Construction-product evidence needs to connect the specified performance to the exact product delivered and the way it will be installed. For London refurbishment and higher-risk building projects, the useful question is whether the documentation supports the proposed application, including its interfaces with adjoining construction.
The government's Construction Products Reform White Paper, published on 25 February 2026, proposes changes to the product regulatory regime. Its September 2026 Grenfell progress report said consultation responses were being considered and legislation for a general safety requirement would be brought forward when Parliamentary time allowed. Those proposals should be kept separate from the requirements already applying to building work.
Construction workers on scaffolding outside a London building, photographed in October 2026. The photograph illustrates installation work on site; the workers, companies and site pictured have no identified connection to the product-evidence matters discussed in this article. Photo: London Construction Magazine
Product evidence in brief
25 Feb 2026Construction Products Reform White Paper published
Sep 2026Government progress report: consultation responses being considered
5Product categories in LCM's illustrative review matrix
3Classes of change on a higher-risk building project: recordable, notifiable and major
Sources: government White Paper and September 2026 progress report; Building Safety Regulator change guidance.
Proposed reform or current requirement?
| Measure | Status |
|---|---|
| Construction Products Reform White Paper, 25 February 2026 | Proposals; consultation responses being considered |
| General safety requirement for construction products | Legislation to be brought forward when Parliamentary time allows |
| Approved Document 7 on materials and workmanship | Current guidance under England's Building Regulations |
| CE and UKCA marking | CE marking continues to be recognised; UKCA marking can also be used |
| Change control on Building Safety Regulator-approved projects | Already applies, including a change log submitted with the completion-certificate application |
Source: government guidance and the September 2026 progress report cited in this article.
Start with the application the evidence must support
Approved Document 7 provides guidance on materials and workmanship under England's Building Regulations. Product information needs to be assessed against the work being designed: the material, its intended function and the conditions in which it will be used.
Government guidance on construction products in Great Britain confirms that CE marking continues to be recognised and that UKCA marking can also be used. The applicable marking and declaration route depends on the product. A procurement checklist should establish that route before requesting documents that may not apply to the category.
LCM recommends recording the manufacturer's name, product designation, relevant variant and document revisions against the specification. A declaration of performance, test report, classification report and installation instruction answer different questions. The reviewer should identify which documents establish the required characteristics and whether their scope includes the proposed arrangement.
What to record against the specification
| Item | Purpose |
|---|---|
| Manufacturer's name | Identifies who made the product |
| Product designation | Identifies the exact product |
| Relevant variant | Confirms the version specified is the version supplied |
| Document revisions | Shows which issue of each document was reviewed |
A declaration of performance, test report, classification report and installation instruction each answer a different question.
Five product categories to test against the specification
The following matrix is an illustrative review aid for a hypothetical refurbishment. It records questions a competent designer or specialist may need to resolve; it is not a finding that any named product is defective or a universal statutory document list.
Five product categories to test against the specification
| Product category | Evidence to examine | Application question |
|---|---|---|
| Fire-resisting doorset | Relevant performance evidence, permitted configurations and installation instructions for the identified doorset. | Does the evidence cover the proposed leaf, frame, hardware, seals, dimensions and supporting construction? |
| Penetration fire-stopping system | System-specific test or classification evidence, scope limitations and installation detail. | Are the service type, opening, substrate, support arrangement and seal configuration covered? |
| Insulation | Applicable declarations, declared thermal and fire characteristics, product identification and intended-use information. | Does the specified variant suit the proposed location and assembly, including applicable restrictions? |
| Post-installed anchor | Relevant assessment and design data, installation instructions and project selection calculations. | Do the substrate, loading, embedment, spacing and installation conditions match the design assumptions? |
| Structural repair mortar | Applicable performance declaration, intended-use information and preparation, application and curing instructions. | Is the material suitable for the repair function, substrate condition and proposed application thickness? |
An illustrative review aid for a hypothetical refurbishment, not a finding about any named product or a universal statutory document list.
For each category, record the unresolved question precisely. Missing evidence may mean the team cannot yet verify the proposed use. It should trigger a documented technical response before the affected installation is released.
Assess substitutions through the project change process
For projects approved by the Building Safety Regulator, changes affecting the agreed documents must follow the applicable change-control process. BSR's guidance on higher-risk building changes requires controlled changes to be assessed and recorded.
The guidance distinguishes recordable, notifiable and major changes. Notifiable changes must be submitted before the related work starts; major changes require approval before the affected work proceeds. Classification needs to consider the whole change, including its effect on fire performance and the agreed design.
Classes of change on a higher-risk building project
| Class | What the guidance requires |
|---|---|
| Recordable | Assessed and recorded |
| Notifiable | Submitted before the related work starts |
| Major | Approved before the affected work proceeds |
Source: Building Safety Regulator guidance on higher-risk building changes. Classification considers the whole change, including its effect on fire performance.
A supplier's description of a replacement as equivalent should therefore be supported by a comparison against the actual specification. Record the reason for substitution, evidence reviewed, technical advice and decision. LCM's inspection and test plan guidance examines how documentary checks can be connected to defined hold points on site.
Keep the delivered product linked to its installation
The proposed evidence workflow should continue through delivery and installation. Retain the product identifiers needed to connect deliveries with accepted submissions, then record the installed location and relevant inspection results. Where batch, expiry or storage conditions affect suitability, include those checks in the package inspection arrangements.
Photographs can support an installation record, but the record also needs to identify what was checked and against which detail. Concealed work needs an inspection opportunity before closure. Departures from the accepted arrangement should be referred through the project's technical and change-control procedures.
From submission to installed record
SubmissionEvidence accepted against the specification
Substitution, if anyReason, evidence reviewed, technical advice and decision recorded through change control
DeliveryProduct identifiers retained; batch, expiry and storage conditions checked where they affect suitability
InstallationInstalled location recorded against the accepted detail
InspectionResults recorded; concealed work inspected before closure
CompletionChange log maintained for submission with the completion-certificate application
The government's September 2026 progress report identified further legislation as part of the product-reform programme. For BSR-approved projects, the existing change-control requirements already require the principal contractor to maintain a change log for submission with the completion-certificate application.