London is preparing a new market for sustainable drainage works, with the Greater London Authority (GLA) targeting up to 100 schemes by April 2031 through its SuDS through Streetworks Market programme. Mayoral Decision MD3529, signed on 5 August 2026, authorised receipt and expenditure of up to £4.19m for programme delivery and staffing, following a £6.87m Ofwat Innovation Fund award to the partnership led by Thames Water.
The programme will allow utility companies and their contractors to offer sustainable drainage systems (SuDS) alongside planned excavations, with organisations seeking flood-risk reduction paying for verified results. Two market rounds are planned around the Central and Lee Valley catchments, and the GLA has published a supplier guide explaining how contractors can identify eligible sites, prepare fixed-price offers and compete for work.
The programme was in mobilisation when LCM checked its published arrangements on 15 November 2026. The target of 100 schemes represents planned market delivery, with individual works contracts dependent on buyer funding, successful matching, design and approvals.
Streetworks and temporary construction barriers on Waterloo Place, St James's, central London, photographed in August 2026. Photo: London Construction Magazine
The SuDS market in figures
100Schemes targeted by April 2031
£6.87mOfwat Innovation Fund award to the partnership led by Thames Water
£4.19mGLA receipt and expenditure authorised by MD3529
2Market rounds planned, around the Central and Lee Valley catchments
Source: GLA Mayoral Decision MD3529. The 100-scheme figure is a target for planned market delivery.
Where the funding sits
The GLA's mayoral decision MD3529, published on 6 August 2026, records an Ofwat Innovation Fund award of £6,869,054 to the partnership. The GLA was allocated £4,050,376 for its activities, with a further £140,000 contribution arrangement bringing its authorised funding receipt and expenditure to £4,190,376.
Thames Water's 19 May 2026 announcement gives a total project value of £7,632,283. That is a broader project-value figure than the Ofwat grant. The GLA's authorised expenditure covers programme and staffing costs, including the market's development, coordination and monitoring activities.
The GLA will manage the programme through its Infrastructure Coordination Service, working with Thames Water and participating organisations. MD3529 says specialist consultancy support will be procured as required, while physical infrastructure will be delivered through participating suppliers and their contractors.
Where the funding sits
| Figure | What it is |
|---|---|
| £6,869,054 | Ofwat Innovation Fund award to the partnership |
| £4,050,376 | GLA allocation for its activities |
| £140,000 | Further contribution arrangement |
| £4,190,376 | GLA authorised funding receipt and expenditure |
| £7,632,283 | Total project value given by Thames Water, a broader figure than the Ofwat grant |
Sources: MD3529, published 6 August 2026; Thames Water, 19 May 2026.
How contractors will compete for drainage work
The GLA's SuDS through Streetworks Market Suppliers Guide sets out a competitive system connecting organisations that want to purchase runoff reduction with suppliers already planning streetworks.
Buyers can include local authorities, water companies and other flood-risk management organisations. Suppliers are principally utility companies, highway authorities, infrastructure providers and their delivery partners. The market operator will oversee bidding, matching, contracting, accreditation and verification.
Before a market round, suppliers identify suitable opportunities within their forward streetworks programmes and prepare concept designs using the market's technical standards. The eligible-area dataset assesses locations against constraints including road width, traffic arrangements, existing trees and buried infrastructure.
During a market round, suppliers submit fixed-price offers for selected projects. Buyers identify the areas where they want drainage improvements and the maximum price they are willing to pay for reductions in surface-water runoff. The market operator then matches offers with available funding, taking account of the location, price and runoff-reduction benefit.
The supplier guide requires an offer to cover the full additional cost of the SuDS element, including design, materials, construction, integration with existing streetworks, consents, traffic management, specialist subcontractors, verification, contingency and commercial margin. Suppliers fund their initial concept design preparation, and submitting a proposal does not guarantee that it will be selected.
This provides two potential routes for construction companies. Organisations promoting their own streetworks may be able to submit suitable SuDS projects directly into the market. Specialist drainage, landscaping and civil engineering subcontractors could secure packages through participating utilities or their existing delivery partners. The guide says suppliers remain responsible for managing their subcontractors and incorporating the required standards into delivery arrangements.
Contractors seeking to prepare for the market can review the published supplier guidance and contact the GLA programme team at SSM@london.gov.uk. The approved programme timetable schedules its formal launch for February or March 2027; the public documents checked on 15 November 2026 did not identify an open construction-package tender or the closing dates for the two market rounds.
