London’s construction market produced major contract, regeneration and infrastructure announcements during November 2026, but London Construction Magazine’s examination of the underlying records shows that the largest financial figures often concerned long-term development arrangements, revisions to existing contracts or future procurement capacity. Meanwhile, official housing statistics confirmed a sharp fall in the capital’s delivered homes, and a London Assembly investigation cited government data showing that annual new-build housing starts had halved compared with 2022-23.
The month’s most consequential developments included a £2.705bn land and development arrangement at Thameside West in the Royal Docks, North London Waste Authority’s decision to revise its Edmonton energy recovery construction contract to £1.25bn, a £30.9m main works award for affordable housing in Tower Hamlets and further progress on HS2’s tunnels towards Euston. Commercial refurbishment packages also advanced in Westminster and Holborn, while updated Building Safety Regulator statistics showed improving approval performance alongside continued programme and capacity pressures.
Central London’s skyline, photographed in October 2026. The image illustrates the capital’s construction and development activity as London Construction Magazine examines November’s major contracts, regeneration agreements, infrastructure projects and delivery pressures. Photo: London Construction Magazine
November 2026 in figures
49.9%Fall in London new-build housing starts, 2022-23 to 2025-26
87.9%London’s share of England’s fall in net additional dwellings
£450.7mIncrease in the Edmonton contract price, to £1.25bn
£30.9mAlbert Jacob House main works award decision, Tower Hamlets
Sources: MHCLG; London Assembly; North London Waste Authority; London Borough of Tower Hamlets notice on Find a Tender. Percentages and the Edmonton increase are LCM calculations.
The month in one line. November’s largest figures measured six different things: a 30-year land arrangement, a revised price on an existing contract, a whole-project cost, a skills budget, a specialist subcontract and one main works award decision. They cannot be added into a total of construction work won.
November’s largest financial figures tell different stories
London Construction Magazine compared the legal, procurement and construction stages behind the principal financial announcements recorded between 1 and 29 November 2026. The distinction changes how much immediate work each announcement represents. A long-term land arrangement can support future development without appointing a main contractor, while a revision to an existing construction contract changes the cost and delivery terms of work already under way.
Six published values and what each measures
Development
Published value
What it measures
Thameside West, Newham
£2.705bn
Long-term land and development arrangement value
Edmonton Energy Recovery Facility
£1.25bn
Revised price of an existing construction contract
London Museum, Smithfield
£437m
Reported overall museum transformation project value
London Construction Skills Package
£88.57m
Multi-year skills funding allocation, including indicative future funding
171 Victoria Street MEP works
£40m
Specialist design-and-build MEP subcontract
Albert Jacob House, Tower Hamlets
£30.91m excluding VAT
Main works contract award decision
Sources: GLA; North London Waste Authority; London Museum; Kane Group; London Borough of Tower Hamlets notice on Find a Tender. Classification by London Construction Magazine. The values are different financial measures and are not added together.
The £2.705bn Thameside West figure alone is greater than the other figures shown, but it relates to a development arrangement extending over approximately 30 years. The £1.25bn Edmonton figure is the total revised price of a contract originally awarded in 2022. Neither amount represents an equivalent volume of new construction contracts awarded during November 2026.
London housing starts fell by almost 50%
The London Assembly’s Getting London Building Again investigation, launched with a call for evidence on 20 November 2026, cites Ministry of Housing, Communities and Local Government data showing 10,860 new-build housing starts in the capital during 2025-26, compared with 21,660 in 2022-23. London Construction Magazine calculates a reduction of 10,800 starts, equivalent to 49.9% across the two financial years.
The Assembly’s Housing Committee also cited a draft London Plan annual housing target of 55,800 homes and an assessed annual requirement of 89,300 net new homes between 2026 and 2036. The figures use different definitions, so they cannot be treated as one interchangeable series, but they show the scale of the difference between London’s present construction activity and its stated housing ambitions.
Further evidence arrived on 26 November, when the Ministry of Housing, Communities and Local Government published its 2025-26 net additional dwellings statistics. London recorded 28,170 net additions, down from 32,680 in 2024-25. England’s corresponding total fell from a revised 208,820 to 203,690.
LCM calculates that London’s reduction of 4,510 net additional dwellings accounted for approximately 87.9% of England’s total annual decline of 5,130. The comparison uses published rounded figures. Net additions include changes in the dwelling stock from new building, conversions, changes of use and demolitions, while housing starts record an earlier construction stage. The MHCLG new-build starts series cited by the Assembly is also separate from the Greater London Authority’s Planning London Datahub starts records, which LCM examined in its analysis of London’s share of England’s housing fall; the two series use different collection methods and should not be mixed.
