Oxford Street's £144m Plan: Who Approves Work and Where Contracts Stand

The Oxford Street Development Corporation (OSDC) has controlled planning applications within its designated area since 10 August 2026, but the next phase of construction on London's principal shopping street will depend on decisions made by several different authorities. Transport for London controls the main highway, Westminster and Camden continue to administer Community Infrastructure Levy payments, and the OSDC is developing the permanent public-realm programme against a capital budget of approximately £144m.

London Construction Magazine's examination of the statutory orders, OSDC's final March 2026 budget and published procurement records identifies the division of responsibilities facing developers and contractors. The capital spending plan totals £144.3m across 2025/26 to 2030/31, with £83.6m, approximately 58%, scheduled for 2028/29 onwards. An engineering services contract was awarded in October 2026, but LCM has not established a publicly confirmed main construction contract for the permanent public-realm transformation as of 14 November 2026.

That separation has a direct effect on project delivery. A developer may obtain planning permission from the OSDC while still needing approval from TfL for construction access, a separate building control decision and a levy assessment from the relevant borough. For companies seeking public-realm work, the OSDC's budget provides an indication of future investment, while the individual procurement notices determine which work is actually available.

Oxford Street near Oxford Circus, showing road traffic, pedestrians and the existing streetscape before the traffic-free section began operating in October 2026. The photograph was taken on 16 October 2026 and documents the street before the latest public-realm changes. Photo: London Construction Magazine

Oxford Street in figures
£144.3mCapital spending plan, 2025/26 to 2030/31
£83.6mScheduled for 2028/29 onwards, about 58% of the plan
10 Aug 2026Planning powers transferred to the OSDC
Midnight to 7amServicing window on the traffic-free section
Sources: OSDC final 2026/27 budget, March 2026; Functions Order 2026 (SI 2026/831); TfL delivery and servicing arrangements. Totals and percentage calculated by LCM.

Planning powers have moved, but the boundary matters

The OSDC was established on 1 January 2026 under the Oxford Street Development Corporation (Establishment) Order 2025. The subsequent Functions Order 2026 (SI 2026/831) transferred local planning authority responsibilities from Westminster City Council and the London Borough of Camden on 10 August 2026.

The transfer covers the defined Oxford Street Mayoral Development Area, which includes Oxford Street and adjoining parts of Westminster and Camden. It does not extend to every property in either borough or every side street approaching Oxford Street. Applicants must check the official boundary map before choosing the authority responsible for a particular site.

Within that boundary, the OSDC determines planning applications and relevant listed building consents, manages planning enforcement and deals with planning conditions and obligations. Its planning service provides the boundary map, application register and submission guidance. New applications are lodged through the national Planning Portal, selecting the OSDC as the local planning authority.

Applications submitted to Westminster or Camden before 10 August 2026 but still awaiting determination generally transferred to the OSDC under the Functions Order's transitional provisions, subject to statutory exceptions. The OSDC applies the existing Westminster or Camden development plan policies, alongside the London Plan and relevant neighbourhood planning policies, while preparing its own Local Plan.

The corporation's draft local validation checklist was approved for consultation by its Board on 18 June 2026. Its planning website still described consultation as forthcoming when checked on 14 November, so applicants should use the current published submission requirements and seek pre-application advice directly from the OSDC for complex proposals.

Oxford Street timeline
September 2025Highway redesignation makes TfL the highway authority for Oxford Street
1 January 2026OSDC established under the Establishment Order 2025
24 March 2026Board considers the final 2026/27 budget; Director Decision DD2796 on CIL functions signed
18 June 2026Board approves the draft local validation checklist for consultation
10 August 2026Planning authority functions transfer from Westminster and Camden to the OSDC
19 October 2026Find a Tender notice records the Norman Rourke Pryme engineering appointment
26 October 2026Oxford Street becomes traffic-free between Orchard Street and Great Portland Street
2027Further permanent improvements programmed
2030/31Final year of the capital spending plan

Who approves each stage of construction?

