Hackney Council has accepted a conditional £22.7m grant offer from the Greater London Authority (GLA) to support 102 social and affordable homes across four housing regeneration projects, under London's £11.7bn Social and Affordable Homes Programme 2026-36. The decision, approved on 5 November 2026, provides an early example of how the new funding programme is moving from capital allocations towards individual housing schemes, although the grant remains subject to funding agreements and delivery milestones.
Croydon Council also approved acceptance of a GLA funding offer on 29 October 2026, with authority delegated to finalise the agreement and amend its programme submissions. Together, the two decisions provide an opportunity to examine what funding recipients must establish before grant-supported housing can progress into construction, including land control, planning status, contractor procurement and evidence of a start on site.
London Cable Car terminal at Greenwich Peninsula, with 6 Mitre Passage and surrounding modern developments, photographed in September 2026. Photo: London Construction Magazine
The first grant decisions in figures
£22.7mConditional GLA grant offer accepted by Hackney Council
102Social and affordable homes across four Hackney regeneration projects
40%Share of requested affordable homes funded on Hackney's three Band B schemes
£4.7bnMaximum available in later years through Continuous Market Engagement
Source: Hackney Council delegated powers report HCE S787, 5 November 2026.
The GLA's revised London Social and Affordable Homes Programme 2026-36 funding guidance, updated in February 2026, establishes the rules for securing grant and meeting development milestones. Funding is available for schemes capable of starting on site by March 2036 and reaching practical completion by March 2039.
Hackney's £22.7m offer exposes the funding gap
Hackney Council's delegated powers report HCE S787, dated 5 November 2026, records a conditional GLA offer issued on 1 October 2026. The £22.7m capital grant supports 102 homes within four housing regeneration projects, following an initial bidding process that the council says was substantially oversubscribed across London.
The offer comprises one fully funded Band A project and three partially funded Band B projects. For the Band B schemes, the GLA offered funding for 40% of the affordable homes for which grant had been requested. Hackney intends to use Right to Buy receipts to support the unfunded homes and maintain the financial viability of the developments.
The council's report also records a construction procurement connection between two of the projects. The fully funded development is being delivered alongside one of the partially funded schemes, and both have been procured jointly from the construction market. Officers rejected accepting only the fully funded element because delivery of the two projects depends on their joint procurement arrangements.
That distinction has commercial consequences for contractors. A funding decision covering only part of a development may require the client to identify additional subsidy, amend its business case or confirm other capital contributions before committing to the next contract stage. In Hackney's case, the council has identified Right to Buy receipts as its intended source for the remaining affordable housing funding requirement.
The public report places the project-by-project allocations in an exempt appendix. It confirms four regeneration projects and their combined funding offer, but does not identify the four sites individually or provide construction-start dates for each scheme.
Croydon approves a separate GLA funding offer
Croydon Council approved acceptance of its London Social and Affordable Homes Programme funding offer through executive decision 2815 on 29 October 2026, published the following day. The published decision record authorises the Corporate Director of Housing to finalise the funding agreement and submit revised information to the GLA's Open Project System (OPS), including amendments relating to Band B allocations.
The decision was handled under urgency procedures because the GLA required Croydon to confirm its position and resubmit amended programme information by 5 November 2026. The council's call-in period expired on 9 November, and the decision became effective on 10 November 2026.
Croydon's public record says affordable housing delivery in the borough fell from 631 homes in 2022/23 to 113 homes in 2025/26. It identifies a cumulative shortfall of approximately 794 affordable homes over the period. The financial details of the new allocation are contained in exempt material accompanying the decision.
LCM's review of the Hackney and Croydon decision records on 15 November 2026 establishes that both authorities had formally accepted conditional funding offers, with Hackney's decision dated 5 November and Croydon's decision effective from 10 November. The records establish grant acceptance and associated delegated authority; they do not record physical construction starts arising from those funding decisions.
Two council decisions compared
| Hackney | Croydon | |
|---|---|---|
| Decision record | Delegated powers report HCE S787 | Executive decision 2815 |
| Approved | 5 November 2026 | 29 October 2026; effective 10 November 2026 |
| Offer | £22.7m for 102 homes across four regeneration projects | Financial details in exempt material |
| Band B | Three partially funded projects, with 40% of the requested affordable homes funded | Amendments relating to Band B allocations to be submitted through OPS |
| Not public | The four sites and project-by-project allocations | The amount of the allocation |
| Construction starts recorded | None | None |
Source: Hackney and Croydon decision records, reviewed by LCM on 15 November 2026.
What providers must demonstrate before construction
The GLA assesses London Social and Affordable Homes Programme bids against three principal criteria: value for money, deliverability and strategic fit. The February 2026 guidance requires providers to demonstrate that the grant requested meets the subsidy gap in their affordable housing proposals, supported by development costs, other funding contributions and expected income.
For named schemes, the GLA considers the development's planning position, land ownership and certainty of delivery within the proposed programme. Its bidding guidance, published on 9 March 2026, also requires applicants to provide their current contractor procurement status through OPS.
The documents create a useful evidence sequence for assessing when a grant-supported scheme is likely to generate construction activity.
From grant to start on site
| Delivery stage | Evidence to establish | Construction significance |
|---|---|---|
| Grant allocation | Named project approval, agreed grant amount, funding contract and delivery milestones | Establishes the subsidy available to support the project's financial appraisal |
| Land and development control | Freehold, sufficient leasehold interest or an enforceable acquisition arrangement | Supports the provider's ability to deliver the identified site and claim eligible grant |
| Planning and regulatory position | Planning decision, relevant conditions and applicable building control or Building Safety Regulator approvals | Establishes which statutory approvals have been secured before controlled construction activities proceed |
| Contractor procurement | Procurement status, tender outcome, contract appointment and agreed construction programme | Identifies the appointed delivery organisation and the maturity of the construction commitment |
| Start on site | Evidence satisfying the GLA funding contract's start-on-site milestone | Supports the contractual grant drawdown and records progression into delivery |
LCM evidence sequence drawn from the GLA funding and bidding guidance.
