London's Billion-Pound Frameworks: Who Won Work and Where to Look Next

Five awarded construction frameworks available to public-sector buyers in London carry published estimated values ranging from £350m to £3bn, but the contracts placed through them tell a more complicated story. London Construction Magazine's examination of procurement records on 14 November 2026 identified a £200m housing major-works appointment in Haringey and two Transport for London project awards carrying published values of £85m and £41.8m. The TfL figures include potential later stages, while the Haringey appointment belongs to a different London Construction Programme framework from the one most recently awarded.

For construction businesses assessing public-sector workload, these distinctions affect which contractors have secured appointments, which work has been instructed and where future subcontract packages may emerge. LCM examined Transport for London's Infrastructure Improvement Framework, two separate London Construction Programme frameworks operated by Haringey, the Greater London Authority's RE:FIT 5 programme and Fusion21's Responsive Repairs and Void Property Framework. The records establish the supplier appointments and several identifiable projects, although a complete financial ledger of call-offs and expenditure could not be reconstructed for all five.

Under section 45 of the Procurement Act 2023, a framework provides for the future award of contracts to appointed suppliers. The Cabinet Office's framework guidance explains that authorities generally do not commit to awarding work simply by establishing the agreement. The estimated framework value therefore records anticipated procurement capacity across its term, not an amount already committed to the suppliers named in the award notice.

Farringdon Street viewed north from Holborn Viaduct in the City of London, with commercial office buildings, street works and temporary barriers visible. The photograph illustrates London's built environment; the works pictured have not been identified as part of the construction frameworks examined in this article. Photographed in October 2026. Photo: London Construction Magazine

Frameworks and contracts in figures
5Awarded frameworks examined by LCM
£350m to £3bnRange of published estimated framework values
£200mHaringey housing major-works contract, as reported by United Infrastructure
£85mSouth Kensington published value, including an optional second stage
Source: procurement records examined by LCM on 14 November 2026. Framework estimates are not amounts committed to suppliers.

What five major frameworks actually establish

LCM selected five awarded frameworks with relevance to London's construction, infrastructure, housing maintenance and public-building markets. Their published values relate to different geographical areas and time periods, and the two national frameworks are available to London buyers without their entire estimated values being attributable to London projects.

Five frameworks compared
Awarded frameworkPublished estimated valueSupplier appointmentsProject evidence identified
TfL Infrastructure Improvement Framework£700m excluding VATAmey Rail, Costain and DragadosDLR Thamesmead early works and South Kensington station upgrade
LCP Major Works Housing MW24-H£3bn framework estimate48 suppliers across housing works lotsHaringey's four geographical housing major-works appointments
LCP General Works MW25-GW£3bn framework estimate44 appointed suppliersA complete priced call-off ledger was not established in the records examined
GLA RE:FIT 5£1bn national framework estimateSix energy performance service providersCamden procurement activity identified, with a completed call-off award not established
Fusion21 Responsive Repairs and Void Property 2026–2030£350m UK-wide estimate announced by Fusion2172 suppliers, including regional specialistsRecently commenced; a complete call-off ledger was not established
Source: Find a Tender award notices and Fusion21's October 2026 announcement. The two national frameworks are not wholly attributable to London projects.

The framework records include the TfL award notice, Haringey's MW24-H housing framework and MW25-GW general works award, the RE:FIT 5 award and Fusion21's October 2026 supplier announcement. Each value describes the wider framework arrangement across its appointed supplier pool.

Haringey's £200m housing award can be traced to MW24-H

Haringey Council confirmed on 19 February 2026 that it had appointed four contractors to deliver its £570m Estate Renovation Plan, covering improvements across a council housing portfolio of approximately 20,000 homes. Equans Regeneration was appointed to the western area, United Infrastructure to central neighbourhoods, Hugh LS McConnell to the eastern southern area and Mulalley & Co to the eastern northern area.

Haringey Estate Renovation Plan delivery partners
AreaAppointed contractor
Western areaEquans Regeneration
Central neighbourhoodsUnited Infrastructure
Eastern southern areaHugh LS McConnell
Eastern northern areaMulalley & Co
Source: Haringey Council announcement, 19 February 2026. Procured by mini-competition through Lot 2.3 of the MW24-H Housing Framework.

The council's official announcement identifies the procurement route as a mini-competition through Lot 2.3 of the London Construction Programme MW24-H Housing Framework. That framework was awarded in October 2024 and carries a published estimated value of £3bn across its supplier pool and potential users.

United Infrastructure separately announced on 3 March 2026 that its central-area housing major-works contract was worth £200m. The contractor said its work would cover more than 5,000 homes in areas including West Green, Noel Park, Woodside and Bounds Green, with programmes involving whole-home improvements, fire safety, building services, decarbonisation and cyclical refurbishment.

