covers the 12 months ending June 2026. Neither dataset measures construction starts.

England, April to June 2026
FigureWhat it describes
91%Major applications decided within 13 weeks or an agreed extended period
19%Major applications determined within the statutory 13 weeks
72 pointsDifference between the two national measures
77%Major decisions involving a performance agreement
74,500Approximate applications decided by district planning authorities, down 8% on the equivalent quarter of 2025
14,100Approximate decisions in London, of which around 11,800 were granted, an 84% grant rate
Source: MHCLG statistical release, published 24 September and corrected 29 October 2026. A different reporting period from the London borough averages.

How an agreed extension changes the deadline

The government's planning practice guidance, updated on 8 April 2026, specifies a 13-week statutory determination period for major development applications, with 16 weeks applying where an Environmental Impact Assessment is required. A longer period can be agreed in writing between the applicant and the local planning authority.

A Planning Performance Agreement may establish a timetable before an application is submitted, covering technical consultation, design amendments and the preparation of legal agreements. An Extension of Time can also be agreed after a valid application has entered the determination process. The agreed timetable may subsequently be amended by written agreement between the parties.

A council determining an application within that agreed period can record the decision as on time for national performance reporting. The resulting percentage therefore measures compliance with the applicable determination timetable, which may extend well beyond the original statutory period.

The agreements have a purpose. Major developments can require amendments following consultation, further environmental assessment, transport negotiations and legally enforceable planning obligations. Camden's November report specifically identifies the time required to complete Section 106 agreements as an issue being examined through its planning improvement work.

Which deadline applies
RouteDetermination period
Major development13 weeks, the statutory period
Major development requiring Environmental Impact Assessment16 weeks
Planning Performance AgreementA timetable that may be established before submission
Extension of TimeA longer period agreed in writing after a valid application has entered determination
Source: government planning practice guidance, updated 8 April 2026. A decision within the agreed period can be recorded as on time.

Three London schemes show different delivery stages

The difference between a planning submission, a committee resolution and construction commencement can be seen in three substantial London development projects. Their published records show why each milestone needs its own date and evidence. These are individual project examples, not a statistical sample of the applications included in the April to June 2026 national dataset.

Earls Court: a committee resolution after an extended application process

The Earls Court Development Company submitted proposals covering the former exhibition centre site across Kensington and Chelsea and Hammersmith & Fulham in 2024. Kensington and Chelsea's application record PP/24/05187 gives a validation date of 22 July 2024, followed by consultation on amended proposals between 5 September and 10 October 2025.

The Royal Borough of Kensington and Chelsea's Planning Committee resolved to approve the proposals on 16 December 2025, subject to the subsequent Mayoral planning process. The hybrid application includes detailed proposals for 310 homes in the first phase and outline proposals for wider residential, commercial and cultural development.

LCM calculates that 512 days elapsed between the recorded validation date and the committee resolution. The proposals were subject to Environmental Impact Assessment, so the applicable statutory starting point was 16 weeks. The elapsed period measures those two documented milestones and does not establish whether the council complied with any separately agreed determination deadline.

Beckton Riverside: two committee stages before legal completion

Beckton Riverside Phase 1, promoted by St William on the former gasworks site in Newham, illustrates the additional stages that can follow a borough committee decision. The GLA's planning chronology records validation of applications 24/00989/OUT and 24/00990/FUL on 25 October 2024.

Newham's Strategic Development Committee resolved to grant permission on 23 October 2025. The Mayor called in the applications on 27 April 2026, and Deputy Mayor Jules Pipe resolved to grant permission following a representation hearing on 7 September 2026, subject to completion of a Section 106 agreement.

The two applications cover an outline residential-led scheme of up to 2,977 homes and detailed proposals for site preparation. LCM calculates 682 days between the original validation and the Mayoral resolution. The GLA's published hearing documents contain draft decision notices and a draft legal agreement, while the Mayoral resolution establishes a further legal stage before the permission can be formally issued.

Battersea: a confirmed construction start

Prospect Place South at Battersea Power Station provides a different form of evidence. On 9 September 2026, Battersea Power Station Development Company and Sisk announced that construction had begun on two Gehry Partners-designed buildings, Rosewood House and Hayworth House.

Wandsworth Council confirmed the construction commencement on 10 September 2026, identifying Sisk as main contractor. The phase will provide approximately 300 homes, 65,000 sq ft of commercial accommodation and a 15,000 sq ft community hub, with completion expected in 2030.

Battersea's developer separately submitted a revised masterplan application on 14 September 2026 for the remaining 16 acres of the wider estate. The two records concern different development stages on the same regeneration site: construction of an existing phase and planning proposals for future phases.

Three schemes, three stages
SchemeLatest recorded milestoneInterval or status
Earls CourtCommittee resolution to approve, 16 December 2025, subject to the Mayoral planning process512 days from validation on 22 July 2024, LCM calculation
Beckton Riverside Phase 1Mayoral resolution to grant, 7 September 2026, subject to a Section 106 agreement682 days from validation on 25 October 2024, LCM calculation
Prospect Place South, BatterseaConstruction start announced on 9 September 2026, with Sisk as main contractorCompletion expected in 2030
Individual project examples, not a statistical sample. The intervals do not establish compliance with any agreed determination deadline.

What the figures mean for contractors

For London contractors assessing a forward order book, a planning application awaiting determination carries a different level of programme certainty from a development with a formal decision notice, discharged pre-commencement conditions and an appointed main contractor. Even an approved scheme may still require further design work, utility agreements, procurement or statutory building control approvals before construction begins.

A committee resolution to grant permission may depend on the completion of a Section 106 agreement. Outline permission can also leave reserved matters to be approved before the relevant works proceed. For higher-risk buildings, Gateway 2 approval introduces a separate building control decision before regulated construction work can commence.

LCM's London Stalled Projects and Delivery Risk Tracker examines the wider consequences of projects remaining between planning, procurement and physical delivery. The tracker distinguishes planning delay from the further technical and commercial risks that may affect mobilisation or a construction restart.

For developers and project teams, a planning programme can be tested against several separate dates: validation, the original statutory determination deadline, each written extension, committee consideration, completion of legal agreements and issue of the formal decision notice. The construction programme then needs its own evidence for conditions, building control, procurement and the actual start of works.

Camden's November 2026 performance report makes the distinction especially visible. The borough recorded 96.9% of major applications within statutory or agreed timescales during the 12 months to June 2026, with 3.1% decided inside the statutory 13-week period. National performance reporting recognises the agreed timetable, while developers and contractors still have to manage the elapsed period between submission and a decision capable of supporting construction.

Dates to test a planning programme against
ValidationThe date the application is recorded as valid
Statutory deadlineThe original 13-week or 16-week determination date
ExtensionsEach written extension of time
CommitteeThe date of committee consideration
Legal agreementsCompletion of the Section 106 agreement
Decision noticeIssue of the formal decision notice
The construction programme then needs its own evidence for conditions, building control, procurement and the actual start of works.

Method and Sources
LCM reviewed Camden Council's Development Management Performance Report dated 12 November 2026, the corrected MHCLG April to June 2026 statistical release and the cited project records on 15 November 2026. Percentage-point gaps were calculated by subtracting the statutory-period result from the statutory-or-agreed-period result for each published geography, retaining Camden's description of the London and Inner London figures as borough averages. Project intervals were calculated as elapsed calendar days between Earls Court's recorded validation on 22 July 2024 and committee resolution on 16 December 2025, and between Beckton Riverside's validation on 25 October 2024 and Mayoral resolution on 7 September 2026. These project intervals measure documented planning milestones and do not establish compliance with individual extension-of-time agreements.