The November evidence therefore shows two separate problems for London’s housing pipeline: fewer homes entering construction and a reduction in the homes added to the dwelling stock. Neither measure identifies how many individual subcontract packages are currently available, which requires project-specific procurement and commencement records.
LCM Graph 1: London’s housing delivery divide
New-build housing starts
2022-2321,660
2025-2610,860
Down 10,800 starts, or 49.9%, across two financial years
Net additional dwellings
2024-2532,680
2025-2628,170
Down 4,510 homes, or 13.8%, in one year
Sources: MHCLG new-build starts as cited by the London Assembly Housing Committee, 20 November 2026; MHCLG net additional dwellings, 26 November 2026. The two panels use separate scales and different years because starts and net additions measure different things. Percentages are LCM calculations.
Thameside West advances through a land agreement
The Greater London Authority published Mayoral Decision MD3542 on 16 November 2026, approving changes to the land arrangements for the Thameside West regeneration site in the Royal Docks. The decision itself authorises £3.4m of GLA expenditure on the land arrangements. The associated contract award notice, published the same day, records a £2.705bn direct award involving GLA Land and Property Limited and Silvertown Homes Limited.
The development is intended to accommodate at least 5,000 homes on former industrial land in Newham. The revised arrangement provides for phased land transfers and development responsibilities, subject to contractual conditions and the approvals needed for individual phases. The underlying procurement carries identifier ocds-h6vhtk-07bd39.
A hybrid planning permission was granted in 2021 and subsequently implemented. Revised proposals for an initial phase of approximately 1,500 homes were submitted in September 2026. The November decision concerns the structure through which the landowners intend to proceed; individual construction phases will need their own technical approvals, delivery arrangements and contractor appointments. The Mayoral Decision records an aim to start on site in early 2028.
The distinction is commercially important. The land agreement gives a route for future development across the Royal Docks, but the estimated £2.705bn arrangement value cannot be placed into a November main-contract awards total. LCM previously examined the project alongside other November developments in its Royal Docks, Edmonton and Enfield construction review.
Edmonton contract reset puts delivery risk into focus
North London Waste Authority agreed revised construction terms with Acciona for the Energy Recovery Facility at Edmonton EcoPark on 12 November 2026. The authority’s published decision sets a revised contract price of £1.25bn and a new completion target of December 2029, with Acciona accepting additional risks previously held by the authority.
The original contract award notice, for a contract concluded on 24 January 2022, recorded a value of £799,339,566 excluding VAT, approximately £799.3m. LCM calculates that the revised price is around £450.7m higher, an increase of approximately 56.4% against that original award figure. The comparison measures a change in the total contract price over the project’s life, not additional work awarded to a new contractor during November.
NLWA reported that the facility was more than 60% complete and approximately £700m had already been spent. The authority attributed earlier problems to inflation, higher interest rates, material costs, labour shortages and difficulty obtaining skilled mechanical and electrical subcontractors for critical plant systems, including boilers and flue-gas treatment equipment.
The revised arrangement follows an improvement in reported site productivity, with more than 400 skilled workers on site each day compared with around 200 at the beginning of 2026. NLWA’s members also requested further detail on the construction and commissioning programme and on the financial assumptions behind the revised agreement. The project remains in active construction, making the contract reset one of the month’s clearest examples of how delivery pressures can alter an established programme.
LCM Graph 2: Edmonton contract reset, £m
2022 award£799.3m
Increase+£450.7m
2026 revised£1,250m
The increase is a change to the price of an existing contract, not a new award
Sources: North London Waste Authority contract award notice, January 2022 (£799,339,566 excluding VAT); NLWA announcement, November 2026 (£1.25bn). The £450.7m increase and 56.4% are LCM calculations.
Tower Hamlets records an affordable housing award
The London Borough of Tower Hamlets published a contract award notice on 13 November 2026 for HAR6107 Albert Jacob House Main Works, naming Sinden Construction Limited following an award decision on 12 November. The Find a Tender notice 2026/S 000-108184 records a contract value of £30,911,821 excluding VAT.
The Bethnal Green project comprises 53 affordable-rent homes and five retail units. It includes higher-risk building requirements under the Building Safety Act regime. The notice gives a prospective construction contract period running from 27 November 2026 to 27 November 2028. As a UK6 contract award notice, it records the award decision; entry into the contract is a separate procurement event.
Tower Hamlets also moved forward with preliminary market engagement for the proposed Augusta Street housing development in Poplar during November. The reported procurement estimate was approximately £58m for 100 social-rent homes across two buildings. The council’s prospective delivery programme remains dependent on the subsequent tender and award stages.
For construction businesses, the distinction between the two Tower Hamlets records is straightforward: Albert Jacob House had reached a main works award decision, while Augusta Street was being prepared for procurement. Neither announcement should be presented as an open specialist subcontract invitation without confirmation from the relevant buyer or appointed main contractor.
