Procure Partnerships Framework is seeking contractor feedback on two proposed four-year agreements in England with a combined estimated value of £14bn. Contractors have until 3pm on Friday 15 January 2027 to complete the market engagement questionnaires for the £8bn National Construction Framework and the £6bn Civil Engineering & Infrastructure Framework. Both are targeted to start in October 2027.
For a London contractor, an £18m council refurbishment illustrates the change. If the council procures it as general building work, the proposal puts it in a sub-regional lot. If it procures an £18m standalone fit-out, the relevant lot is regional. If the council keeps the general building scope but raises the project value to £25m, that package also moves to a regional lot. A bid team needs two details before it can choose a lot: what the client intends to buy and the value of that package.
Tower cranes and scaffolding at a London construction site in November 2026. Photo: London Construction Magazine
The proposals in figures
£14bnCombined estimated value of the two proposed frameworks
£8bnNational Construction Framework
£6bnCivil Engineering & Infrastructure Framework
15 JanQuestionnaire deadline, 3pm, 2027
How the proposed lots divide the work
The National Construction Framework would cover general construction, fit-out and mechanical and electrical (M&E) works, with project values starting at £50,000. Under the lot structure reported on 23 November 2026, the geographical area expands with the value of a general construction project. Fit-out and M&E would each operate across nine regions.
Proposed lot structure
| Proposed workstream | Project value or scope | Geographical level |
|---|---|---|
| General construction | Lower bands up to £20m | Sub-regional lots |
| General construction | £20m to £40m band | Regional lots |
| General construction | Above £40m | North, Midlands or South |
| Fit-out and M&E | Separate specialist workstreams | Nine regions |
| Civil engineering and infrastructure | Lots up to £30m | 14 sub-regional areas |
| Higher-value civils | £30m to £50m and £50m-plus bands | North, Midlands or South |
Source: lot structure reported on 23 November 2026. Proposals are subject to market engagement.
The dedicated civils framework would cover five types of work: enabling works and demolition, highways and transport, water and flood defence including coastal infrastructure, utilities and energy including electrical infrastructure, and regeneration including brownfield and urban infrastructure. In the £18m London example, a separately procured enabling works and demolition contract would therefore point a contractor towards the civils questionnaire, reference DN836900. The general refurbishment and standalone fit-out examples both sit under construction reference DN836612.
The £18m London example: which lot?
| What the council buys | Package value | Proposed lot level | Questionnaire |
|---|---|---|---|
| General building refurbishment | £18m | Sub-regional | DN836612 |
| Standalone fit-out | £18m | Regional | DN836612 |
| General building refurbishment | £25m | Regional | DN836612 |
| Enabling works and demolition, procured separately | £18m | Civils framework | DN836900 |
Illustrative LCM example based on the published bands. Boundary cases at exactly £20m or £30m are not yet defined.
Two details are worth raising during engagement. For a scheme valued at exactly £20m or £30m, which side of the boundary applies and on what VAT basis? For a contractor delivering work across several London boroughs, which boroughs fall within each proposed sub-region? The published summary gives the broad bands. The detailed lot schedule will matter to firms making a decision at either boundary.
What smaller lots could change for regional contractors
Robbie Blackhurst, chief executive of Procure Partnerships Framework, linked the proposals to councils and combined authorities gaining greater control over local investment. His stated aim is to give regional contractors a more visible route to public work in the areas they serve, while retaining larger geographical lots for contractors capable of delivering the highest-value schemes.
For a regional builder, the practical question is how much territory it must be prepared to cover to compete for the size of job it normally delivers. A sub-regional lot could allow a firm to concentrate on an area it can serve from its existing teams and supply chain. The material reviewed by LCM on 23 November 2026 did not establish a registered-office requirement or an SME-only reservation. Those are separate eligibility questions for the procurement documents.
What Bromley's £9m office refurbishment shows
Churchill Court in Bromley provides a London example of how a lot turns into an identifiable construction contract. LCM checked Bromley Council's award notice (2023/S 000-033753), published on 15 November 2023. The council described the fit-out, refurbishment and adaptation of its civic offices as a further competition under Procure Partnerships' South East £4m to £12m lot. A London borough had used a lot carrying the South East label, a detail a contractor could easily miss if it searched for the word London alone.
Neilcott Construction delivered the works in phases under a JCT Design and Build contract. Procure Partnerships' Churchill Court project record puts the scheme at £9m. The £4m to £12m figure identifies the range of projects the lot could accommodate. The £9m figure describes the refurbishment delivered for Bromley.
Churchill Court, Bromley: lot against contract
| Item | What the record shows |
|---|---|
| Framework lot used | Procure Partnerships South East £4m to £12m |
| Scheme value | £9m |
| Works | Fit-out, refurbishment and adaptation of civic offices |
| Route | Further competition under the lot |
| Contractor and contract | Neilcott Construction; JCT Design and Build, delivered in phases |
| Award notice | 2023/S 000-033753 published 15 November 2023 |
Sources: Find a Tender and Procure Partnerships project record. The lot range is capacity; the £9m is the delivered scheme.
The same distinction applies to the proposed £14bn arrangements. The £8bn and £6bn estimates cover potential procurement across the two frameworks over four years. Individual clients would award the works through call-offs, the contracts placed under a framework. The announced proposals allow for direct award and single-stage or two-stage competition, with NEC and JCT forms available. LCM's analysis of London framework appointments and individual call-off awards shows where contractors can look for evidence that a particular project has reached that stage.
How to respond before 15 January 2027
Contractors can use the Current Opportunities section of The Chest procurement portal and search for the reference matching their work. The action requested by 3pm on Friday 15 January 2027 is a market engagement questionnaire. The two online sessions follow that deadline, so firms wishing to respond should complete the relevant questionnaire before the presentations take place.
For general construction, fit-out or M&E, use DN836612, National Construction Framework. Its online engagement session is scheduled for 11am on Tuesday 26 January 2027.
For enabling works, demolition or the other civils workstreams, use DN836900, Civil Engineering & Infrastructure Framework. Its online engagement session is scheduled for 11am on Tuesday 2 February 2027.
Which questionnaire to use
| Framework | Estimated value | Covers | Reference | Online session |
|---|---|---|---|---|
| National Construction Framework | £8bn | General construction, fit-out and M&E, from £50,000 | DN836612 | 11am, Tuesday 26 January 2027 |
| Civil Engineering & Infrastructure Framework | £6bn | Enabling works and demolition, highways and transport, water and flood defence, utilities and energy, regeneration | DN836900 | 11am, Tuesday 2 February 2027 |
Source: Procure Partnerships Framework market engagement, via The Chest. Both agreements are proposed for four years in England.
Key dates for contractors
Market engagement timeline
23 November 2026Proposed lot structure reported
Friday 15 January 2027, 3pmDeadline for both market engagement questionnaires
Tuesday 26 January 2027, 11amOnline session: National Construction Framework
Tuesday 2 February 2027, 11amOnline session: Civil Engineering & Infrastructure Framework
October 2027Targeted start for both frameworks
Source: Procure Partnerships Framework market engagement.
Method and Sources
LCM reviewed the proposed lot structure as reported on 23 November 2026 and the market engagement references DN836612 and DN836900 on The Chest. The Churchill Court example was checked against Bromley Council’s award notice (2023/S 000-033753) and Procure Partnerships’ project record.
The £8bn and £6bn figures are estimated framework values over four years, not committed spending or guaranteed work. The £18m London scenarios are illustrative. The material reviewed did not establish a registered-office requirement or an SME-only reservation, and the lot boundaries remain subject to the final procurement documents.