The £200m is the value reported by the appointed contractor for its housing major-works arrangement. It is not the £3bn parent framework estimate and does not establish how much Haringey has paid for completed work. The council's £570m Estate Renovation Plan is another financial measure, covering the wider housing investment programme rather than United Infrastructure's individual appointment.

The procurement identifier is important here. Haringey's separate MW25-GW General Works Framework was awarded later, with 44 appointed firms, but it is not the framework named by the council for the four housing major-works appointments. Assigning the £200m contract to MW25-GW would put a genuine award against the wrong parent procurement and distort any subsequent call-off analysis.

TfL's two published project values include work still to be instructed

Transport for London's Infrastructure Improvement Framework provides a second example of why the wording inside an award notice matters. Awarded to Amey Rail, Costain and Dragados in 2026, the framework has an estimated value of £700m excluding VAT and supports infrastructure enhancement projects through early contractor involvement and staged design-and-build arrangements.

Docklands Light Railway Limited's 28 October 2026 notice names Amey Rail for the DLR Thamesmead Extension Early Works contract and publishes an estimated £41.8m value excluding VAT. The initial commitment, however, is limited to Stage 1.1, covering mobilisation, programme and risk review, definition of early works and survey scoping.

Later stages covering investigations and delivery of defined enabling works are subject to further approvals, affordability and instructions. LCM examined the scope in its earlier report, Amey Wins DLR Thamesmead Extension Early Works. The £41.8m published value includes anticipated later work and is not the amount already committed to physical construction.

London Underground Limited's 23 September 2026 South Kensington Station Capacity Upgrade notice similarly identifies Costain under the TfL framework, with a published estimated contract value of £85m excluding VAT. Its initial stage is detailed design under NEC3 ECC Main Option E, while the proposed construction stage would use Option C if instructed.

The South Kensington notice expressly says that the construction-stage price had not been agreed when the notice was published and that the £85m value included an estimate for the optional second stage. TfL's plans cover a new eastbound platform, an enlarged ticket hall, step-free access and station systems improvements, with the wider scheme targeted for completion in 2031.

Both notices identify real contractor selections and project scopes. Neither published headline value can be read as the full amount of construction work already instructed at the date of the initial award notice. For subcontractors, the next useful signal will be a confirmed instruction or package procurement covering the relevant physical works.

What each published figure records
FigureWhat it isWhat it does not show
£3bnMW24-H framework estimate across its supplier pool and potential usersWork awarded to any one contractor
£570mHaringey's Estate Renovation Plan, the wider housing investment programmeThe value of an individual appointment
£200mContract value reported by United Infrastructure for its central-area appointmentHow much Haringey has paid for completed work
£85mSouth Kensington published estimate, including the optional second stageAn agreed construction-stage price
£41.8mDLR Thamesmead early works published estimate, including anticipated later workThe amount committed; the initial commitment is Stage 1.1
£120.95mEnfield Meridian Water awarded contract valueAn audited expenditure outturn
Source: the notices, announcements and register entries cited in this article. All TfL and Enfield values as published; TfL values exclude VAT.

Enfield's Meridian Water register shows what a traceable call-off looks like

Enfield Council's historic Meridian Water Strategic Infrastructure Works Framework provides a useful comparison with the newer arrangements. The framework, reference DN372948, was awarded in March 2021 with an estimated value of £135m, and the council's contract register connects an individual works call-off to that parent reference.

The ProContract register entry records an award dated 1 December 2023, with both estimated and awarded values of £120.95m and a contract end date of 31 March 2026. It identifies Taylor Woodrow Infrastructure Limited as the awarded supplier and describes the contract as works called off from the Meridian Water framework.

The council's 2024 and 2025 committee contract listings also connect the overarching Meridian Water framework with subsequent works call-offs. The register therefore gives a more complete procurement trail than a framework announcement alone: a parent agreement, a named works contract, an awarded supplier, a published value and a contract period.

The £120.95m remains an awarded contract value. The cited record does not provide an audited expenditure outturn or confirm that every item of construction work had been completed by the contract end date. This historic example is included to demonstrate the distinction between the three forms of evidence, and is not part of the five currently operating frameworks compared above.

Why the complete spending figure is harder to establish

The Procurement Act 2023 introduced a wider series of contract notices for procurements commenced under the new regime from 24 February 2025. Its contract details notice guidance explains the publication requirements for qualifying contracts, including relevant call-offs.

Older frameworks established under the Public Contracts Regulations 2015 continue under transitional arrangements, and their call-offs follow the applicable earlier rules. Haringey's MW24-H framework and the GLA's RE:FIT 5 procurement originated under the previous regime, while TfL's Infrastructure Improvement Framework was procured under the Procurement Act 2023.