HS2 records physical progress towards Euston
HS2’s London programme provided some of November’s most direct evidence of work physically progressing. On 23 November 2026, HS2 Ltd confirmed that its two tunnel boring machines, Madeleine and Karen, had reached the halfway point on their approximately 4.5-mile journeys from Old Oak Common towards Euston. The machines are operated by the Skanska Costain STRABAG joint venture.
Separate HS2 construction logistics reporting in November described plans to transport up to 170,000 tonnes of excavated material by rail from the Euston site, potentially avoiding more than 10,000 HGV journeys. Approximately 35,000 tonnes had already been moved during trials between February and September 2026.
The figures describe physical tunnelling and excavation logistics, with measurable outputs and equipment already deployed. They give a different kind of market evidence from proposals still undergoing business-case development.
That earlier-stage activity was also visible in the West London Orbital railway proposals. On 2 November 2026, WSP announced its appointment to support TfL’s assessment of the proposed 18.5km route between Hounslow and Hendon, with Costain and Fereday Pollard contributing specialist expertise. The work covers technical and programme development, forecasting and constructability advice ahead of later decisions on funding, approvals and delivery.
London’s commercial construction market continued to produce identifiable specialist packages during November. On 23 November, Kane Group confirmed a £40m design-and-build MEP subcontract for the refurbishment of 171 Victoria Street, working with main contractor Sisk. The works include new building services for an all-electric office redevelopment, with retail units remaining operational during construction.
Kane plans to use prefabrication for parts of the building services installation. That provides a defined specialist work package, its value, appointed subcontractor and delivery method, in contrast to a development proposal that has reached planning or pre-construction only.
Also on 23 November, Permasteelisa Group announced its façade appointment at One Museum Street in Holborn. Working with Bovis, the specialist will design, engineer, manufacture and install 11,200 sq m of unitised façade and 1,200 sq m of stick-system façade on the development’s 19-storey office tower. The announcement identifies the scope without publishing a subcontract value.
November also brought a completed cultural development at Smithfield. London Museum’s 24 November announcement confirmed the transformation of the historic General Market ahead of its public opening on 28 November. The £437m overall project has been delivered through a partnership involving London Museum, the City of London Corporation and the Mayor of London. The adjacent Poultry Market is scheduled to open in 2028.
Building Safety Regulator decisions improve while capacity pressures remain
The Building Safety Regulator’s August-to-October 2026 application data reported a 95% approval rate for new-build Gateway 2 applications nationally, with data correct to 1 November. Its headline tables for August to October record 9,453 residential units approved in new higher-risk buildings and conversions and 9,956 in external remediation applications, which LCM adds to 19,409. London reached a 97% approval rate for new higher-risk buildings and conversions, with a reported 20-week median approval time for non-complex cases.
The improvement is substantial compared with earlier Gateway 2 reporting periods. It does not eliminate the programme requirements applying after approval, including start notifications, change control and completion certification. London Construction Magazine’s Gateway 2 Approval Index keeps these regulatory stages separate from construction commencements.
The month’s structural-safety concerns were particularly visible at Royal Gateway in Canning Town. A government statement issued on 24 November 2026 confirmed an urgent review and assurance exercise covering Galliard buildings previously assessed as not requiring remediation works. The announcement followed the evacuation of residents from five buildings affected by serious structural concerns. It did not establish defects at other Galliard developments.
The workforce dimension emerged in the government’s Planning Skills and Capacity Survey 2026, published on 25 November 2026, which found that 63% of responding London borough planning authorities reported difficulties recruiting building control staff, compared with 28% across England. Planning and regulatory capacity therefore remained a separate operational issue even as the BSR’s reported Gateway 2 approval rate improved.
Skills funding advances as national construction output remains weak
The GLA published Mayoral Decision MD3493 in November, recording an £88,565,712 London Construction Skills Package across 2025-26 to 2029-30. The total includes £54,369,619 within the 2026-29 Integrated Settlement and £8,747,990 indicated for 2029-30, subject to future Spending Review confirmation.
The allocation supports a longer-term training and workforce programme rather than a newly awarded construction contract. Its relevance to project delivery is reinforced by the specialist labour difficulties recorded at Edmonton and the building control recruitment pressures identified by MHCLG.
National economic data also argues against interpreting November’s London announcements as evidence of a general construction recovery. The Office for National Statistics release of 12 November showed that Great Britain construction output increased by 0.8% in September 2026 after four successive monthly declines, but output across Q3 2026 remained 0.7% below Q2.
Private new housing output fell by 4.7% during Q3, while the annual construction output price index increased by 3.2% in the 12 months to September. Those figures describe Great Britain, not Greater London, but they provide a consistent national reference for the weakness visible in London’s residential starts and the selective nature of its project announcements.