LCM's comparison of the September 2025 highway redesignation, the August 2026 planning transfer and the March 2026 CIL decision identifies the principal approval routes for work within and around the development area.

Approval routes in and around the development area
Decision or activityResponsible authorityWhat the applicant needs to establish
Planning permission within the MDAOSDCSite boundary, applicable planning policies, validation and decision requirements.
Listed building consent and relevant planning conditionsOSDC within the MDAHeritage permissions, approved alterations and the status of outstanding conditions.
Borough and Mayoral CIL administrationWestminster or Camden, according to site locationChargeable floorspace, applicable schedules, liability notices and relief claims.
Highway occupation and works on designated GLA RoadsTfLRoadworks permits, temporary structures, traffic arrangements and construction access.
Works on designated GLA Side RoadsTfL for traffic functions; relevant borough for retained highway functionsWhether both highway licensing and traffic-management approval are needed.
Undesignated borough streetsWestminster or CamdenStreet-specific highway occupation, traffic orders and temporary works permissions.
Building controlRelevant borough building control service, registered building control approver or BSR, depending on building typeBuilding Regulations compliance and the appropriate statutory approval route.
Public construction contract awardOSDC, TfL or another named public buyerThe actual procurement notice, contracting authority, scope and award stage.
Source: LCM comparison of the highway redesignation, the planning transfer and the CIL decision.

The distinction between GLA Roads and GLA Side Roads is particularly relevant to scaffolding, hoardings, mobile cranes, temporary loading arrangements and utility works. TfL is the highway authority for Oxford Street itself following the September 2025 redesignation, but on designated GLA Side Roads it may hold traffic authority powers while Westminster retains highway authority functions. Contractors therefore need to establish the legal designation of the precise working area rather than rely on the property's planning authority.

Why Westminster and Camden still collect development levies

Planning powers transferred to the OSDC, but Community Infrastructure Levy functions did not. GLA Director Decision DD2796, signed on 24 March 2026, restricts the corporation from exercising CIL functions until a charging schedule for the Mayoral Development Area is approved and takes effect. Westminster and Camden continue to act as charging and collecting authorities within their respective parts of the area.

For a development requiring planning permission inside the MDA, this can mean applying to the OSDC while dealing separately with Westminster or Camden over CIL liability and payment. Mayoral CIL requirements also continue to apply where relevant. Section 106 planning obligations remain part of the OSDC's development management responsibilities, although agreements may involve other public authorities where their interests or infrastructure are affected.

The same separation applies to building control. The Functions Order transferred planning functions but did not transfer general Building Act responsibilities to the OSDC. Ordinary building work follows the relevant local authority or registered building control approver route, while qualifying higher-risk building work is controlled by the Building Safety Regulator. Planning consent from the OSDC does not replace those separate statutory approvals.

The £144m budget is spread across six financial years

The OSDC's final 2026/27 budget, considered by its Board on 24 March 2026, contains a capital spending plan for the initial Oxford Street West transformation. The programme covers pedestrianisation between Orchard Street and Great Portland Street and related infrastructure works, with an expected capital requirement of approximately £144m to 2030/31.

Table 5 of the budget identifies £2.7m as the forecast 2025/26 capital outturn, £27.1m budgeted for 2026/27 and further planned expenditure of £30.9m in 2027/28, £46.7m in 2028/29, £17.8m in 2029/30 and £19.1m in 2030/31. The six figures total £144.3m. Of that amount, £83.6m falls in the final three financial years, equivalent to approximately 57.9% of the overall plan.

OSDC capital spending plan by year
Financial yearAmountBasis
2025/26£2.7mForecast outturn
2026/27£27.1mBudget
2027/28£30.9mPlanned
2028/29£46.7mPlanned
2029/30£17.8mPlanned
2030/31£19.1mPlanned
Total£144.3m£83.6m, about 57.9%, falls in the final three years
Source: Table 5 of the OSDC final 2026/27 budget. Total and share calculated by LCM. A spending profile, not a list of construction contracts.