How a market round works
Before the roundSuppliers identify opportunities in their forward streetworks programmes and prepare concept designs at their own cost
OffersSuppliers submit fixed-price offers covering the full additional cost of the SuDS element
BidsBuyers name the areas they want improved and the maximum price they will pay for runoff reduction
MatchingThe market operator matches offers with funding on location, price and runoff-reduction benefit
DeliveryThe supplier builds the scheme and manages its subcontractors to the required standards
VerificationCredits are issued after construction and verification by the market operator
Source: GLA Suppliers Guide. Submitting a proposal does not guarantee that it will be selected.
Five drainage systems are eligible
The GLA has developed technical guidance around five eligible SuDS types: rain gardens, tree pits, permeable paving, swales and filter drains. Each manages runoff differently, so the selected system will depend on the available space, drainage catchment, buried services and the requirements of the highway authority.
Rain gardens use planted beds and engineered soil layers to intercept and store water. Tree pits can incorporate storage around tree-rooting areas. Permeable paving allows water to enter the storage layers beneath the surface, while swales use vegetated channels or depressions and filter drains provide below-ground storage and drainage through granular material.
The construction interfaces will be familiar to highway and public-realm contractors. Kerb levels, falls, existing services, excavation depth, pavement construction, pedestrian routes and maintenance access all affect the feasibility of integrating drainage into a planned reinstatement.
LCM examined related design conflicts in Public Realm Specification in 2026: HVM, SuDS and Active Travel, where drainage, underground utilities and public-space requirements can compete within the same pavement footprint.
The five eligible systems
| System | How it manages runoff |
|---|---|
| Rain gardens | Planted beds and engineered soil layers intercept and store water |
| Tree pits | Storage can be incorporated around tree-rooting areas |
| Permeable paving | Water enters the storage layers beneath the surface |
| Swales | Vegetated channels or depressions |
| Filter drains | Below-ground storage and drainage through granular material |
Source: GLA technical guidance, as described in this article.
Three completed pilots show the cost differences
The earlier development phase produced three completed SuDS pilots in Merton, Croydon and Kingston upon Thames between April 2025 and May 2026. Thames Water and the GLA published their final project evaluation, revision 4.0, on 29 May 2026, recording the individual scheme costs and lessons from construction.
Three completed pilots
| Pilot location | Reported scheme cost | Recorded delivery evidence |
|---|---|---|
| Lower Green West, Merton | £120,840.74 | The evaluation attributes the higher cost to technical difficulties encountered during delivery. |
| St Andrews Road, Croydon | £26,982.68 | The project benefited from lessons learned in Merton, including delivery coordination. |
| Richmond Road, Kingston upon Thames | £18,155.65 | Shallow underground utilities led to a redesign from a tree pit to shrub-based planting. |
Source: Thames Water and GLA final project evaluation, revision 4.0, 29 May 2026. Combined reported cost: £165,979.07, LCM calculation. These are not standard rates.
LCM's calculation from the three reported scheme costs gives a combined pilot cost of £165,979.07. The final evaluation separately reports £147,823 of expenditure against its original piloting workstream and describes additional council funding for the Kingston scheme, including a £9,077.83 reimbursement agreed by Thames Water.
The individual costs cannot be used as standard rates for future rain gardens or drainage installations because the schemes had different scopes and site conditions. The evaluation attributes the variation partly to technical complexity, traffic sensitivity, utility interfaces and local delivery requirements.
Kingston provides a particularly relevant construction example. Site investigations identified shallow utility assets that restricted the depth available for the proposed tree pit. The design was subsequently changed to shrub-based planting to manage the risk to existing services while retaining a drainage and greening function.
The final report also records that all three pilots tested the single-contractor delivery model, in which the utility's contractor undertakes the planned works and incorporates SuDS into reinstatement. It identifies maintenance responsibility, asset constraints and early communication with residents among the lessons for future delivery.
How construction quality and drainage performance will be verified
The new market will use Reduction in Surface Water Volume (RSWV) credits to quantify the runoff that a completed SuDS installation prevents from entering the drainage system. The supplier guidance measures this in cubic metres using a standard design calculation based on a 40 mm rainfall event.
The calculation combines water intercepted and stored at the surface, water held in subsurface storage layers and runoff lost through infiltration. The credited volume is limited by the amount of runoff available from the contributing catchment. A larger physical drainage feature therefore does not automatically generate a larger eligible credit if its catchment cannot supply the required water.
