Royal Gateway: What 'No Remediation' Means for Building Safety

Housing secretary Angela Rayner ordered an urgent government review on 24 November 2026 of Galliard buildings previously assessed by the developer as not needing remediation, following the evacuation of five residential buildings at Royal Gateway in Canning Town, east London. The written ministerial statement directs officials to review those earlier assessments; it does not report structural defects in other Galliard developments.

The decision raises a broader question for England's building owners, developers and construction professionals: what has actually been checked when a building is described as requiring no remediation? Under the government's developer remediation contract, the central test concerns life-critical fire-safety defects. The Building Safety Act regime for occupied higher-risk buildings separately requires fire-spread and structural-failure risks to be assessed and managed.

London Construction Magazine reported the first Royal Gateway evacuation on 26 October 2026. Since then, Newham Council has served dangerous-structure notices on all five buildings, and ministers have directed a review of Galliard's other no-remediation decisions. The important distinction is between the scope of an earlier assessment, the condition of the structure and the different legal powers used when a danger emerges.

Housing secretary Angela Rayner ordered the review of Galliard's no-remediation assessments on 24 November 2026. Image: Angela Rayner via X

Royal Gateway and the rules in figures
5Royal Gateway buildings under Newham dangerous-structure notices
7Categories of required action listed in both notice summaries
11 metresMinimum height for buildings covered by the developer remediation contract
18 metresOr seven storeys: the occupied higher-risk building threshold
Sources: Newham Council notice summaries, MHCLG developer remediation contract guidance and BSR accountable-person guidance. Higher-risk buildings also need at least two residential units.

Four different checks, four different purposes

The Royal Gateway case brings together statutory duties and industry guidance that answer different questions. None of the routes below is an all-purpose certificate of structural safety.

What each check is for
RouteMain questionWhat the record must establish
Developer remediation contractAre qualifying life-critical fire-safety defects present?The buildings, defects and fire-safety assessment covered by the developer's decision.
Building Safety Act safety caseHow are fire spread and structural failure risks being managed during occupation?The building-specific risk assessment, evidence and measures kept under review.
Dangerous-structure enforcementDoes the structure present a danger requiring immediate statutory action?The danger identified and the protective, investigative and remedial actions required.
IStructE engineering guidanceWhat competent technical appraisal is appropriate for a transfer slab?Design assumptions, condition, load paths and assessment method. Not statutory sign-off
Source: LCM comparison of the guidance and legislation linked in this article. Duties and powers are described for England; building control, occupied-building safety regimes and emergency structural powers differ elsewhere in the United Kingdom.

What the developer remediation contract covers

The government's guidance on the developer remediation contract explains that participating developers must identify and address qualifying life-critical fire-safety defects in relevant residential buildings in England at least 11 metres high, developed or refurbished within the contract's defined period of 30 years ending on 4 April 2022. Its defect definition relates to fire-safety risk arising from design, construction or refurbishment. Galliard Group Limited is listed among the developers that signed the contract.

A finding that no work is required under that contractual test says what was concluded for defects within its scope. It should not be presented as proof that a reinforced concrete transfer slab has been reassessed for structural capacity. Equally, it would be premature to claim that Galliard's earlier assessments omitted structural checks: the 24 November ministerial statement does not publish the methods or evidence behind them. LCM has separately examined the liability questions raised by transfer-slab defects and construction disputes.

The structural duty continues during occupation

In England, the Building Safety Regulator's accountable-person guidance applies to occupied higher-risk residential buildings with at least seven storeys or a height of 18 metres and at least two residential units. Accountable persons assess and manage risks from fire spread and structural failure; the principal accountable person must prepare and maintain a safety case report and coordinate the relevant information across the building.

The legislation is unusually explicit about what happens when somebody decides a structural investigation is unnecessary. Paragraph 24 of Schedule 1 to the Higher-Risk Buildings (Keeping and Provision of Information etc.) (England) Regulations 2024 includes both structural-risk assessment reports and statements giving assurance that an assessment is not needed among the prescribed golden-thread documents. That does not order the same intrusive investigation at every building. It requires the reasoning and the evidence trail to be retained where those documents exist.

What the golden thread must keep. Under paragraph 24, a statement that a structural risk assessment is not necessary is itself a prescribed document, alongside any report that evaluates structural risks. A "no assessment needed" decision therefore has to leave its own record.

The safety case is an ongoing responsibility, not a one-off examination completed when a building is registered. The BSR guidance on safety case reports requires an explanation of the hazards identified, how risks were assessed and the measures used to manage them. A managing agent can undertake work for an accountable person, but the statutory accountability remains with the party identified under the Act.

Transfer slabs: a risk to assess proportionately

Transfer slabs carry loads between different column arrangements, often where flats stand above commercial space or parking. The BSR warning of 19 December 2025 raised concerns about punching shear in some historic designs, but said the presence of a transfer slab alone should not cause residents to be moved out. Its subsequent guidance for principal accountable persons says most transfer slabs are likely to be adequate.

