Warm Homes Retrofit: 20,050 Measures Outside Published Totals

England’s Warm Homes: Social Housing Fund recorded 32,250 energy-efficiency measures installed across 16,390 homes by the end of October 2026, while the TrustMark data warehouse held approximately 52,300 measure lodgements covering 26,000 households. The figures, published by the Department for Energy Security and Net Zero (DESNZ) on 26 November 2026, leave a difference of 20,050 measures between the two reporting systems, according to London Construction Magazine calculations.

The difference arises because installations can be lodged with TrustMark before the corresponding grant recipient records have been submitted, linked and validated for publication. The latest statistics also introduce local-authority delivery tables for the first time, allowing construction businesses and housing providers to examine reported retrofit activity geographically. London has a further complication: its separate £58.7m social housing retrofit allocation through the Integrated Settlement is excluded from this national statistical release.

Residential development and construction activity in Woolwich, southeast London, photographed in April 2026. The image illustrates London’s wider housing and building improvement sector as new government figures provide further detail on social housing energy-efficiency installations. Photo: London Construction Magazine

Warm Homes: Social Housing Fund in figures
32,250Measures in the published DESNZ statistics, across 16,390 homes
52,300Measure lodgements held in the TrustMark data warehouse
20,050Difference between the two reporting systems, calculated by LCM
£58.7mLondon’s separate retrofit allocation, excluded from the national release
Sources: DESNZ Warm Homes: Social Housing Fund statistics, 26 November 2026, to the end of October 2026; GLA Mayoral Decision MD3531. Source totals are rounded.

32,250 measures appear in the official statistics

The DESNZ statistical release of 26 November 2026 covers work delivered under the Warm Homes: Social Housing Fund (WH:SHF), previously known as Social Housing Decarbonisation Fund Wave 3. The programme provides grant funding to local authorities, housing associations and other eligible social housing providers for insulation, low-carbon heating and energy-efficiency improvements.

The department received returns from 103 of the programme’s 138 participating grant recipients by mid-November 2026, reporting installations to the end of October 2026. The validated records contain approximately 32,250 installed measures across 16,390 households, equivalent to an average of 1.97 reported measures per upgraded home, calculated by LCM.

Grant recipients report delivery through the Grant Reporting System, with records linked to TrustMark installation lodgements. The department uses these linked records to produce its published statistics after processing and validation. A measure recorded in TrustMark may already have been installed even where the corresponding grant reporting has not yet passed through that process.

The 20,050-measure reporting difference

The TrustMark warehouse contained approximately 52,300 Warm Homes: Social Housing Fund measure lodgements covering 26,000 households at the end of October 2026. Comparing those figures with the DESNZ validated statistics produces two differences: 20,050 measures and 9,610 households. The published measure count was equivalent to approximately 61.7% of the TrustMark total, while the published household count was equivalent to 63.0% of the corresponding TrustMark figure.

Published statistics against TrustMark lodgements
Reporting measureDESNZ published statisticsTrustMark lodgementsDifferencePublished as share of TrustMark
Measures recorded32,25052,30020,05061.7%
Households covered16,39026,0009,61063.0%
Source: DESNZ, Warm Homes: Social Housing Fund statistics, November 2026. Differences and shares are LCM calculations from rounded source totals.

The difference is a measure of the reporting and validation position, not a count of defective installations, unfinished work or failed inspections. DESNZ says grant recipient returns can arrive after the statistical cut-off, while some records require additional matching or validation. The department expects early published figures to be revised as more records are processed.

For housing providers commissioning refurbishment work, the distinction affects how programme progress is monitored. Contractor completion records, TrustMark lodgements and published government statistics each serve different reporting functions. A landlord reviewing delivery should be able to reconcile its installed measures with the grant reporting records and the evidence supporting individual installations.

Solar PV accounts for 38% of installed measures

Solar photovoltaic systems accounted for 38% of the installed measures in the validated Warm Homes: Social Housing Fund records to the end of October 2026, according to DESNZ. Loft insulation accounted for 28% and cavity wall insulation for 8%. Together, these categories represented approximately 74% of the reported measures.

Installed measures by type
Measure typeShare of validated installed measures
Solar photovoltaic systems38%
Loft insulation28%
Cavity wall insulation8%
These three categories togetherApproximately 74%
Source: DESNZ, Warm Homes: Social Housing Fund statistics, November 2026. The combined figure is an LCM calculation. Shares are of measures, not of homes.

The distribution is relevant to contractors working across roofing, electrical installations, insulation and domestic energy improvements. Solar PV installation can involve roof condition assessments, electrical design, safe access and commissioning. Insulation work requires an appropriate assessment of existing construction, ventilation and moisture risks, along with records showing the installed system and any associated work.

The measure percentages do not describe the proportion of homes receiving each technology. One dwelling may receive several upgrades, and the department’s figures count individual measures as well as households. The average of 1.97 validated measures per upgraded household reflects that distinction.

The construction implications of the wider electrification programme were examined in London Construction Magazine’s analysis of the November 2026 electrification roadmap, including the relationship between building fabric improvements, solar generation, low-carbon heating and the technical standards applying to construction work.

New local-authority tables allow closer delivery scrutiny

DESNZ introduced three geographical tables in the 26 November 2026 publication covering delivery by parliamentary constituency, English local authority and combined authority. Table 5 provides local-authority-level figures for households with reported measures installed, creating a more detailed basis for examining where validated programme delivery has occurred.