For contractors, the inspection process will include checking that the completed installation matches the approved design. The supplier guide identifies inspection, quality assurance, as-built documentation, defect management and handover among the delivery requirements. Market credits are issued after construction and verification by the market operator.
Maintenance must also be addressed before long-term handover. The GLA's Buyers Guide requires ownership and maintenance responsibilities to be established, while the supplier guidance describes a defects liability period followed by handover to the agreed adopting organisation.
The distinction between design capacity and verified construction is central to the commercial model. Suppliers are contracted to deliver an agreed design specification, and the market operator will manage adjustments if the accredited runoff-reduction outcome differs from the original estimate. The published guidance does not require suppliers to guarantee performance beyond the agreed design and verification process.
How a runoff-reduction credit is measured
| Element | Detail |
|---|---|
| Unit | Reduction in Surface Water Volume (RSWV), in cubic metres |
| Design event | A standard calculation based on a 40 mm rainfall event |
| Components | Water intercepted and stored at the surface, water held in subsurface storage layers and runoff lost through infiltration |
| Limit | The runoff available from the contributing catchment |
| Issue | After construction and verification by the market operator |
Source: GLA Suppliers Guide.
What the programme could change for streetworks contractors
London undertakes approximately 186,000 streetworks annually, according to Thames Water's May 2026 announcement. The proposed market is designed to identify a proportion of that existing excavation activity where additional drainage works could be incorporated without requiring a separate road-opening programme.
The GLA's earlier analysis estimated that coordinated SuDS delivery could produce approximately 27% cost efficiencies and avoid an average of more than 20 days of disruption per project. These are modelled potential benefits recorded in MD3529, with the planned market rounds intended to test actual costs, delivery performance and outcomes.
For contractors, the procurement model introduces a different commercial test from a conventional drainage works tender. The supplier must identify an opportunity within planned streetworks, prepare a compliant design and offer a price that competes against other suppliers on runoff reduction and delivery cost. The model also creates a route for specialist subcontractors through utilities and their established streetworks supply chains.
This proposed investment sits alongside the wider Thames Water infrastructure programme examined in LCM's reporting on Thames Water's financing and construction commitments. Funding for the SuDS market has been awarded through the Ofwat Innovation Fund, but individual drainage contracts will depend on the market's separate buyer commitments and procurement processes.
The scale and the modelled benefits
| Figure | What it describes |
|---|---|
| 186,000 | Approximate streetworks undertaken in London each year, according to Thames Water |
| 27% | Approximate cost efficiencies estimated for coordinated SuDS delivery |
| 20+ days | Average disruption avoided per project in the same analysis |
Sources: Thames Water, May 2026; MD3529. The efficiency and disruption figures are modelled potential benefits, to be tested by the market rounds.
The delivery timetable to 2031
The GLA's approved timetable places programme mobilisation in September 2026, with specialist technical resources scheduled to start between September and December 2026. The formal market launch was planned for February or March 2027, followed by market development, bidding, matching and project delivery activities extending into 2031.
The first delivery areas are the Central and Lee Valley catchments, where the GLA plans to establish the governance, funding arrangements and supplier capability needed for two market rounds. The programme's scheduled delivery end date is April 2031, with a final evaluation and closure report due in the same month.
Timeline
April 2025 to May 2026Three pilots completed in Merton, Croydon and Kingston upon Thames
19 May 2026Thames Water announces the funding
29 May 2026Final project evaluation, revision 4.0, published
5 August 2026Mayoral Decision MD3529 signed; published the following day
September 2026Programme mobilisation
September to December 2026Specialist technical resources scheduled to start
February or March 2027Formal market launch planned
April 2031Scheduled delivery end date, with a final evaluation and closure report
Method and Sources
LCM reviewed the GLA's Mayoral Decision MD3529, the published market guidance and the Thames Water/GLA final evaluation, revision 4.0, on 15 November 2026. The three completed pilot costs were taken from page 17 of the evaluation, issued on 29 May 2026, and added without adjusting for separate funding contributions or reimbursements. The resulting £165,979.07 represents the combined reported costs of the Merton, Croydon and Kingston schemes, not expenditure charged exclusively to the evaluation's P2 workstream. The funding figures and delivery programme were checked separately against MD3529, published on 6 August 2026.