Building owners are advised to identify whether transfer slabs exist, investigate signs of movement and obtain suitable professional advice where defects or design concerns arise. The regulator also identifies changed loading, new service openings and intrusive drilling as matters that can affect slab capacity. Before work that could weaken a transfer slab proceeds, its advice is to have proposals checked by a competent structural engineer.

What the BSR asks owners to do about transfer slabs
StepBSR advice to principal accountable persons
IdentifyEstablish whether the building has a transfer slab, with professional help if unsure
WatchLook for signs of movement; seek urgent advice if cracks grow or new cracks appear
InvestigateObtain suitable professional advice where defects, design concerns or resident reports arise
Control changeTreat changed loading, new service openings and intrusive drilling as risks to slab capacity
Check firstHave proposals checked by a competent structural engineer before work proceeds
Source: BSR transfer-slab guidance for principal accountable persons.

The Institution of Structural Engineers published design guidance in November 2024 and followed it with July 2026 material on the design and assessment of reinforced concrete transfer slabs. These publications give structural engineers more specific technical reference points than a general assurance that a building is sound. Cracking or deflection requires investigation, but observed distress does not establish that punching shear has occurred or determine the permanent repair design.

What Newham required at Royal Gateway

Newham Council arranged dangerous-structure notices for Centurion Tower, Sovereign Tower and St Vincent Court on 29 October 2026. A further set for Thanet Tower and Prince Court followed on 5 November 2026. The notices were issued under the London Building Acts (Amendment) Act 1939, which provides a specific dangerous-structure enforcement route in London.

LCM's comparison of Newham's two published notice summaries found the same seven categories of required action in both groups. The summaries do not give the building-by-building engineering findings or show that identical defects were found in every block.

Seven categories of required action in Newham's notice summaries
CategoryNorthern three, 29 OctoberSouthern two, 5 November
Immediate temporary works and risk mitigationListedListed
Structural monitoring and investigationListedListed
Comprehensive appraisal and materials investigationListedListed
Structural safety report and remedial worksListedListed
Independent external peer reviewListedListed
Continuing enforcement responsibilitiesListedListed
General measures to protect residents and the publicListedListed
Source: LCM comparison of Newham Council's published notice summaries, reviewed on 27 November 2026. Northern three: Centurion Tower, Sovereign Tower and St Vincent Court. Southern two: Thanet Tower and Prince Court.

These notices are concerned with the condition of the buildings and the actions necessary to assess or remove danger. They are distinct from BSR safety-case duties, the developer remediation contract and any eventual civil claim over design or construction responsibility. Newham's resident updates say the notices remained in force and that investigations were continuing.

What the wider government review will need to establish

The central question from the 24 November ministerial statement is what Galliard assessed when it decided particular buildings did not need remediation. For a useful assurance exercise, that requires an identifiable list of buildings, the original decision criteria, the underlying reports and a record of who reviewed the conclusions. Separate structural evidence would be necessary to determine whether transfer-slab risks were examined.

For other developers and building owners, the same documentary distinction is relevant. A fire-remediation decision should be filed with its stated purpose and limits. The occupied-building safety case must have its own competent evaluation of structural risk, informed by the building's drawings, alteration history, condition and any specialist investigation warranted by the evidence. A local authority dangerous-structure notice may then impose immediate requirements if a particular building is certified dangerous.

The ministerial statement confirms that technical investigations at Royal Gateway were continuing as of 24 November 2026. It did not publish a list of buildings in Galliard's wider review, a methodology or a completion timetable. Nor did it announce a finding that other Galliard buildings were structurally defective.

Key dates

Transfer slabs and Royal Gateway timeline
4 November 2024IStructE publishes design guidance on reinforced concrete transfer slabs
19 December 2025BSR warns of potential punching-shear risks in some historic transfer-slab designs
July 2026IStructE publishes material on the design and assessment of reinforced concrete transfer slabs
26 October 2026LCM reports the first Royal Gateway evacuation
29 October 2026Newham notices for Centurion Tower, Sovereign Tower and St Vincent Court
5 November 2026Newham notices for Thanet Tower and Prince Court
24 November 2026Housing secretary orders a review of Galliard's no-remediation assessments
Sources: IStructE, BSR, Newham Council and UK Parliament.

Method and Sources

London Construction Magazine reviewed the published Newham Council summaries for the northern three buildings, dated 29 October 2026, and the southern two, dated 5 November 2026, on 27 November 2026. Each summary lists seven categories of required action; LCM matched those headings across the two documents and compared the notice dates, which are seven calendar days apart.

The published summaries are not the full underlying engineering reports or individually served notices. The four-route comparison is LCM's reading of the linked legislation and guidance for England. This article is general information, not legal or engineering advice.