The November construction delivery record
The following LCM register separates selected November announcements according to the stage reached by 29 November 2026. It covers the most consequential records used in this analysis, with related announcements combined where they describe the same underlying development.
LCM November 2026 delivery record
Date
Development
Verified stage or announcement
2 Nov
West London Orbital
Technical and business-case support appointment
6 Nov
London Construction Skills Package
Multi-year funding decision published
12 Nov
Edmonton Energy Recovery Facility
Existing construction contract revision agreed
13 Nov
Albert Jacob House
Main works contract award notice published
16 Nov
Thameside West
Land and development arrangement notice
17 Nov
HS2 Euston excavation logistics
Rail-freight material removal programme announced
20 Nov
London Assembly housing inquiry
Construction starts evidence and scrutiny
23 Nov
HS2 Euston tunnels
Halfway excavation milestone confirmed
23 Nov
171 Victoria Street and One Museum Street
Two specialist construction package announcements
24 Nov
Royal Gateway, Newham
Government safety assurance review announced
24 Nov
London Museum, Smithfield
Completed General Market transformation announced
26 Nov
London housing supply
2025-26 net additions statistics published
27 Nov
Liberty Centre, Romford
Council planning committee approval announced
28 Nov
London Museum, Smithfield
General Market opened to the public
Source: London Construction Magazine register of selected records, 1 to 29 November 2026. Dates are publication or announcement dates. It is not an exhaustive census.
Havering Council’s 27 November announcement described its committee’s support for the Liberty Shopping Centre redevelopment, involving up to 900 homes and retail and public realm changes in Romford town centre. The decision advances the planning process, with subsequent statutory and delivery stages to follow.
Where November’s records point contractors towards 2027
The November evidence provides several different types of commercial signal for contractors. Active infrastructure works at Euston and Edmonton have established delivery teams and defined construction programmes. The Victoria Street and One Museum Street announcements identify specialist contractors and packages already awarded. Tower Hamlets has separate council housing projects at award and market-engagement stages, while Thameside West remains a longer-term phased development prospect.
For contractors tracking future opportunities, the useful next evidence is a published tender, confirmed specialist package invitation, contractual commencement, Gateway decision where required or construction-start record. LCM’s London Construction Intelligence Observatory records the distinction between project announcements, regulatory stages and delivery evidence across major London schemes.
The Office for National Statistics has scheduled its next construction output release for 11 December 2026, covering October activity and revisions to earlier estimates. The GLA’s Thameside West arrangements, Tower Hamlets’ procurement programme and NLWA’s revised Edmonton construction and commissioning schedule provide separate project-level records to examine as the 2027 pipeline develops.
Questions this review answers
How much did London housing starts fall?MHCLG data cited by the London Assembly Housing Committee shows 10,860 new-build housing starts in London in 2025-26, compared with 21,660 in 2022-23. LCM calculates a fall of 10,800 starts, or 49.9%.
What share of England’s housing supply fall was in London?London’s net additional dwellings fell by 4,510, from 32,680 in 2024-25 to 28,170 in 2025-26. England’s total fell by 5,130. LCM calculates that London accounted for approximately 87.9% of the national fall.
Is the £2.705bn Thameside West figure a construction contract?No. It is the value attributed to a long-term land and development arrangement between GLA Land and Property Limited and Silvertown Homes Limited for a site planned for at least 5,000 homes. Individual phases still need their own approvals and contractor appointments.
Why did the Edmonton Energy Recovery Facility contract rise to £1.25bn?North London Waste Authority agreed revised terms with Acciona, with a new completion target of December 2029. The original January 2022 award was £799,339,566 excluding VAT, so the revised price is about £450.7m, or 56.4%, higher. NLWA cited inflation, interest rates, material costs and labour shortages.
Which main works contract award was recorded in Tower Hamlets?A contract award notice published on 13 November 2026 names Sinden Construction Limited for HAR6107 Albert Jacob House Main Works in Bethnal Green, at £30,911,821 excluding VAT, for 53 affordable-rent homes and five retail units.
Method and Sources
London Construction Magazine reviewed primary procurement, government, regulator, public authority and contractor records on 29 November 2026. The London housing starts decline is calculated as (21,660 minus 10,860) divided by 21,660, giving 49.9%; the capital’s share of England’s net housing supply reduction is (32,680 minus 28,170) divided by (208,820 minus 203,690), giving 87.9%. The Edmonton contract comparison uses the original approximately £799.3m award and revised £1.25bn price, a difference of approximately £450.7m or 56.4%. The 19,409 residential units figure is the sum of two Building Safety Regulator categories, 9,453 and 9,956. The article covers 1-29 November and classifies the selected developments by their published stage; the records are not an exhaustive census of London construction activity, and different financial value types have not been aggregated.