The new tables can be obtained from the official November 2026 data workbook. They allow London borough records to be examined alongside the rest of England using a consistent publication, rather than relying solely on regional totals or separate announcements from individual housing providers.

However, an absolute count of upgraded households is not a measure of the proportion of a borough’s social housing stock improved. Boroughs differ in the size and condition of their housing portfolios, the number of participating landlords and the amount of work undertaken through other funding arrangements. A meaningful performance comparison needs the relevant housing stock denominator and a consistent definition of programme coverage.

The department also says its statistics do not provide grant-recipient-level performance information. This limits what can be concluded about an individual housing association or council-led delivery programme from the national publication. A borough total cannot establish the number of properties already surveyed, awaiting installation or requiring further quality checks.

London’s £58.7m programme sits outside the national count

London has a separate £58.7m capital allocation for social housing retrofit through the government’s Integrated Settlement. Greater London Authority Mayoral Decision MD3531, published on 24 September 2026, approved arrangements for the Mayor’s Home Energy Saving Fund, with a target of upgrading 5,000 additional social homes to Energy Performance Certificate band C or above by 2029.

The DESNZ statistical release explicitly excludes delivery funded through Integrated Settlement arrangements. Consequently, the new local-authority tables cannot be read as a complete account of retrofit activity across London’s funded programmes. The £58.7m is a capital funding allocation, not a construction contract award or evidence that 5,000 homes have already been improved.

The GLA decision records the planned funding allocation process beginning on 1 November 2026, with awards scheduled to be completed by 15 January 2027. The delivery end date is 1 April 2029. It also anticipates limited delivery during 2026-27 while recipients secure match funding and arrange mobilisation, including work alongside existing Warm Homes: Social Housing Fund schemes.

This creates two reporting streams relevant to London contractors: retrofit installations recorded in the national Warm Homes: Social Housing Fund statistics and additional projects financed through the Mayor’s Integrated Settlement allocation. The underlying grant awards, housing provider procurement exercises and installation records will determine when the second stream turns into identifiable work packages.

LCM previously reported the capital allocation and its relationship with the separate Warm Homes: Local Grant programme in What the Electrification Roadmap Means for London Construction Standards. The two London funding streams have different eligibility and delivery arrangements, and their budgets cannot be combined as though they were a single construction contract.

Where the retrofit work reaches contractors

For specialist subcontractors, the Warm Homes: Social Housing Fund involves work that may be procured by participating councils, housing associations or their appointed delivery partners. The national statistics identify the type and volume of reported installations, but individual commercial opportunities depend on the procurement arrangements of the organisation commissioning each programme.

A contractor seeking roofing, solar PV, insulation or electrical work should establish which housing provider is responsible for the relevant stock, whether it has an existing framework or appointed delivery contractor, and whether specialist packages are being procured separately. The published measure totals establish completed reported activity; they do not identify live tender deadlines or unlet packages.

The contractual scope also matters for quality assurance. Evidence of a physical installation, the TrustMark lodgement and the documentation required by the funding scheme must be reconciled before a programme can be accurately reported. That includes the installation date, property reference, measure type and the relevant grant recipient’s records, as well as any inspection or commissioning evidence required for the specific works.

The Government’s wider funding position changed in October 2026, when Budget 2026 reduced the Warm Homes Plan’s capital grant provision by £1bn while saying that most support for low-income households and social housing would be protected. LCM examined the distinction in Budget 2026 Cuts £1bn From Warm Homes Capital Grant. The November statistics record delivery under the existing scheme and do not establish the value of future specialist work packages.

The next delivery figures are due in February 2027

DESNZ has scheduled the next Warm Homes: Social Housing Fund statistical release for 25 February 2027. The November 2026 publication covers returns from 103 of 138 participating grant recipients and includes installations reported to the end of October 2026, with the latest reporting month subject to further revisions.

For London, the next useful comparison will be between revised local-authority delivery totals, additional TrustMark records entering the validated statistics and the separate Integrated Settlement programme’s funding awards scheduled for January 2027. The GLA’s decision sets 1 April 2029 as the delivery end date for its £58.7m programme.

Key dates for the two reporting streams
24 September 2026GLA publishes Mayoral Decision MD3531 on London’s £58.7m Integrated Settlement allocation
End of October 2026Cut-off for installations reported in the latest national statistics
1 November 2026Planned start of the GLA funding allocation process
26 November 2026DESNZ publishes the Warm Homes: Social Housing Fund statistics, with new local-authority tables
15 January 2027GLA funding awards scheduled to be completed
25 February 2027Next national statistical release
1 April 2029Delivery end date for the London programme
Sources: DESNZ; Greater London Authority, MD3531.

Method and Sources

London Construction Magazine compared the DESNZ Warm Homes: Social Housing Fund statistics published on 26 November 2026, using reporting to the end of October 2026 and source information checked on 29 November 2026. Subtracting 32,250 validated measures from approximately 52,300 TrustMark lodgements produces a difference of 20,050 measures; subtracting 16,390 validated households from approximately 26,000 TrustMark households produces 9,610. The validated counts equal approximately 61.7% and 63.0% of the corresponding TrustMark totals, while 32,250 measures divided by 16,390 households gives an average of 1.97 measures per upgraded home. The source totals are rounded, so the calculated differences are approximate.