For higher-risk residential buildings, the regulatory evidence also needs to establish the appropriate Gateway 2 position. A funding allocation, planning consent or contractor appointment cannot replace Building Safety Regulator approval where that approval is required before building work starts.
The distinction is examined in LCM's earlier analysis of affordable housing funding and construction delivery, which considered the gap between government programme announcements and the release of actual construction packages.
Grant payments begin before site mobilisation
The GLA's funding arrangements allow grant payments at land acquisition, start on site and practical completion. Under the February 2026 guidance, strategic partners are generally expected to receive 60% of their grant at land acquisition, 20% at start on site and 20% at practical completion.
For non-strategic partners, the expected payment profile is 40% at land acquisition, 35% at start on site and 25% at practical completion. The GLA may agree flexibility where an alternative payment structure can bring projects forward sooner or reduce the subsidy requirement.
These payment profiles demonstrate why a grant drawdown cannot automatically be counted as evidence of building work having started. A provider may receive an agreed proportion of subsidy at the land acquisition stage while design development, statutory approvals and contractor procurement continue.
The guidance also specifies that grant payments are made only against schemes approved by the GLA as named projects. Providers holding indicative programme allocations must progress the relevant homes into approved named projects before receiving scheme-level payments.
When grant is expected to be paid
| Provider | Land acquisition | Start on site | Practical completion |
|---|---|---|---|
| Strategic partners | 60% | 20% | 20% |
| Non-strategic partners | 40% | 35% | 25% |
Source: GLA funding guidance, February 2026. The GLA may agree an alternative payment structure. A drawdown is not evidence that building work has started.
The difference between named projects and indicative allocations
The London Social and Affordable Homes Programme allows providers to seek funding through named project bids or indicative allocations. A named project identifies a specific site, although the provider may still be progressing its acquisition. An indicative allocation supports longer-term development capacity and can cover projects that have not reached the same level of definition.
Providers seeking indicative allocations must identify the number of homes they expect to deliver by financial year and tenure, alongside evidence from their development pipeline and business planning. The GLA may withdraw indicative funding where the expected homes do not start on site in the agreed year or the provider cannot demonstrate sufficient delivery capacity.
This distinction affects how contractors should interpret affordable housing announcements. A strategic partnership allocation can support a substantial future programme without confirming the location, procurement stage or main contractor for every proposed development.
For firms targeting council and housing association work, named schemes with established land control, an advanced planning position and identified procurement arrangements provide a firmer basis for assessing opportunities than indicative housing totals alone.
Named projects and indicative allocations
| Named project | Indicative allocation | |
|---|---|---|
| What it identifies | A specific site, although acquisition may still be in progress | Homes expected by financial year and tenure |
| Evidence | Planning position, land ownership and certainty of delivery | Development pipeline and business planning |
| Grant payments | Paid against schemes approved as named projects | Homes must first progress into approved named projects |
| Risk | Contractual delivery milestones for each project | Funding may be withdrawn if homes do not start on site in the agreed year |
Source: GLA funding guidance, February 2026.
The subsidy scheme has passed its regulatory stage
The original November 2025 GLA funding guidance described the programme as an advance draft while the subsidy control assessment was being completed. That position changed in February 2026 after the Competition and Markets Authority's Subsidy Advice Unit published its final report on 3 February 2026.
The GLA's revised guidance confirms that the Subsidy Advice Unit process was completed and that the London Social and Affordable Homes Programme 2026-36 subsidy scheme had been made. Providers remain responsible for complying with the programme's subsidy conditions and providing accurate records of actual project costs and income.
That completed programme-level process sits separately from individual grant agreements, planning decisions and construction approvals. Each recipient must still meet the conditions attached to its funding and the statutory requirements applicable to its development.
Up to £4.7bn remains for future funding rounds
The first London bidding window opened on 24 February 2026 and closed on 15 April 2026. After substantial overbidding, applicants were invited to revise their submissions, with a further deadline of 20 May 2026. In a written answer dated 22 September 2026, the Mayor said he intended to offer initial allocations of at least £6bn to providers.
Hackney's November 2026 report records confirmation from the GLA that up to £4.7bn would be available over the following years through Continuous Market Engagement (CME). That programme route is intended to support further named projects and allow providers to bring additional schemes forward after the initial allocation process.
The report also says that further funding could become available if initial recipients do not enter contracts or if the overall programme receives additional government funding. Hackney intends to continue seeking support through CME for schemes and affordable homes that did not secure full grant coverage in the first round.
The GLA's funding guidance establishes 31 March 2036 as the final deadline for funded projects to start on site and 31 March 2039 as the completion deadline. Each approved named project will have its own contractual delivery milestones, with grant payments linked to the agreed stages of land acquisition, start on site and practical completion.
Timeline
November 2025GLA funding guidance issued as an advance draft
3 February 2026Subsidy Advice Unit publishes its final report
24 February 2026First London bidding window opens
9 March 2026GLA bidding guidance published
15 April 2026Bidding window closes
20 May 2026Deadline for revised submissions after overbidding
22 September 2026Mayor says he intends to offer initial allocations of at least £6bn
1 October 2026GLA issues its conditional offer to Hackney
29 October 2026Croydon approves acceptance of its offer
5 November 2026Hackney approves acceptance of its £22.7m offer
31 March 2036Final deadline for funded projects to start on site
31 March 2039Completion deadline