This is a spending profile, not a list of construction contracts. The largest annual allocation, £46.7m in 2028/29, points to the scale of delivery expenditure anticipated after the initial design and traffic-management stages, but individual contract scopes, award values and actual expenditure must be established separately. The March budget envisages funding the capital programme principally through borrowing, with the corporation developing potential commercial contributions and other income.

A separate Mayoral Decision MD3445, signed on 25 November 2025 and published on 11 May 2026, approved transferring £6.29m from GLA Group reserves to TfL in 2025/26. That allocation supported programme acceleration and road maintenance and improvement following the highway redesignation. It cannot be added to the £144.3m capital plan as an additional construction contract without reconciling the underlying programme accounts.

Which companies have actually been appointed?

The Oxford Street public-realm programme has moved through technical requirements and design procurement. Under GLA decision DD2733, expenditure of up to £74,700 was approved for Publica Associates Limited to prepare Phase 1 technical requirements through the GLA Architecture and Urbanism Framework. That work helped define the requirements for subsequent design and engineering.

East and Hawkins\Brown have also been identified by the OSDC as members of the public-realm design team. Their work includes developing the transitional street environment and the permanent design response to the operation of the traffic-free section. The corporation's 26 October 2026 announcement confirms their continuing involvement.

A more recent procurement record identifies a specific engineering appointment. Find a Tender notice 2026/S 000-098717, published on 19 October 2026, records a contract for Norman Rourke Pryme Limited to support the permanent scheme's engineering development. The contract has a ceiling of £75,000 excluding VAT, with an initial instructed value of £56,257, and runs from 20 October 2026 to 19 May 2028.

The services cover RIBA Stages 2 and 3, coordination with East, engagement with TfL and review of subsequent detailed design by others. The appointment is an engineering services call-off under an existing framework. It does not appoint Norman Rourke Pryme to construct the permanent public realm.

LCM's review of the identified procurement and governance records up to 14 November 2026 did not establish an awarded main construction contract for the permanent Oxford Street West public-realm works. The OSDC and TfL have been progressing temporary arrangements following the traffic-free launch, while further permanent improvements are programmed for 2027. The eventual procurement structure and confirmed tender timetable remain important information for contractors seeking the larger civil engineering packages.

Appointments identified in the public-realm programme
FirmRolePublished value or term
Publica AssociatesPhase 1 technical requirements, through the GLA Architecture and Urbanism FrameworkUp to £74,700 approved under DD2733
East and Hawkins\BrownPublic-realm design team-
Norman Rourke PrymeEngineering services for the permanent scheme, RIBA Stages 2 and 3Ceiling £75,000 excluding VAT; initial instructed value £56,257; 20 October 2026 to 19 May 2028
Main construction contractorPermanent Oxford Street West public-realm worksNo awarded contract established by LCM as of 14 November 2026
Source: GLA decision DD2733, OSDC announcement of 26 October 2026 and Find a Tender notice 2026/S 000-098717.

Private development is already producing construction work

Oxford Street's wider construction market includes projects commissioned by private landlords and developers. Derwent London appointed Kier to deliver Holden House on the corner of Oxford Street and Rathbone Place, with the contractor confirming the appointment on 11 August 2026. The £98.95m scheme involves a substantial redevelopment behind retained historic façades, creating approximately 135,000 sq ft of commercial accommodation.

Kier said works were commencing in August 2026, with superstructure construction targeted for spring 2027 and completion expected in 2028. The development's Oxford Street frontage brings the contractor's deliveries, temporary works and pedestrian arrangements into close contact with TfL's highway operating requirements. It is a privately commissioned development, separate from the OSDC public-realm construction programme.

British Land has also appointed McLaren Construction under a reported £99m design-and-build contract at 75 Davies Street, above West One Shopping Centre and Bond Street Underground Station. Designed by Allford Hall Monaghan Morris, the redevelopment combines retained structure with new construction and additional office floors. Its construction requirements involve an occupied commercial location and transport infrastructure beneath the building.