That difference affects which notices can be expected and how easily an outside researcher can connect a call-off to its parent framework. Even where the contract award is published, the record may not identify subsequent payments, approved variations or the stage of physical delivery. Missing call-off records cannot be counted as contracts that were never awarded.

The Greater London Authority has demonstrated another route to publication through its 18 September 2026 freedom of information response concerning the separate Architecture and Urbanism Framework. That response included a schedule of call-offs showing project titles, framework lots, appointed consultants and contract or fee values, although some requested fields were not held in the exact form sought. Comparable contract-level schedules would help establish the actual use of construction frameworks beyond their estimated maximum values.

Where contractors and specialists can look for the next packages

The five frameworks examined have appointed supplier pools. Contractors outside those pools cannot generally submit a direct bid for an ordinary call-off competition restricted to the appointed firms, although specialist subcontractors may seek packages through the relevant main contractor or service provider. The named delivery partners provide a starting point for identifying which businesses may control future subcontract procurement.

For Haringey housing refurbishment, the council has identified Equans Regeneration, United Infrastructure, Hugh LS McConnell and Mulalley as its geographical delivery partners. Contractors offering roofing, kitchens, bathrooms, electrical work, fire safety upgrades, façade improvements and retrofit services can examine those firms' supplier arrangements and published project requirements, subject to each contractor's commercial qualification process.

For TfL infrastructure, Amey Rail and Costain have been named in the Thamesmead and South Kensington notices, with Dragados holding a separate place on the parent framework. Specialist opportunities depend on the detailed scope eventually instructed, particularly where early contractor involvement must first resolve design, programme, funding or approval conditions.

The GLA's RE:FIT 5 programme has six appointed energy performance providers: Ameresco, Asset Plus Energy Performance, Dalkia Energy Services, Honeywell, SSE Energy Solutions and Vital Energi. Potential work includes heating, renewable energy, building fabric and energy efficiency improvements, with individual projects to be procured through the framework arrangements.

Fusion21's Responsive Repairs and Void Property Framework has 72 appointed suppliers, including Axis Europe, Cardo, Chigwell London, Equans Regeneration, Ian Williams, Mears, Mulalley and Wates Property Services. Fusion21 says 78% of the appointees are SMEs. Their appointments provide social landlords with a procurement route for repairs and void work, although individual project awards still need to be identified before they can be counted as secured workload.

Named delivery partners by framework
Framework or programmeNamed firms
Haringey housing major works (MW24-H)Equans Regeneration, United Infrastructure, Hugh LS McConnell, Mulalley
TfL Infrastructure Improvement FrameworkAmey Rail, Costain, Dragados
GLA RE:FIT 5Ameresco, Asset Plus Energy Performance, Dalkia Energy Services, Honeywell, SSE Energy Solutions, Vital Energi
Fusion21 Responsive Repairs and Void Property72 suppliers, including Axis Europe, Cardo, Chigwell London, Equans Regeneration, Ian Williams, Mears, Mulalley and Wates Property Services
Subcontract opportunities depend on each firm's own supplier arrangements and on the work eventually instructed.

One separate opportunity remains open to direct bidders. Fusion21's new £1bn Construction and Refurbishment Framework is being tendered for a planned 2027 commencement, and its submission deadline has been extended to noon on 22 January 2027. The procurement is separate from the already awarded £350m responsive repairs framework. LCM's report on the extended deadline explains the housing and non-domestic construction lots, London supplier positions, turnover thresholds and the revised timetable.

For housing contractors assessing the scale of potential maintenance work, LCM's separate investigation into England's £11.1bn social housing repairs forecast identifies live and planned procurement routes. The distinction is the same: forecast investment provides a measure of market demand, while a specific tender or awarded contract establishes the next procurement stage.

The next financial evidence required from the framework operators is a dated register of individual call-offs showing the buying authority, appointed supplier, contract value, VAT basis, parent-framework reference and award date, followed by expenditure figures linked to those contracts. Without that reconciliation, the published framework estimates cannot establish the amount of work already paid for or physically delivered.

How LCM checked the framework records
London Construction Magazine compared the award and procurement records for five London-relevant frameworks with individual TfL notices, Haringey Council's 19 February 2026 contractor announcement, United Infrastructure's 3 March 2026 contract statement and Enfield's Meridian Water contract register, using information available on 14 November 2026. The investigation records each published financial figure according to its stated meaning, distinguishing framework estimates, contractor-reported contract values, project notices containing optional stages and awarded contract values. No cross-framework spending total has been calculated because the identified records do not establish comparable committed values and VAT treatment for every call-off, and the review does not provide a complete register of all awards or expenditure under the five frameworks.