Private schemes on the Oxford Street corridor
SchemeClientContractorPublished valueProgramme
Holden House, Oxford Street and Rathbone PlaceDerwent LondonKier£98.95mWorks from August 2026; superstructure targeted for spring 2027; completion expected in 2028
75 Davies Street, above West One Shopping CentreBritish LandMcLaren ConstructionReported £99m design-and-build contract-
Sources: Kier announcement, 11 August 2026; published report on the British Land appointment. Both are separate from the OSDC public-realm programme.

These private projects demonstrate that work around the Oxford Street corridor does not depend exclusively on the timing of the public-realm main contract. They also show why contractors need to distinguish the client's building project from TfL's highway controls and the relevant planning authority's statutory decisions.

The overnight servicing window changes construction planning

Oxford Street became traffic-free between Orchard Street and Great Portland Street on 26 October 2026. TfL's delivery and servicing arrangements allow authorised servicing vehicles to enter that section between midnight and 7am using designated routes. Emergency vehicles retain access, while general traffic, including cycles, is excluded from the traffic-free section.

For construction contractors, a seven-hour servicing window can affect how materials, plant and waste are moved through a working site. Large mechanical equipment, structural steel, glazing, fit-out materials and skips may require separate planning for vehicle arrival, unloading, lifting and storage. Restrictions on noisy work, permitted working hours and highway occupation still need to be addressed individually.

The highway arrangements are not uniform across all surrounding roads. TfL's designated GLA Road network, designated GLA Side Roads and ordinary borough streets have different legal responsibilities. Contractors preparing hoarding layouts, crane operations or delivery management plans should establish which authority controls the precise location of each proposed activity before finalising the construction logistics plan.

LCM previously examined the immediate effect of the Oxford Street servicing restrictions on construction operations and subsequently photographed the first week of the traffic-free street. Those reports found that road-space changes had moved ahead of the permanent streetscape. The current procurement records establish more precisely which design and engineering appointments support the next phase.

Where contractors can identify the next work packages

The most direct route into publicly procured Oxford Street construction will be through the contracting authority responsible for each package. The OSDC publishes governance and financial material through its corporate publications and Board records, including its Contracts and Funding Code, capital budget and reports on programme delivery. Its Board approves major spending decisions, while smaller appointments can be made under delegated authority.

Contractors can also monitor Find a Tender and Contracts Finder for OSDC, TfL and related public-sector procurements. The Norman Rourke Pryme award illustrates why exact notice references matter: the published contract records the buyer, supplier, engineering scope, value ceiling and contract period. Its existing framework route also shows that not every new contract is offered as an unrestricted public competition.

For specialists not already appointed to a relevant framework, potential work may arise through the supply chains of the design consultants, civil engineering delivery partners or main contractors eventually selected. Public-realm construction could involve paving, drainage, utilities, lighting, landscaping, street furniture, accessibility measures and traffic infrastructure, although the final work packages and responsible contractors must be verified when procurement documents are published.

The next material procurement development will be a confirmed works tender or contract award defining who is responsible for delivering the permanent public realm, how the packages are divided and the anticipated construction programme. The OSDC's March 2026 capital plan provides the spending profile through 2030/31, while its October 2026 engineering appointment demonstrates that the permanent design programme is continuing ahead of those larger construction decisions.

Method and Sources
London Construction Magazine compared the OSDC's March 2026 final capital spending plan with the statutory planning and highway decisions and procurement records available on 14 November 2026. The six annual capital figures in Table 5 of the budget total £144.3m. The planned amounts for 2028/29, 2029/30 and 2030/31 total £83.6m; dividing £83.6m by £144.3m gives 57.9%. These figures describe the OSDC's budgeted and forecast capital expenditure, including the earlier forecast outturn, rather than construction contracts awarded or money actually paid.